017839_FL-PROJECT_RECORD_DOCUMENTS.pdf

PDF 21 KB Posted

Attached to
Chicopee Armory Renovations Sub-Contractor Bids
Solicitation number
S125144-vCurrent
Issued by
Hampden County, Massachusetts

About this file

This document is the Project Record Documents section for the Chicopee Armory Rehabilitation project in Chicopee, Massachusetts, project number 985101. It outlines the administrative and procedural requirements for maintaining project record documents, including record drawings, specifications, product data, and miscellaneous submittals. The record documents must be maintained throughout construction and submitted at project closeout. The project record documents must be complete, accurate, and use personnel proficient in recording graphic information. The records must be organized digitally and submitted in PDF format, with links to the appropriate specification sections and items.

The document does not provide details on the overall state or local contract opportunity, but rather focuses on the record documentation requirements for the construction project. It does not mention any pricing terms, set-asides, incumbent contractors, funding sources, or other salient commercial information about the contract opportunity.

View the file

Other files

File Type Posted
265100_Lighting_Fixtures.pdf PDF
260001-ELECTRICAL_FSB.pdf PDF
220529_Hangers_and_Supports_JPB.pdf PDF
232123_hydronic_pumps.pdf PDF
015000_FL-TEMPORARY_FACILITIES_AND_CONTROLS.pdf PDF
M-601-10090.pdf PDF
AD121-10090.pdf PDF
M-651-10090.pdf PDF
061600_FL-SHEATHING_v1.pdf PDF
040001-MASONRY_WORK_FSB.pdf PDF
Specifications_Volume_2_Cover.pdf PDF
ES101-10090.pdf PDF
235216_condensing_boilers.pdf PDF
MD101-10090.pdf PDF
013200_FL-CONSTRUCTION_PROGRESS_DOCUMENTATION.pdf PDF
Prevailing_Wage_Chicopee_20110531-011.pdf PDF
C-100_CIVIL_SITE_PLAN.pdf PDF
260530_Electrical_Acceptance_Testing.pdf PDF
017419_FL-CONSTRUCTION_WASTE_MANAGEMENT_AND_DISPOSAL.pdf PDF
090005-RESILIENT_FLOORS_FSB.pdf PDF
E-001-10090.pdf PDF
220500_plumbing_materials_JPB.pdf PDF
230719_hvac_pipe_ins.pdf PDF
087100_FL-DOOR_HARDWARE_v1.pdf PDF
EFT_FORM.pdf PDF
EL102-10090.pdf PDF
MIL_general_conditions_contract_Chicopee2011_Rev01.doc DOC document
262416_Panelboards.pdf PDF
033000_FL-CAST-IN-PLACE_CONCRETE_MAC.pdf PDF
238900_Louvers_and_Vents.pdf PDF
Specifications_Table_of_Contents.pdf PDF
093000_FL-TILING_v1.pdf PDF
096513_FL-RESILIENT_BASE_AND_ACCESSORIES.pdf PDF
GI001-10090.pdf PDF
233300_duct_accessories.pdf PDF
230500_mech_materials.pdf PDF
231123_fuel_gas_piping.pdf PDF
01811313_FL-SUSTAINABLE_DESIGN_REQUIREMENTS-LEED_FOR_NEW_CONSTRUCTION_AND_MAJOR_RENOVATIONS.pdf PDF
232300_refrigerant_piping.pdf PDF
262200_Low_Voltage_Transformers.pdf PDF
MIL_Invitation_to_Bid_Chicopee2011.doc DOC document
230993_seq_of_operations.pdf PDF
Ch_149_FORM_FOR_SUB_BID_MIL_Chicopee2011_Masonry.doc DOC document
230593_testing_adjusting_balancing.pdf PDF
AE311-10090.pdf PDF
102800_FL-TOILET_BATH_AND_LAUNDRY_ACCESSORIES_v1.pdf PDF
M-001-10090.pdf PDF
075423_FL-THERMOPLASTIC_POLYOLEFIN_TPO_ROOFING_v1.pdf PDF
SF501-10090.pdf PDF
230900_hvac_instrumentation_controls.pdf PDF
Show 40 more

Latest 50 of 183 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

CHICOPEE ARMORY REHABILITATION MMD PROJECT NO. 985101

CHICOPEE, MASSACHUSETTS ISSUED FOR BID - 05/20/11

10090 PROJECT RECORD DOCUMENTS 017839 - 1

SECTION 017839

PROJECT RECORD DOCUMENTS

PART 1 - GENERAL

1.1 RELATED DOCUMENTS

A. Drawings and general provisions of the Contract, including General and Supplementary

Conditions and other Division 01 Specification Sections, apply to this Section.

1.2 SUMMARY

A. Section includes administrative and procedural requirements for project record documents, including the following:

1. Record Drawings.

2. Record Specifications.

3. Record Product Data.

4. Miscellaneous record submittals.

B. Related Requirements:

1. Section 017300 "Execution" for final property survey.

2. Section 017700 "Closeout Procedures" for general closeout procedures.

3. Section 017823 "Operation and Maintenance Data" for operation and maintenance manual requirements.

1.3 CLOSEOUT SUBMITTALS

A. Record Drawings: Comply with the following:

a. Initial Submittal:

1) Submit record digital data files and one set(s) of plots.

2) Architect will indicate whether general scope of changes, additional information recorded, and quality of drafting are acceptable.

3) Submit record digital data files and three set(s) of record digital data file plots.

4) Plot each drawing file, whether or not changes and additional information were recorded.

B. Record Product Data: Submit one paper copy and annotated PDF electronic files and directories of each submittal.

1. Where record Product Data are required as part of operation and maintenance manuals, submit duplicate marked-up Product Data as a component of manual.

10090 PROJECT RECORD DOCUMENTS 017839 - 2

C. Retain "Miscellaneous Record Submittals" Paragraph below if Owner desires a complete project record

PART 2 - PRODUCTS

2.1 RECORD DRAWINGS

A. Record Prints: Maintain one set of marked-up paper copies of the Contract Drawings and Shop

Drawings, incorporating new and revised drawings as modifications are issued.

1. Preparation: Mark record prints to show the actual installation where installation varies from that shown originally. Require individual or entity who obtained record data, whether individual or entity is Installer, subcontractor, or similar entity, to provide information for preparation of corresponding marked-up record prints.

a. Give particular attention to information on concealed elements that would be difficult to identify or measure and record later.

b. Accurately record information in an acceptable drawing technique.

c. Record data as soon as possible after obtaining it.

d. Record and check the markup before enclosing concealed installations.

e. Cross-reference record prints to corresponding archive photographic documentation.

2. Content: Types of items requiring marking include, but are not limited to, the following:

a. Dimensional changes to Drawings.

b. Revisions to details shown on Drawings.

c. Depths of foundations below first floor.

d. Locations and depths of underground utilities.

e. Revisions to routing of piping and conduits.

f. Revisions to electrical circuitry.

g. Actual equipment locations.

h. Duct size and routing.

i. Locations of concealed internal utilities.

j. Changes made by Change Order or Construction Change Directive.

k. Changes made following Architect's written orders.

l. Details not on the original Contract Drawings.

m. Field records for variable and concealed conditions.

n. Record information on the Work that is shown only schematically.

3. Mark the Contract Drawings and Shop Drawings completely and accurately. Use personnel proficient at recording graphic information in production of marked-up record prints.

4. Mark record sets with erasable, red-colored pencil. Use other colors to distinguish between changes for different categories of the Work at same location.

5. Mark important additional information that was either shown schematically or omitted from original Drawings.

6. Note Construction Change Directive numbers, alternate numbers, Change Order numbers, and similar identification, where applicable.

10090 PROJECT RECORD DOCUMENTS 017839 - 3

B. Record Digital Data Files: Immediately before inspection for Certificate of Substantial

Completion, review marked-up record prints with Architect. When authorized, prepare a full set of corrected digital data files of the Contract Drawings, as follows:

1. Format: Same digital data software program, version, and operating system as the original Contract Drawings.

2. Incorporate changes and additional information previously marked on record prints.

Delete, redraw, and add details and notations where applicable.

3. Refer instances of uncertainty to Architect for resolution.

4. Architect will furnish Contractor one set of digital data files of the Contract Drawings for use in recording information.

a. See Section 013300 "Submittal Procedures" for requirements related to use of

Architect's digital data files.

C. Format: Identify and date each record Drawing; include the designation "PROJECT RECORD

DRAWING" in a prominent location.

1. Record Digital Data Files: Organize digital data information into separate electronic files that correspond to each sheet of the Contract Drawings. Name each file with the sheet identification. Include identification in each digital data file.

2. Identification: As follows:

a. Project name.

b. Date.

c. Designation "PROJECT RECORD DRAWINGS."

d. Name of Architect.

e. Name of Contractor.

2.2 RECORD PRODUCT DATA

A. Preparation: Mark Product Data to indicate the actual product installation where installation varies substantially from that indicated in Product Data submittal.

1. Give particular attention to information on concealed products and installations that cannot be readily identified and recorded later.

2. Include significant changes in the product delivered to Project site and changes in manufacturer's written instructions for installation.

3. Note related Change Orders and record Drawings where applicable.

B. Format: Submit record Product Data as scanned PDF electronic file(s) of marked-up paper copy of Product Data.

1. Include record Product Data directory organized by Specification Section number and title, electronically linked to each item of record Product Data.

10090 PROJECT RECORD DOCUMENTS 017839 - 4

2.3 MISCELLANEOUS RECORD SUBMITTALS

A. Assemble miscellaneous records required by other Specification Sections for miscellaneous record keeping and submittal in connection with actual performance of the Work. Bind or file miscellaneous records and identify each, ready for continued use and reference.

B. Format: Submit miscellaneous record submittals as scanned PDF electronic file(s) of marked-up miscellaneous record submittals.

1. Include miscellaneous record submittals directory organized by Specification Section number and title, electronically linked to each item of miscellaneous record submittals.

PART 3 - EXECUTION

3.1 RECORDING AND MAINTENANCE

A. Recording: Maintain one copy of each submittal during the construction period for project record document purposes. Post changes and revisions to project record documents as they occur; do not wait until end of Project.

B. Maintenance of Record Documents and Samples: Store record documents and Samples in the field office apart from the Contract Documents used for construction. Do not use project record documents for construction purposes. Maintain record documents in good order and in a clean, dry, legible condition, protected from deterioration and loss. Provide access to project record documents for Architect's reference during normal working hours.

END OF SECTION 017839

File details come from the government source that posted it. Updated .