About this file

This document is a specification section for the Demonstration and Training requirements of the Chicopee Armory Rehabilitation project in Chicopee, Massachusetts. The section covers the administrative and procedural requirements for instructing the Owner's personnel on the operation and maintenance of the systems, subsystems, and equipment installed as part of the project. Key details include the requirement for the Contractor to provide an instruction program with training modules for each system and piece of equipment, including instruction on the basis of system design, documentation, emergencies, operations, adjustments, troubleshooting, and maintenance. The Contractor is also required to provide demonstration and training video recordings, as well as a training manual, to be submitted at the completion of the training.

The related state and local contract opportunity is for the Chicopee Armory Renovations sub-contractor bids, located in the state of Massachusetts. The document does not provide any additional details about the specific contract opportunity, such as the scope of work, response dates, or award information.

View the file

Other files

File Type Posted
265100_Lighting_Fixtures.pdf PDF
260001-ELECTRICAL_FSB.pdf PDF
220529_Hangers_and_Supports_JPB.pdf PDF
232123_hydronic_pumps.pdf PDF
015000_FL-TEMPORARY_FACILITIES_AND_CONTROLS.pdf PDF
M-601-10090.pdf PDF
AD121-10090.pdf PDF
M-651-10090.pdf PDF
061600_FL-SHEATHING_v1.pdf PDF
040001-MASONRY_WORK_FSB.pdf PDF
Specifications_Volume_2_Cover.pdf PDF
ES101-10090.pdf PDF
235216_condensing_boilers.pdf PDF
MD101-10090.pdf PDF
013200_FL-CONSTRUCTION_PROGRESS_DOCUMENTATION.pdf PDF
Prevailing_Wage_Chicopee_20110531-011.pdf PDF
C-100_CIVIL_SITE_PLAN.pdf PDF
260530_Electrical_Acceptance_Testing.pdf PDF
017839_FL-PROJECT_RECORD_DOCUMENTS.pdf PDF
017419_FL-CONSTRUCTION_WASTE_MANAGEMENT_AND_DISPOSAL.pdf PDF
090005-RESILIENT_FLOORS_FSB.pdf PDF
E-001-10090.pdf PDF
220500_plumbing_materials_JPB.pdf PDF
230719_hvac_pipe_ins.pdf PDF
087100_FL-DOOR_HARDWARE_v1.pdf PDF
EFT_FORM.pdf PDF
EL102-10090.pdf PDF
MIL_general_conditions_contract_Chicopee2011_Rev01.doc DOC document
262416_Panelboards.pdf PDF
033000_FL-CAST-IN-PLACE_CONCRETE_MAC.pdf PDF
238900_Louvers_and_Vents.pdf PDF
Specifications_Table_of_Contents.pdf PDF
093000_FL-TILING_v1.pdf PDF
096513_FL-RESILIENT_BASE_AND_ACCESSORIES.pdf PDF
GI001-10090.pdf PDF
233300_duct_accessories.pdf PDF
230500_mech_materials.pdf PDF
231123_fuel_gas_piping.pdf PDF
01811313_FL-SUSTAINABLE_DESIGN_REQUIREMENTS-LEED_FOR_NEW_CONSTRUCTION_AND_MAJOR_RENOVATIONS.pdf PDF
232300_refrigerant_piping.pdf PDF
262200_Low_Voltage_Transformers.pdf PDF
MIL_Invitation_to_Bid_Chicopee2011.doc DOC document
230993_seq_of_operations.pdf PDF
Ch_149_FORM_FOR_SUB_BID_MIL_Chicopee2011_Masonry.doc DOC document
230593_testing_adjusting_balancing.pdf PDF
AE311-10090.pdf PDF
102800_FL-TOILET_BATH_AND_LAUNDRY_ACCESSORIES_v1.pdf PDF
M-001-10090.pdf PDF
075423_FL-THERMOPLASTIC_POLYOLEFIN_TPO_ROOFING_v1.pdf PDF
SF501-10090.pdf PDF
Show 40 more

Latest 50 of 183 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

CHICOPEE ARMORY REHABILITATION MMD PROJECT NO. 985101

CHICOPEE, MASSACHUSETTS ISSUED FOR BID - 05/20/11

10090 DEMONSTRATION AND TRAINING 017900 - 1

SECTION 017900

DEMONSTRATION AND TRAINING

PART 1 - GENERAL

1.1 RELATED DOCUMENTS

A. Drawings and general provisions of the Contract, including General and Supplementary

Conditions and other Division 01 Specification Sections, apply to this Section.

1.2 SUMMARY

A. Section includes administrative and procedural requirements for instructing Owner's personnel, including the following:

1. Demonstration of operation of systems, subsystems, and equipment.

2. Training in operation and maintenance of systems, subsystems, and equipment.

3. Demonstration and training video recordings.

1.3 INFORMATIONAL SUBMITTALS

A. Instruction Program: Submit outline of instructional program for demonstration and training, including a list of training modules and a schedule of proposed dates, times, length of instruction time, and instructors' names for each training module. Include learning objective and outline for each training module.

1. Indicate proposed training modules using manufacturer-produced demonstration and training video recordings for systems, equipment, and products in lieu of video recording of live instructional module.

B. Qualification Data: For facilitator .

C. Attendance Record: For each training module, submit list of participants and length of instruction time.

D. Evaluations: For each participant and for each training module, submit results and documentation of performance-based test.

1.4 CLOSEOUT SUBMITTALS

A. Demonstration and Training Video Recordings: Submit two copies within seven days of end of each training module.

1. Identification: On each copy, provide an applied label with the following information:

10090 DEMONSTRATION AND TRAINING 017900 - 2

a. Name of Project.

b. Name and address of videographer.

c. Name of Architect.

d. Name of Construction Manager.

e. Name of Contractor.

f. Date of video recording.

2. Transcript: Prepared and bound in format matching operation and maintenance manuals.

Mark appropriate identification on front and spine of each binder. Include a cover sheet with same label information as the corresponding video recording. Include name of

Project and date of video recording on each page.

3. Transcript: Prepared in PDF electronic format. Include a cover sheet with same label information as the corresponding video recording and a table of contents with links to corresponding training components. Include name of Project and date of video recording on each page.

4. At completion of training, submit complete training manual(s) for Owner's use prepared and bound in format matching operation and maintenance manuals .

1.5 QUALITY ASSURANCE

A. Facilitator Qualifications: A firm or individual experienced in training or educating maintenance personnel in a training program similar in content and extent to that indicated for this Project, and whose work has resulted in training or education with a record of successful learning performance.

B. Instructor Qualifications: A factory-authorized service representative, complying with requirements in Section 014000 "Quality Requirements," experienced in operation and maintenance procedures and training.

C. Videographer Qualifications: A professional videographer who is experienced photographing demonstration and training events similar to those required.

D. Preinstruction Conference: Conduct conference at Project site to comply with requirements in

Section 013100 "Project Management and Coordination." Review methods and procedures related to demonstration and training including, but not limited to, the following:

1.6 COORDINATION

A. Coordinate instruction schedule with Owner's operations. Adjust schedule as required to minimize disrupting Owner's operations and to ensure availability of Owner's personnel.

B. Coordinate instructors, including providing notification of dates, times, length of instruction time, and course content.

C. Coordinate content of training modules with content of approved emergency, operation, and maintenance manuals. Do not submit instruction program until operation and maintenance data has been reviewed and approved by Architect.

10090 DEMONSTRATION AND TRAINING 017900 - 3

PART 2 - PRODUCTS

2.1 INSTRUCTION PROGRAM

A. Program Structure: Develop an instruction program that includes individual training modules for each system and for equipment not part of a system, as required by individual Specification

Sections.

B. Training Modules: Develop a learning objective and teaching outline for each module. Include a description of specific skills and knowledge that participant is expected to master. For each module, include instruction for the following as applicable to the system, equipment, or component:

1. Basis of System Design, Operational Requirements, and Criteria: Include the following:

a. System, subsystem, and equipment descriptions.

b. Performance and design criteria if Contractor is delegated design responsibility.

c. Operating standards.

d. Regulatory requirements.

e. Equipment function.

f. Operating characteristics.

g. Limiting conditions.

h. Performance curves.

2. Documentation: Review the following items in detail:

a. Emergency manuals.

b. Operations manuals.

c. Maintenance manuals.

d. Project record documents.

e. Identification systems.

f. Warranties and bonds.

g. Maintenance service agreements and similar continuing commitments.

3. Emergencies: Include the following, as applicable:

a. Instructions on meaning of warnings, trouble indications, and error messages.

b. Instructions on stopping.

c. Shutdown instructions for each type of emergency.

d. Operating instructions for conditions outside of normal operating limits.

e. Sequences for electric or electronic systems.

f. Special operating instructions and procedures.

4. Operations: Include the following, as applicable:

a. Startup procedures.

b. Equipment or system break-in procedures.

c. Routine and normal operating instructions.

d. Regulation and control procedures.

e. Control sequences.

10090 DEMONSTRATION AND TRAINING 017900 - 4

f. Safety procedures.

g. Instructions on stopping.

h. Normal shutdown instructions.

i. Operating procedures for emergencies.

j. Operating procedures for system, subsystem, or equipment failure.

k. Seasonal and weekend operating instructions.

l. Required sequences for electric or electronic systems.

m. Special operating instructions and procedures.

5. Adjustments: Include the following:

a. Alignments.

b. Checking adjustments.

c. Noise and vibration adjustments.

d. Economy and efficiency adjustments.

6. Troubleshooting: Include the following:

a. Diagnostic instructions.

b. Test and inspection procedures.

7. Maintenance: Include the following:

a. Inspection procedures.

b. Types of cleaning agents to be used and methods of cleaning.

c. List of cleaning agents and methods of cleaning detrimental to product.

d. Procedures for routine cleaning

e. Procedures for preventive maintenance.

f. Procedures for routine maintenance.

g. Instruction on use of special tools.

8. Repairs: Include the following:

a. Diagnosis instructions.

b. Repair instructions.

c. Disassembly; component removal, repair, and replacement; and reassembly instructions.

d. Instructions for identifying parts and components.

e. Review of spare parts needed for operation and maintenance.

PART 3 - EXECUTION

3.1 PREPARATION

A. Assemble educational materials necessary for instruction, including documentation and training module. Assemble training modules into a training manual organized in coordination with requirements in Section 017823 "Operation and Maintenance Data."

B. Set up instructional equipment at instruction location.

10090 DEMONSTRATION AND TRAINING 017900 - 5

3.2 INSTRUCTION

A. Facilitator: Engage a qualified facilitator to prepare instruction program and training modules, to coordinate instructors, and to coordinate between Contractor and Owner for number of participants, instruction times, and location.

B. Engage qualified instructors to instruct Owner's personnel to adjust, operate, and maintain systems, subsystems, and equipment not part of a system.

1. Owner will furnish Contractor with names and positions of participants.

C. Scheduling: Provide instruction at mutually agreed on times. For equipment that requires seasonal operation, provide similar instruction at start of each season.

1. Schedule training with Owner with at least seven days' advance notice.

D. Training Location and Reference Material: Conduct training on-site in the completed and fully operational facility using the actual equipment in-place. Conduct training using final operation and maintenance data submittals.

E. Evaluation: At conclusion of each training module, assess and document each participant's mastery of module by use of a demonstration performance-based test.

F. Cleanup: Collect used and leftover educational materials and give to Owner. Remove instructional equipment. Restore systems and equipment to condition existing before initial training use.

3.3 DEMONSTRATION AND TRAINING VIDEO RECORDINGS

A. General: Engage a qualified commercial videographer to record demonstration and training video recordings. Record each training module separately. Include classroom instructions and demonstrations, board diagrams, and other visual aids, but not student practice.

1. At beginning of each training module, record each chart containing learning objective and lesson outline.

B. Video: Provide minimum 640 x 480 video resolution converted to format file type acceptable to Owner, on electronic media.

1. Electronic Media: Read-only format compact disc acceptable to Owner, with commercial-grade graphic label.

2. File Hierarchy: Organize folder structure and file locations according to project manual table of contents. Provide complete screen-based menu.

3. File Names: Utilize file names based upon name of equipment generally described in video segment, as identified in Project specifications.

4. Contractor and Installer Contact File: Using appropriate software, create a file for inclusion on the Equipment Demonstration and Training DVD that describes the following for each Contractor involved on the Project, arranged according to Project table of contents:

a. Name of Contractor/Installer.

10090 DEMONSTRATION AND TRAINING 017900 - 6

b. Business address.

c. Business phone number.

d. Point of contact.

e. E-mail address.

C. Recording: Mount camera on tripod before starting recording, unless otherwise necessary to adequately cover area of demonstration and training. Display continuous running time.

1. Film training session(s) in segments not to exceed 15 minutes.

a. Produce segments to present a single significant piece of equipment per segment.

b. Organize segments with multiple pieces of equipment to follow order of Project

Manual table of contents.

c. Where a training session on a particular piece of equipment exceeds 15 minutes, stop filming and pause training session. Begin training session again upon commencement of new filming segment.

D. Light Levels: Verify light levels are adequate to properly light equipment. Verify equipment markings are clearly visible prior to recording.

1. Furnish additional portable lighting as required.

E. Narration: Describe scenes on video recording by audio narration by microphone while video recording is recorded. Include description of items being viewed.

F. Transcript: Provide a transcript of the narration. Display images and running time captured from videotape opposite the corresponding narration segment.

G. Preproduced Video Recordings: Provide video recordings used as a component of training modules in same format as recordings of live training.

END OF SECTION 017900