013323 SHOP DRAWINGS.doc

DOC document 34 KB Posted

Attached to
6115--520-21-1-7039-0001 Project No 520-22-101 Generator Controls Upgrade
Solicitation number
36C25621R0040
Issued by

About this file

This document includes a federal contract solicitation and related project file. The solicitation is for generator controls upgrade services for the Gulf Coast Veterans Health Care System, with a project cost between $500,000 and $1,000,000. The solicitation will be issued as a 100% SDVOSB set-aside through RFP procedures. Interested offerors must check the beta.SAM website for the RFP release on or around January 12, 2021, with proposals due around February 10, 2021. The anticipated contract award date is approximately 30 days after receipt of proposals. The contract performance period is 120 calendar days from notice to proceed. The project location is the Gulf Coast Veterans Health Care System in Biloxi, Mississippi. Offerors must be registered and verified as an SDVOSB in the VetBiz registry and SAM database to be considered.

The related project file provides submittal requirements and processes for shop drawings, product data, samples and other submittals for a construction project. It specifies the project contact for submittals, labeling requirements, required approvals, resubmittal processes, handling of approved and disapproved samples, and other policies.

View the file

Other files

File Type Posted
36C25621R0040 0005.docx DOCX document
Dwg Site Plan - Overall Facility Layout.pdf PDF
36C25621R0040 0004.docx DOCX document
36C25621R0040 0003.docx DOCX document
WD General Decision No MS20210050 02-12-2021.pdf PDF
Register containing all RFI Inquiries _ Responses.docx DOCX document
36C25621R0040 0002.docx DOCX document
(2) Site Visit Sign-In Sheets - Proj 520-22-101.pdf PDF
36C25621R0040 0001.docx DOCX document
Generator Yard Plan sheet 2 of 2 dated 6-17-2020.pdf PDF
EXHIBIT F REQUEST FOR INFORMATION FORM.docx DOCX document
263214 ENGINE GENERATORS - 2000 KW.pdf PDF
EXHIBIT A PERFORMANCE RELEVANCY SURVEY.docx DOCX document
263623 AUTOMATIC TRANSFER SWITCHES.pdf PDF
DIAGRAM SINGLE-LINE UTILITY-TIE-FEEDER B dated 1-10-2011.pdf PDF
DIMENSION PRINT OUTLINE DRAWING KOHLER POWER SYSTEMS dated 11-5-2010.pdf PDF
EXHIBIT E SURETY FORM.docx DOCX document
DIMENSION PRINT OUTLINE DRAWING dated 11-5-2010.pdf PDF
EXHIBIT B PAST AND PRESENT PERFORMANCE QUESTIONNAIRE.docx DOCX document
EXHIBIT D CONTRACTOR EVALUATION FORM CONSTRUCTION SAFETY.docx DOCX document
DIAGRAM SINGLE-LINE OVERVIEW E1 OF 330 dated 1-10-2011.pdf PDF
DIMENSION PRINT STRUCTURE-BREAKER DATA dated 1-15-2010.pdf PDF
262726 WIRING DEVICES.doc DOC document
010000 GENERAL REQUIREMENTS.docx DOCX document
Location Plan sheet 1 of 2 dated 6-16-2020.pdf PDF
SUPPLEMENTAL INFORMATION - POWER COMMAND CONTROLLERS.pdf PDF
ICRA - Project 520-22-101.pdf PDF
017419 CONSTRUCTION WASTE MANAGEMENT.doc DOC document
VA CATEX - 520-22-101 GENERATOR SWITCH GEAR July 2020.pdf PDF
Drawing ES _ 102 PARTIAL SITE GUIDE PLAN _ NORTH.pdf PDF
36C25621R0040_2.docx DOCX document
Drawing ES _ 111 ELECTRICAL SERVICE EQUIPMENT YARD.pdf PDF
WD General Decision No. MS20210050 01-01-2021.docx DOCX document
260511 REQUIREMENTS FOR ELECTRICAL INSTALLATIONS.doc DOC document
EXHIBIT C SUBCONTRACTOR INFORMATION AND CONSENT.docx DOCX document
SITE VISIT MAP - Biloxi VA.pdf PDF
MP 110 FUEL OIL SYSTEM FOR SERVICE YARD AREA F.pdf PDF
DIAGRAM SINGLE-LINE GENS 1 _ 2 EXISTING dated 7-08-2009.pdf PDF
270511 REQ FOR COM INSTALL.doc DOC document
260526 GROUNDING AND BONDING FOR ELECTRICAL SYSTEMS.doc DOC document
260521 LOW VOLT CONDUCTORS.doc DOC document
Show all 41

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

03-01-12

SECTION 01 33 23

SHOP DRAWINGS, PRODUCT DATA, AND SAMPLES

1-1.

Refer to Articles titled SPECIFICATIONS AND DRAWINGS FOR CONSTRUCTION (FAR 52.236‑21) and, SPECIAL NOTES (VAAR 852.236-91), in GENERAL CONDITIONS.

1-2.

For the purposes of this contract, samples, test reports, certificates, and manufacturers' literature and data shall also be subject to the previously referenced requirements. The following text refers to all items collectively as SUBMITTALS.

1-3.

Submit for approval, all of the items specifically mentioned under the separate sections of the specification, with information sufficient to evidence full compliance with contract requirements. Materials, fabricated articles and the like to be installed in permanent work shall equal those of approved submittals. After an item has been approved, no change in brand or make will be permitted unless:

A.

Satisfactory written evidence is presented to, and approved by Contracting Officer, that manufacturer cannot make scheduled delivery of approved item or;

B.

Item delivered has been rejected and substitution of a suitable item is an urgent necessity or;

C.

Other conditions become apparent which indicates approval of such substitute item to be in best interest of the Government.

1-4.

Forward submittals in sufficient time to permit proper consideration and approval action by Government. Time submission to assure adequate lead time for procurement of contract ‑ required items. Delays attributable to untimely and rejected submittals will not serve as a basis for extending contract time for completion.

1-5.

Submittals will be reviewed for compliance with contract requirements by C.O.R., and action thereon will be taken by C.O.R. on behalf of the Contracting Officer.

1-6.

Upon receipt of submittals, C.O.R. will assign a file number thereto. Contractor, in any subsequent correspondence, shall refer to this file and identification number to expedite replies relative to previously approved or disapproved submittals.

1-7.

The Government reserves the right to require additional submittals, whether or not particularly mentioned in this contract. If additional submittals beyond those required by the contract are furnished pursuant to request therefor by Contracting Officer, adjustment in contract price and time will be made in accordance with Articles titled CHANGES (FAR 52.243‑4) and CHANGES ‑ SUPPLEMENT (VAAR 852.236‑88) of the GENERAL CONDITIONS.

1-8.

Schedules called for in specifications and shown on shop drawings shall be submitted for use and information of Department of Veterans Affairs. However, the Contractor shall assume responsibility for coordinating and verifying schedules. The Contracting Officer and C.O.R. assumes no responsibility for checking schedules or layout drawings for exact sizes, exact numbers and detailed positioning of items.

1-9.

Submittals must be submitted by Contractor only and shipped prepaid. Contracting Officer assumes no responsibility for checking quantities or exact numbers included in such submittals.

A.

Submit samples in single units unless otherwise specified. Submit shop drawings, schedules, manufacturers' literature and data, and certificates in quadruplicate, except where a greater number is specified.

B.

Submittals will receive consideration only when covered by a transmittal letter signed by Contractor. Letter shall be sent via first class mail or by e-mail and shall contain the list of items, name of Medical Center, name of Contractor, contract number, applicable specification paragraph numbers, applicable drawing numbers (and other information required for exact identification of location for each item), manufacturer and brand, ASTM or Federal Specification Number (if any) and such additional information as may be required by specifications for particular item being furnished. In addition, catalogs shall be marked to indicate specific items submitted for approval.

1.

A copy of letter must be enclosed with items, and any items received without identification letter will be considered "unclaimed goods" and held for a limited time only.

2.

Each sample, certificate, manufacturers' literature and data shall be labeled to indicate the name and location of the Medical Center, name of Contractor, manufacturer, brand, contract number and ASTM or Federal Specification Number as applicable and location(s) on project.

3.

Required certificates shall be signed by an authorized representative of manufacturer or supplier of material, and by Contractor.

C.

If submittal samples have been disapproved, resubmit new samples as soon as possible after notification of disapproval. Such new samples shall be marked "Resubmitted Sample" in addition to containing other previously specified information required on label and in transmittal letter.

D.

Approved samples will be kept on file by the C.O.R. at the site until completion of contract, at which time such samples will be delivered to Contractor as Contractor's property. Where noted in technical sections of specifications, approved samples in good condition may be used in their proper locations in contract work. At completion of contract, samples that are not approved will be returned to Contractor only upon request and at Contractor's expense. Such request should be made prior to completion of the contract. Disapproved samples that are not requested for return by Contractor will be discarded after completion of contract.

F.

Submittal drawings (shop, erection or setting drawings) and schedules, required for work of various trades, shall be checked before submission by technically qualified employees of Contractor for accuracy, completeness and compliance with contract requirements. These drawings and schedules shall be stamped and signed by Contractor certifying to such check.

1.

For each drawing required, submit one legible photographic paper or vellum reproducible.

2.

Reproducible shall be full size.

3.

Each drawing shall have marked thereon, proper descriptive title, including Medical Center location, project number, manufacturer's number, reference to contract drawing number, detail Section Number, and Specification Section Number.

4.

A space 120 mm by 125 mm (4‑3/4 by 5 inches) shall be reserved on each drawing to accommodate approval or disapproval stamp.

5.

Submit drawings, ROLLED WITHIN A MAILING TUBE, fully protected for shipment.

6.

One reproducible print of approved or disapproved shop drawings will be forwarded to Contractor.

7.

When work is directly related and involves more than one trade, shop drawings shall be submitted to C.O.R. under one cover.

1-10.

Samples, shop drawings, test reports, certificates and manufacturers' literature and data, shall be submitted for approval to project C.O.R.:

WILLIAM ROBERTS

PROJECTS DIRECTOR

VA GULF COAST VETERANS HEALTH CARE SYSTEM

BLDG. 10, ROOM 110B

400 VETERANS AVENUE

BILOXI, MS 39531-2410

‑ ‑ ‑ E N D ‑ ‑ ‑