About this file

This document contains a pre-solicitation notice and technical specifications for a federal contract opportunity to repair, install, inspect, test and decommission fire dampers at the Manhattan Veterans Affairs Medical Center in New York. Key details include that the project is a 100% set-aside for verified Veteran-Owned Small Businesses, with an estimated construction cost range of $200,000 to $500,000. The contractor shall provide all labor, materials, equipment and supervision to inspect and test approximately 350 fire dampers, and perform any necessary construction to access dampers. Deliverables include shop drawings, an inventory and location of all fire dampers, digital photographs and as-built drawings. The performance period is 360 calendar days from issuance of the notice to proceed. The point of contact is listed and a site visit will be held for prospective bidders. The solicitation is anticipated to be issued on August 27, 2021.

View the file

Other files for this federal contract opportunity

Other files attached to Z1DA--FIRE DAMPERS -Repair, Install, Inspect and Testing, newest first.
File Type Posted
Bid Sheet -36C24221B0065 Rev.pdf PDF
36C24221B0065 0004.docx DOCX document
Site Visit - Sign In 36C24221B0065 Fire Damper.pdf PDF
Bid Sheet -36C24221B0065.pdf PDF
36C24221B0065 0003.docx DOCX document
RFIs -36C24221B0065 Answers.pdf PDF
VA NOTICE OF LIMITATIONS ON SUBCONTRACTING CERTIFICATION.pdf PDF
36C24221B0065 0002.docx DOCX document
36C24221B0065 0001.docx DOCX document
015719Temp Env Cntrls 01-11 - Edited 121511.pdf PDF
010000 Gen Req 6-11- Edited -121311.pdf PDF
Fire Dampers Report - 2014.pdf PDF
015816 Temp Int Signage 08-11 Edited 121511.pdf PDF
017419 Const Waste management 09-10 edited 121511.pdf PDF
014529 Testing Lab Srvcs 05-09 - Edited - 121511.pdf PDF
Building 6.pdf PDF
Building 1.pdf PDF
DB Wage Determination dtd 10-22-2021.pdf PDF
014219 Ref Standards 09-11 - Edited - 121511.pdf PDF
36C24221B0065.docx DOCX document
Show all 20

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

11-08M

Repair Fire Dampers/Testing last edited 1/4/12

01 33 23 - 1

SECTION 01 33 23

SHOP DRAWINGS, PRODUCT DATA, AND SAMPLES

1-1. Refer to Articles titled SPECIFICATIONS AND DRAWINGS FOR CONSTRUCTION

(FAR 52.236-21) and, SPECIAL NOTES (VAAR 852.236-91), in GENERAL

CONDITIONS.

1-2. For the purposes of this contract, samples, test reports, certificates, and manufacturers' literature and data shall also be subject to the previously referenced requirements. The following text refers to all items collectively as SUBMITTALS.

1-3. Submit for approval, all of the items specifically mentioned under the separate sections of the specification, with information sufficient to evidence full compliance with contract requirements. Materials, fabricated articles and the like to be installed in permanent work shall equal those of approved submittals. After an item has been approved, no change in brand or make will be permitted unless:

A. Satisfactory written evidence is presented to, and approved by

Contracting Officer, that manufacturer cannot make scheduled delivery of approved item or;

B. Item delivered has been rejected and substitution of a suitable item is an urgent necessity or;

C. Other conditions become apparent which indicates approval of such substitute item to be in best interest of the Government.

1-4. Forward submittals in sufficient time to permit proper consideration and approval action by Government. Time submission to assure adequate lead time for procurement of contract - required items. Delays attributable to untimely and rejected will not serve as a basis for extending contract time for completion.

1-5. Submittals will be reviewed for compliance with contract requirements by Architect-Engineer, and action thereon will be taken by Resident

Engineer on behalf of the Contracting Officer.

1-6. Upon receipt of submittals, Architect-Engineer will assign a file number thereto. Contractor, in any subsequent correspondence, shall refer to this file and identification number to expedite replies relative to previously approved or disapproved submittals.

last edited 1/4/12

01 33 23 - 2

1-7. The Government reserves the right to require additional submittals, whether or not particularly mentioned in this contract. If additional submittals beyond those required by the contract are furnished pursuant to request therefor by Contracting Officer, adjustment in contract price and time will be made in accordance with Articles titled CHANGES

(FAR 52.243-4) and CHANGES - SUPPLEMENT (VAAR 852.236-88) of the

GENERAL CONDITIONS.

1-8. Schedules called for in specifications and shown on shop drawings shall be submitted for use and information of Department of Veterans Affairs and Architect-Engineer. However, the Contractor shall assume responsibility for coordinating and verifying schedules. The

Contracting Officer and Architect- Engineer assumes no responsibility for checking schedules or layout drawings for exact sizes, exact numbers and detailed positioning of items.

1-9. Submittals must be submitted by Contractor only and shipped prepaid.

Contracting Officer assumes no responsibility for checking quantities or exact numbers included in such submittals.

A. NA

B. Submittals will receive consideration only when covered by a transmittal letter signed by Contractor. Letter shall be sent via first class mail and shall contain the list of items, name of Medical Center, name of Contractor, contract number, applicable specification paragraph numbers, applicable drawing numbers (and other information required for exact identification of location for each item), manufacturer and brand, ASTM or Federal Specification Number (if any) and such additional information as may be required by specifications for particular item being furnished. In addition, catalogs shall be marked to indicate specific items submitted for approval.

1. A copy of letter must be enclosed with items, and any items received without identification letter will be considered "unclaimed goods" and held for a limited time only.

2. Each sample, certificate, manufacturers' literature and data shall be labeled to indicate the name and location of the Medical Center, name of Contractor, manufacturer, brand, contract number and ASTM or

Federal Specification Number as applicable and location(s) on project.

last edited 1/4/12

01 33 23 - 3

3. Required certificates shall be signed by an authorized representative of manufacturer or supplier of material, and by

Contractor.

C. NA

D. If submittal samples have been disapproved, resubmit new samples as soon as possible after notification of disapproval. Such new samples shall be marked "Resubmitted Sample" in addition to containing other previously specified information required on label and in transmittal letter.

E. Approved samples will be kept on file by the Resident Engineer at the site until completion of contract, at which time such samples will be delivered to Contractor as Contractor's property. Where noted in technical sections of specifications, approved samples in good condition may be used in their proper locations in contract work. At completion of contract, samples that are not approved will be returned to Contractor only upon request and at Contractor's expense. Such request should be made prior to completion of the contract. Disapproved samples that are not requested for return by Contractor will be discarded after completion of contract.

F. Submittal drawings (shop, erection or setting drawings) and schedules, required for work of various trades, shall be checked before submission by technically qualified employees of Contractor for accuracy, completeness and compliance with contract requirements. These drawings and schedules shall be stamped and signed by Contractor certifying to such check.

1. For each drawing required, submit one legible photographic paper or vellum reproducible.

2. Reproducible shall be full size.

3. Each drawing shall have marked thereon, proper descriptive title, including Medical Center location, project number, manufacturer's number, reference to contract drawing number, detail Section Number, and Specification Section Number.

4. A space 120 mm by 125 mm (4-3/4 by 5 inches) shall be reserved on each drawing to accommodate approval or disapproval stamp.

5. Submit drawings, ROLLED WITHIN A MAILING TUBE, fully protected for shipment.

last edited 1/4/12

01 33 23 - 4

6. One reproducible print of approved or disapproved shop drawings will be forwarded to Contractor.

7. When work is directly related and involves more than one trade, shop drawings shall be submitted to Architect-Engineer under one cover.

1-10. NA

1-11. The Contractor shall send a copy of the complete submittal directly to the COTR.

1-12. Samples for approval shall be sent to COTR, as directed.

- - - E N D - - -