014529 Testing Lab Srvcs 05-09 - Edited - 121511.pdf
PDF 110 KB Posted
- Attached to
- Z1DA--FIRE DAMPERS -Repair, Install, Inspect and Testing Federal contract opportunity
- Solicitation number
- 36C24221B0065
About this file
This document provides details for an upcoming federal solicitation seeking fire damper repair, installation, inspection, and testing services. The Department of Veterans Affairs Veterans Health Administration Veterans Integrated Service Network 2 will issue a solicitation on or about August 27, 2021 to repair, install, inspect, test, and decommission approximately 350 fire dampers located in Buildings 1 and 6 of the VA New York Harbor Healthcare System Manhattan Veterans Affairs Medical Center. The project is a 100% Veteran-Owned Small Business set-aside with an estimated construction cost range of $200,000 to $500,000 classified under NAICS code 238220. The selected contractor must provide all labor, materials, equipment, and supervision to inspect and test existing fire dampers, research facility records to locate damper locations, prepare shop drawings and as-built drawings in AutoCAD and PDF formats, and submit a final report with drawings, photographs, and an inventory sheet. The performance period is 360 calendar days from notice to proceed.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| 36C24221B0065 0004.docx | DOCX document | |
| Bid Sheet -36C24221B0065 Rev.pdf | ||
| 36C24221B0065 0003.docx | DOCX document | |
| RFIs -36C24221B0065 Answers.pdf | ||
| VA NOTICE OF LIMITATIONS ON SUBCONTRACTING CERTIFICATION.pdf | ||
| Site Visit - Sign In 36C24221B0065 Fire Damper.pdf | ||
| Bid Sheet -36C24221B0065.pdf | ||
| 36C24221B0065 0002.docx | DOCX document | |
| 36C24221B0065 0001.docx | DOCX document | |
| 015816 Temp Int Signage 08-11 Edited 121511.pdf | ||
| 017419 Const Waste management 09-10 edited 121511.pdf | ||
| Building 6.pdf | ||
| Building 1.pdf | ||
| DB Wage Determination dtd 10-22-2021.pdf | ||
| 014219 Ref Standards 09-11 - Edited - 121511.pdf | ||
| 36C24221B0065.docx | DOCX document | |
| 015719Temp Env Cntrls 01-11 - Edited 121511.pdf | ||
| 013323 Shop Dwgs Product Data and Samples - Edited - 121511.pdf | ||
| 010000 Gen Req 6-11- Edited -121311.pdf | ||
| Fire Dampers Report - 2014.pdf |
Show all 20
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
05-09M
Repair Fire Dampers/Testing last edited 1/4/12
01 45 29 - 1
SECTION 01 45 29
TESTING LABORATORY SERVICES
PART 1 - GENERAL
1.1 DESCRIPTION:
This section specifies materials testing activities and inspection services required during project construction to be provided by a
Testing Laboratory retained and paid for by Contractor.
1.2 APPLICABLE PUBLICATIONS:
A. The publications listed below form a part of this specification to the extent referenced. The publications are referred to in the text by the basic designation only.
B. American Association of State Highway and Transportation Officials
(AASHTO):
T27-06 ................ Sieve Analysis of Fine and Coarse Aggregates
T96-02 (R2006)......... Resistance to Degradation of Small-Size Coarse
Aggregate by Abrasion and Impact in the Los
Angeles Machine
T99-01 (R2004)......... The Moisture-Density Relations of Soils Using a
2.5 Kg (5.5 lb.) Rammer and a 305 mm (12 in.)
Drop
T104-99 (R2003)........ Soundness of Aggregate by Use of Sodium Sulfate or Magnesium Sulfate
T180-01 (R2004)........ Moisture-Density Relations of Soils using a
4.54 kg (10 lb.) Rammer and a 457 mm (18 in.)
Drop
T191-02(R2006)......... Density of Soil In-Place by the Sand-Cone
Method
C. American Concrete Institute (ACI):
506.4R-94 (R2004) ...... Guide for the Evaluation of Shotcrete
D. American Society for Testing and Materials (ASTM):
A325-06 ............... Structural Bolts, Steel, Heat Treated, 120/105 ksi Minimum Tensile Strength
A370-07 ............... Definitions for Mechanical Testing of Steel
Products
A416/A416M-06 ......... Steel Strand, Uncoated Seven-Wire for
Prestressed Concrete
01 45 29 - 2
A490-06 ............... Heat Treated Steel Structural Bolts, 150 ksi
Minimum Tensile Strength
C31/C31M-06 ........... Making and Curing Concrete Test Specimens in the Field
C33-03 ................ Concrete Aggregates
C39/C39M-05 ........... Compressive Strength of Cylindrical Concrete
Specimens
C109/C109M-05 ......... Compressive Strength of Hydraulic Cement
Mortars
C138-07 ............... Unit Weight, Yield, and Air Content
(Gravimetric) of Concrete
C140-07 ............... Sampling and Testing Concrete Masonry Units and
Related Units
C143/C143M-05 ......... Slump of Hydraulic Cement Concrete
C172-07 ............... Sampling Freshly Mixed Concrete
C173-07 ............... Air Content of freshly Mixed Concrete by the
Volumetric Method
C330-05 ............... Lightweight Aggregates for Structural Concrete
C567-05 ............... Density Structural Lightweight Concrete
C780-07 ............... Pre-construction and Construction Evaluation of
Mortars for Plain and Reinforced Unit Masonry
C1019-08 .............. Sampling and Testing Grout
C1064/C1064M-05........ Freshly Mixed Portland Cement Concrete
C1077-06 .............. Laboratories Testing Concrete and Concrete
Aggregates for Use in Construction and Criteria for Laboratory Evaluation
C1314-07 .............. Compressive Strength of Masonry Prisms
D698-07 ............... Laboratory Compaction Characteristics of Soil
Using Standard Effort
D1143-07 .............. Piles Under Static Axial Compressive Load
D1188-07 .............. Bulk Specific Gravity and Density of Compacted
Bituminous Mixtures Using Paraffin-Coated
Specimens
D1556-07 .............. Density and Unit Weight of Soil in Place by the
Sand-Cone Method
D1557-07 .............. Laboratory Compaction Characteristics of Soil
Using Modified Effort
01 45 29 - 3
D2166-06 .............. Unconfined Compressive Strength of Cohesive
Soil
D2167-94(R2001)........ Density and Unit Weight of Soil in Place by the
Rubber Balloon Method
D2216-05 .............. Laboratory Determination of Water (Moisture)
Content of Soil and Rock by Mass
D2922-05 .............. Density of soil and Soil-Aggregate in Place by
Nuclear Methods (Shallow Depth)
D2974-07 .............. Moisture, Ash, and Organic Matter of Peat and
Other Organic Soils
D3666-(2002) .......... Minimum Requirements for Agencies Testing and
Inspection Bituminous Paving Materials
D3740-07 .............. Minimum Requirements for Agencies Engaged in the Testing and Inspecting Road and Paving
Material
E94-04 ................ Radiographic Testing
E164-03 ............... Ultrasonic Contact Examination of Weldments
E329-07 ............... Agencies Engaged in Construction Inspection and/or Testing
E543-06 ............... Agencies Performing Non-Destructive Testing
E605-93(R2006)......... Thickness and Density of Sprayed Fire-Resistive
Material (SFRM) Applied to Structural Members
E709-(2001) ........... Guide for Magnetic Particle Examination
E1155-96(R2008)........ Determining FF Floor Flatness and FL Floor
Levelness Numbers
E. American Welding Society (AWS):
D1.1-07 ............... Structural Welding Code-Steel
1.3 REQUIREMENTS:
A. Accreditation Requirements: Construction materials testing laboratories must be accredited by a laboratory accreditation authority and will be required to submit a copy of the Certificate of Accreditation and Scope of Accreditation. The laboratory’s scope of accreditation must include the appropriate ASTM standards (i.e.; E 329, C 1077, D 3666, D3740, A
880, E 543) listed in the technical sections of the specifications.
Laboratories engaged in Hazardous Materials Testing shall meet the requirements of OSHA and EPA. The policy applies to the specific
01 45 29 - 4 laboratory performing the actual testing, not just the “Corporate
Office.”
B. Inspection and Testing: Testing laboratory shall inspect materials and workmanship and perform tests described herein and additional tests requested by Resident Engineer. When it appears materials furnished, or work performed by Contractor fail to meet construction contract requirements, Testing Laboratory shall direct attention of Resident
Engineer to such failure.
C. Written Reports: Testing laboratory shall submit test reports to
Resident Engineer, Contractor, unless other arrangements are agreed to in writing by the Resident Engineer. Submit reports of tests that fail to meet construction contract requirements on colored paper.
D. Verbal Reports: Give verbal notification to Resident Engineer immediately of any irregularity.
PART 2 - PRODUCTS (NOT USED)
PART 3 - EXECUTION
3.1 EARTHWORK:
NA
3.2 FOUNDATION PILES:
NA
3.3 FOUNDATION CAISSONS:
A. NA
3.4 LANDSCAPING:
NA
3.5 ASPHALT CONCRETE PAVING:
3.6 SITE WORK CONCRETE:
NA.
3.7 POST-TENSIONING OF CONCRETE:
NA large volume of concrete, reduction in plant inspection without sacrificing quality would produce cost savings.
3.8 CONCRETE:
A. Batch Plant Inspection and Materials Testing:
1. Perform continuous batch plant inspection until concrete quality is established to satisfaction of Resident Engineer with concurrence of
01 45 29 - 5
Contracting Officer and perform periodic inspections thereafter as determined by Resident Engineer.
2. Periodically inspect and test batch proportioning equipment for accuracy and report deficiencies to Resident Engineer.
3. Sample and test mix ingredients as necessary to insure compliance with specifications.
4. Sample and test aggregates daily and as necessary for moisture content. Test the dry rodded weight of the coarse aggregate whenever a sieve analysis is made, and when it appears there has been a change in the aggregate.
5. Certify, in duplicate, ingredients and proportions and amounts of ingredients in concrete conform to approved trial mixes. When concrete is batched or mixed off immediate building site, certify
(by signing, initialing or stamping thereon) on delivery slips
(duplicate) that ingredients in truck-load mixes conform to proportions of aggregate weight, cement factor, and water-cement ratio of approved trial mixes.
SPEC WRITER NOTE: Include only tests applicable to the project. For a project with a large volume of concrete consider changing the rate of making concrete cylinders during the progress of the job.
B. Field Inspection and Materials Testing:
1. Provide a technician at site of placement at all times to perform concrete sampling and testing.
2. Review the delivery tickets of the ready-mix concrete trucks arriving on-site. Notify the Contractor if the concrete cannot be placed within the specified time limits or if the type of concrete delivered is incorrect. Reject any loads that do not comply with the
Specification requirements. Rejected loads are to be removed from the site at the Contractor’s expense. Any rejected concrete that is placed will be subject to removal.
3. Take concrete samples at point of placement in accordance with ASTM
C172. Mold and cure compression test cylinders in accordance with
ASTM C31. Make at least three cylinders for each 40 m3 (50 cubic yards) or less of each concrete type, and at least three cylinders for any one day's pour for each concrete type. // After good concrete quality control has been established and maintained as
01 45 29 - 6 determined by Resident Engineer make three cylinders for each 80 m 3
(100 cubic yards) or less of each concrete type, and at least three cylinders from any one day's pour for each concrete type. // Label each cylinder with an identification number. Resident Engineer may require additional cylinders to be molded and cured under job conditions.
4. Perform slump tests in accordance with ASTM C143. Test the first truck each day, and every time test cylinders are made. Test pumped concrete at the hopper and at the discharge end of the hose at the beginning of each day’s pumping operations to determine change in slump.
5. Determine the air content of concrete per ASTM C173. For concrete required to be air-entrained, test the first truck and every 20 m3
(25 cubic yards) thereafter each day. For concrete not required to be air-entrained, test every 80 m3 (100 cubic yards) at random. For pumped concrete, initially test concrete at both the hopper and the discharge end of the hose to determine change in air content.
6. If slump or air content fall outside specified limits, make another test immediately from another portion of same batch.
7. Perform unit weight tests in compliance with ASTM C138 for normal weight concrete and ASTM C567 for lightweight concrete. Test the first truck and each time cylinders are made.
8. Notify laboratory technician at batch plant of mix irregularities and request materials and proportioning check.
9. Verify that specified mixing has been accomplished.
10. Environmental Conditions: Determine the temperature per ASTM C1064 for each truckload of concrete during hot weather and cold weather concreting operations:
a. When ambient air temperature falls below 4.4 degrees C (40 degrees F), record maximum and minimum air temperatures in each
24 hour period; record air temperature inside protective enclosure; record minimum temperature of surface of hardened concrete.
b. When ambient air temperature rises above 29.4 degrees C (85 degrees F), record maximum and minimum air temperature in each 24 hour period; record minimum relative humidity; record maximum
01 45 29 - 7 wind velocity; record maximum temperature of surface of hardened concrete.
11. Inspect the reinforcing steel placement, including bar size, bar spacing, top and bottom concrete cover, proper tie into the chairs, and grade of steel prior to concrete placement. Submit detailed report of observations.
12. Observe conveying, placement, and consolidation of concrete for conformance to specifications.
13. Observe condition of formed surfaces upon removal of formwork prior to repair of surface defects and observe repair of surface defects.
14. Observe curing procedures for conformance with specifications, record dates of concrete placement, start of preliminary curing, start of final curing, end of curing period.
15. Observe preparations for placement of concrete:
a. Inspect handling, conveying, and placing equipment, inspect vibrating and compaction equipment.
b. Inspect preparation of construction, expansion, and isolation joints.
16. Observe preparations for protection from hot weather, cold weather, sun, and rain, and preparations for curing.
17. Observe concrete mixing:
a. Monitor and record amount of water added at project site.
b. Observe minimum and maximum mixing times.
18. Measure concrete flatwork for levelness and flatness as follows:
a. Perform Floor Tolerance Measurements FF and FL in accordance with
ASTM E1155. Calculate the actual overall F- numbers using the inferior/superior area method.
b. Perform all floor tolerance measurements within 48 hours after slab installation and prior to removal of shoring and formwork.
c. Provide the Contractor and the Resident Engineer with the results of all profile tests, including a running tabulation of the overall FF and FL values for all slabs installed to date, within
72 hours after each slab installation.
19. Other inspections:
a. Grouting under base plates.
b. Grouting anchor bolts and reinforcing steel in hardened concrete.
C. Laboratory Tests of Field Samples:
01 45 29 - 8
1. Test compression test cylinders for strength in accordance with ASTM
C39. For each test series, test one cylinder at 7 days and one cylinder at 28 days. Use remaining cylinder as a spare tested as directed by Resident Engineer. Compile laboratory test reports as follows: Compressive strength test shall be result of one cylinder, except when one cylinder shows evidence of improper sampling, molding or testing, in which case it shall be discarded and strength of spare cylinder shall be used.
2. Make weight tests of hardened lightweight structural concrete in accordance with ASTM C567.
3. Furnish certified compression test reports (duplicate) to Resident
Engineer. In test report, indicate the following information:
a. Cylinder identification number and date cast.
b. Specific location at which test samples were taken.
c. Type of concrete, slump, and percent air.
d. Compressive strength of concrete in MPa (psi).
e. Weight of lightweight structural concrete in kg/m3 (pounds per cubic feet).
f. Weather conditions during placing.
g. Temperature of concrete in each test cylinder when test cylinder was molded.
h. Maximum and minimum ambient temperature during placing.
i. Ambient temperature when concrete sample in test cylinder was taken.
j. Date delivered to laboratory and date tested.
3.9 REINFORCEMENT:
3.10 SHOTCRETE:
NA
3.11 PRESTRESSED CONCRETE:
NA
3.12 ARCHITECTURAL PRECAST CONCRETE:
NA
3.13 MASONRY:
A. Mortar Tests:
1. Laboratory compressive strength test:
a. Comply with ASTM C780.
01 45 29 - 9
b. Obtain samples during or immediately after discharge from batch mixer.
c. Furnish molds with 50 mm (2 inch), 3 compartment gang cube.
d. Test one sample at 7 days and 2 samples at 28 days.
2. Two tests during first week of operation; one test per week after initial test until masonry completion.
B. Grout Tests:
1. Laboratory compressive strength test:
a. Comply with ASTM C1019.
b. Test one sample at 7 days and 2 samples at 28 days.
c. Perform test for each 230 m2 (2500 square feet) of masonry.
C. Masonry Unit Tests:
1. Laboratory Compressive Strength Test:
a. Comply with ASTM C140.
b. Test 3 samples for each 460 m2 (5000 square feet) of wall area.
D. Prism Tests: For each type of wall construction indicated, test masonry prisms per ASTM C1314 for each 460 m2 (5000 square feet) of wall area.
Prepare one set of prisms for testing at 7 days and one set for testing at 28 days.
SPEC WRITER NOTE: Verify need for and extent of Structural Steel Inspection and testing services with Structural
Engineer.
3.14 STRUCTURAL STEEL:
A. General: Provide shop and field inspection and testing services to certify structural steel work is done in accordance with contract documents. Welding shall conform to AWS D1.1 Structural Welding Code.
B. Prefabrication Inspection:
1. Review design and shop detail drawings for size, length, type and location of all welds to be made.
2. Approve welding procedure qualifications either by pre-qualification or by witnessing qualifications tests.
3. Approve welder qualifications by certification or retesting.
4. Approve procedure for control of distortion and shrinkage stresses.
5. Approve procedures for welding in accordance with applicable sections of AWS D1.1.
C. Fabrication and Erection:
1. Weld Inspection:
01 45 29 - 10
a. Inspect welding equipment for capacity, maintenance and working condition.
b. Verify specified electrodes and handling and storage of electrodes in accordance with AWS D1.1.
c. Inspect preparation and assembly of materials to be welded for conformance with AWS D1.1.
d. Inspect preheating and interpass temperatures for conformance with AWS D1.1.
e. Measure 25 percent of fillet welds.
f. Welding Magnetic Particle Testing: Test in accordance with ASTM
E709 for a minimum of:
1) 20 percent of all shear plate fillet welds at random, final pass only.
2) 20 percent of all continuity plate and bracing gusset plate fillet welds, at random, final pass only.
3) 100 percent of tension member fillet welds (i.e., hanger connection plates and other similar connections) for root and final passes.
4) 20 percent of length of built-up column member partial penetration and fillet welds at random for root and final passes.
5) 100 percent of length of built-up girder member partial penetration and fillet welds for root and final passes.
g. Welding Ultrasonic Testing: Test in accordance with ASTM E164 and
AWS D1.1 for 100 percent of all full penetration welds, braced and moment frame column splices, and a minimum of 20 percent of all other partial penetration column splices, at random.
SPEC WRITER NOTE: Specify radiographic testing only for very large jobs or those with complicated full penetration welds.
h. Welding Radiographic Testing: Test in accordance with ASTM E94, and AWS D1.1 for 5 percent of all full penetration welds at random.
i. Verify that correction of rejected welds are made in accordance with AWS D1.1.
j. Testing and inspection do not relieve the Contractor of the responsibility for providing materials and fabrication procedures in compliance with the specified requirements.
01 45 29 - 11
2. Bolt Inspection:
a. Inspect high-strength bolted connections in accordance AISC
Specifications for Structural Joints Using ASTM A325 or A490
Bolts.
b. Slip-Critical Connections: Inspect 10 percent of bolts, but not less than 2 bolts, selected at random in each connection in accordance with AISC Specifications for Structural Joints Using
ASTM A325 or A490 Bolts. Inspect all bolts in connection when one or more are rejected.
c. Fully Pre-tensioned Connections: Inspect 10 percent of bolts, but not less than 2 bolts, selected at random in 25 percent of connections in accordance with AISC Specification for Structural
Joints Using ASTM A325 or A490 Bolts. Inspect all bolts in connection when one or more are rejected.
d. Bolts installed by turn-of-nut tightening may be inspected with calibrated wrench when visual inspection was not performed during tightening.
e. Snug Tight Connections: Inspect 10 percent of connections verifying that plies of connected elements have been brought into snug contact.
f. Inspect field erected assemblies; verify locations of structural steel for plumbness, level, and alignment.
D. Submit inspection reports, record of welders and their certification, and identification, and instances of noncompliance to Resident
Engineer.
SPEC WRITER NOTE: Verify need for and extent of Steel Decking Inspection and testing services with Structural
Engineer.
3.15 STEEL DECKING:
A. Provide field inspection of welds of metal deck to the supporting steel, and testing services to insure steel decking has been installed in accordance with contract documents and manufacturer’s requirements.
B. Qualification of Field Welding: Qualify welding processes and welding operators in accordance with “Welder Qualification” procedures of AWS
D1.1. Refer to the “Plug Weld Qualification Procedure” in Part 3 “Field
Quality Control.”
01 45 29 - 12
C. Submit inspection reports, certification, and instances of noncompliance to Resident Engineer.
3.16 SHEAR CONNECTOR STUDS:
A. Provide field inspection and testing services required by AWS D.1 to insure shear connector studs have been installed in accordance with contract documents.
B. Tests: Test 20 percent of headed studs for fastening strength in accordance with AWS D1.1.
C. Submit inspection reports, certification, and instances of noncompliance to Resident Engineer.
SPEC WRITER NOTE: Verify need for sprayed-on fireproofing inspection and testing services with Architect.
3.17 SPRAYED-ON FIREPROOFING:
A. Provide field inspection and testing services to certify sprayed-on fireproofing has been applied in accordance with contract documents.
B. Obtain a copy of approved submittals from Resident Engineer.
C. Use approved installation in test areas as criteria for inspection of work.
D. Test sprayed-on fireproofing for thickness and density in accordance with ASTM E605.
1. Thickness gauge specified in ASTM E605 may be modified for pole extension so that overhead sprayed material can be reached from floor.
E. Location of test areas for field tests as follows:
1. Thickness: Select one bay per floor, or one bay for each 930 m 2
(10,000 square feet) of floor area, whichever provides for greater number of tests. Take thickness determinations from each of following locations: Metal deck, beam, and column.
2. Density: Take density determinations from each floor, or one test from each 930 m2 (10,000 square feet) of floor area, whichever provides for greater number of tests, from each of the following areas: Underside of metal deck, beam flanges, and beam web.
F. Submit inspection reports, certification, and instances of noncompliance to Resident Engineer.
3.18 NA
- - - E N D - - -
File details come from the government source that posted it. Updated .