This construction waste management plan outlines requirements for handling and disposing of waste from a Department of Energy construction project to renovate interior walls and floors. The selected contractor must develop and implement a waste management plan to recycle or salvage at least 50% of construction debris excluding soil. The plan must include an inventory of waste to be generated along with means to recycle and reuse materials. The contractor will provide monthly reports on all recycled items by type and tonnage. Collection bins for recyclable materials like lumber, gypsum, paper, plastics and metals must be provided on site. At least 80% of construction waste by weight must be diverted from landfills through resale, recycling or reuse. The contractor will arrange for processing of salvaged materials and is responsible for proper disposal of non-recyclable waste in accordance with all applicable regulations.

View the file

Other files

Show all 24

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

PPPL Construction Waste Management and Disposal August 2023

CONSTRUCTION WASTE MANAGEMENT AND DISPOSAL

017419 -1

SECTION 017419 - CONSTRUCTION WASTE MANAGEMENT AND DISPOSAL

PART 1 GENERAL

1.1 RELATED DOCUMENTS

A. The following applies to this section:

1. The PPPL Subcontract General Provisions and Special Terms and

Conditions for Construction Subcontracts

2. Related requirements in other Subcontract Documents including, but not necessarily limited to, the Subcontract Drawings and Specifications.

B. Related Sections:

1. SECTION 015000 - TEMPORARY FACILITIES AND CONTROLS

2. SECTION 017700 – CLOSEOUT PROCEDURES

3. SECTION 018113 - SUSTAINABLE DESIGN REQUIREMENTS

C. Related requirements in other Subcontract Documents listed in the Agreement.

D. Review these documents for coordination with additional requirements and information that applies to work under this Section.

1.2 SUMMARY

A. Section Includes:

1. Construction waste management plan.

2. Construction waste recycling.

1.3 PLAN REQUIREMENTS

A. Develop, submit, and implement a Construction Waste Management plan to recycle or salvage at least 50 percent of the non-hazardous construction, demolition and land clearing materials, excluding soil, for compliance with DOE Guiding Principle.

B. The Subcontractor shall dispose of all construction debris in accordance with Federal, State, and Local requirements. In an effort to reduce waste to landfill per DOE E.O.

13834, the Subcontractor shall perform an inventory of waste to be generated and put in process means to recycle and reuse materials generated. Inventory of materials generated for the purpose of diverting waste from landfill shall be provided to the PTR.

Additionally, the subcontractor shall provide the PTR data for all items recycled by type.

Data shall be reported in tons and provided monthly.

1.4 SUBMITTALS

A. Construction Plan: Submit construction waste management plan describing methods and procedures for implementation and monitoring compliance including the following:

1. Transportation company hauling construction waste to waste processing facilities.

017419 -2

2. Recycling and adaptive reuse processing facilities and waste type each facility will accept.

3. Construction waste materials anticipated for recycling and adaptive reuse.

4. On site sorting and site storage methods.

B. Submit documentation prior to Substantial Completion, substantiating construction waste management plan was maintained, and goals were achieved.

1. Trash: Quantity by weight deposited in landfills. Provide receipt tickets from the disposal facility throughout the demolition/removal process to document weight.

2. Salvaged Material: Quantity by weight with destination for each type of material salvaged for resale, recycling, or adaptive reuse.

1.5 CONSTRUCTION WASTE MANAGEMENT PLAN

A. Construction Waste Landfill Diversion: A goal of 80 percent by weight of construction waste materials for the duration of the Project through resale, recycling, or adaptive reuse.

B. Implement construction waste management plan at start of construction.

C. Review construction waste management plan at pre-construction meeting and progress meetings

D. Distribute approved construction waste management plan to subcontractors and others affected by Plan Requirements.

E. Oversee plan implementation, instruct construction personnel for plan compliance, and document plan results.

1.6 CONSTRUCTION WASTE RECYCLING

A. The Subcontractor shall have the option of sorting the materials off-site or on-site.

1. Off-Site: If the Subcontractor chooses to sort the material off-site, he shall provide the name of the vendor, and provide procedures on the documentation of the recyclable waste.

2. On-Site: The Subcontractor shall provide separate collection containers for a minimum of the following materials:

a) Untreated lumber.

b) Gypsum wallboard.

c) Paper, paper products, and cardboard.

d) Plastics.

e) Metals.

f) Glass.

g) Other salvageable materials.

1.7 CONSTRUCTION WASTE ADAPTIVE RE-USE

017419 -3

A. Arrange with processing facility for salvage of construction material and processing for reuse. Do not reuse construction materials on site except as accepted by PPPL.

1.8 QUALITY ASSURANCE

A. Regulatory Requirements: Comply with applicable local ordinances and regulations.

B. Disposal Sites, Recyclers, and Waste Materials Processors: Use only facilities properly permitted by the State of New Jersey, and by local authorities where applicable.

C. Prior to beginning work at the site, schedule and conduct a conference to review the Construction Waste Management Plan and discuss procedures, schedules and specific requirements for waste materials recycling and disposal. Discuss coordination and interface between the Subcontractor and other construction activities. Identify and resolve problems with compliance with requirements. Record minutes of the meeting, identifying all conclusions reached and matters requiring further resolution.

1. Attendees: The Subcontractor and related Subcontractor personnel associated with the work of this section, including personnel to be in charge of the waste management program; the PPPL Sustainability representative, Construction Quality Manager; and such additional personnel as PPPL deems appropriate.

2. Plan Revision: Make any revisions to the Construction Waste Management Plan agreed upon during the meeting and incorporate resolutions agreed to be made subsequent to the meeting. Submit the revised plan to PPPL for approval.

D. Implementation: Designate an on-site person responsible for instructing workers and implementing the Construction Waste Management Plan. Distribute copies of the Construction Waste Management Plan to the job site foreman and each subcontractor.

Post Waste Management Plan on the job site bulletin board. Include waste management and recycling in worker orientation and review periodically. Provide on-site instruction on appropriate separation, handling, recycling, and salvaging methods to be used by all parties at the appropriate stages of the work at the site. Include waste management and recycling discussion in pre-fabrication meetings with subcontractors and fabricators. Also include discussion of waste management and recycling in regular job meetings and job safety meetings conducted during the course of work at the site.

PART 2 PRODUCTS – NOT USED

PART 3 EXECUTION

2.1 CONSTRUCTION WASTE COLLECTION

A. Collect construction waste materials in marked bins or containers and arrange for transportation to recycling centers or adaptive salvage and reuse processing facilities.

Remove all indicated recyclable materials from the work location to approved containers daily. Failure to remove waste materials will be considered cause for withholding payment and termination of Subcontract.

017419 -4

B. Containers: Change out loaded containers for empty ones as demand requires, but not less than weekly. See Section 015000 for temporary protections for containers.

C. Handling: Deposit all indicated recyclable materials in the containers in a clean (no mud, adhesives, solvents, petroleum contamination), debris-free condition. Do not deposit contaminated materials into the containers until such time as such materials have been cleaned.

D. If the contamination chemically combines with the material so that it cannot be cleaned, do not deposit into the recycle containers. In such a case, request resolution by the Construction Quality Manager as to disposal of the contaminated material. Directions from the Construction Quality Manager do not relieve the Subcontractor from compliance with all legal and regulatory requirements for disposal, nor shall such directions cause a request for modification of the Subcontract

E. Maintain recycling and adaptive reuse storage and collection area in orderly arrangement with materials separated to eliminate co-mingling of materials required to be delivered separately to the waste processing facility.

F. Store construction waste materials to prevent environmental pollution, fire hazards, hazards to persons and property, and contamination of stored materials.

G. Cover construction waste materials subject to disintegration, evaporation, settling, or runoff to prevent polluting air, water, and soil.

2.2 CONSTRUCTION WASTE DISPOSAL

A. Deliver construction waste to waste processing facilities. Obtain receipt for deliveries.

B. Dispose construction waste not capable of being recycled or adaptively reused by delivery to landfill, incinerator, or other legal disposal facility. Obtain receipt for deliveries.

END OF SECTION 017419