MACC FREQUENTLY ASKED QUESTIONS
Question 1: Can an Offeror submit a CCASS evaluation for a project where they performed as a subcontractor?
Answer: Yes, but the CCASS evaluation should identify the name of the Subcontractor
(Offeror) in the evaluation and provide information to evaluate the Subcontractor’s (Offeror’s) performance on the project.
Question 2: Will the government allow Offerors to include previously completed Past
Performance Questionnaires from the same customer points of contact in lieu of new Past Performance Questionnaires? Can these be US Army Corps of Engineers surveys that have slightly different questions?
Answer: Yes, it is acceptable to submit previously completed Past Performance
Questionnaires, as long as the evaluations assign an overall rating and cover the same criteria as the PPQ form included with the RFP.
Question 3: Is a typed/electronic signature acceptable on a past performance questionnaire?
Answer: A typed signature is not acceptable. Acceptable signatures include handwritten signatures or digital signatures via Adobe (or similar). If the signature appears questionable, the evaluator may be contacted to verify the information.
Question 4: How many Past Performance Questionnaires can we submit for each project?
Answer: Only one past performance evaluation will be considered per project. If more than one past performance evaluation is included, only the first will be considered. Note that if a PPQ is provided but an evaluation is in the CPARS system, the CPARS evaluation supersedes the PPQ.
Question 5: Where can I obtain a list of examples of projects that are within the scope of this
MACC?
Answer: Examples of project types included within the scope of this MACC are identified in the RFP Section 00801 under the Description of Work. This is not an all-inclusive list of projects nor is it an indication of specific projects that will be procured under this MACC. The projects listed are a small sampling of the types of projects that may be included under this MACC.
Only projects within the NAICS code shown on the SF1442 are within the scope of this MACC. To view additional examples of the various project types that fall under that NAICS code, you can visit the following website and enter the appropriate NAICS code into the "2017 NAICS Search" field.
http://www.census.gov/cgi-bin/sssd/naics/naicsrch
Projects which are outside of the NAICS code shown on the SF1442 are not considered within the scope of this MACC and will not be considered for evaluation.
Question 6: If we are a JV firm, does each JV partner submit 5 projects or is it a total of 5 projects between the two firms?
Answer: As stated in the RFP, you can submit a combined maximum of five projects for the Joint Venture. This does not mean five projects for each JV partner. If more than five total projects are submitted for the evaluation of the JV firm, only the first five projects will be evaluated.
Question 7: Can the aggregate of a Job Order Contract count as a single project experience?
Answer: No. As stated in the RFP, PROJECT is defined as “A design-build or design-bid-build construction activity or task, with a single starting point and a single ending point.” COMBINED PROJECT(S) is defined as “Projects with multiple starting and ending points, performed under separate task orders, delivery orders, or multiple contracts combined in a single description. No credit will be given for work performed under MACC/IDIQ contracts in the aggregate, for multiple projects completed under more than one task/delivery order.”
Question 8: The Proposal Submission Requirements under the Experience factor provide a description of what defines a relevant project. Does that mean that in order to be considered relevant, the projects we submit need to meet those requirements, including the project construction cost minimum?
Answer: Yes. Projects outside of the relevant project description (defined in the
Experience factor proposal submission requirements) or that fall below the construction cost minimum will not be considered relevant.
Question 9: Can the dollar amounts shown on Exhibit B include escalation to today’s dollars to meet the relevant project construction cost noted in the proposal submission requirements for Experience?
Answer: No.
Question 10: The format for the proposal submittal is clearly outlined in the Instructions to
Offerors. Are we permitted to provide a Table of Contents in addition to the required documents before Tab 1?
Answer: As noted in Section 00100 (Instruction to Offerors) of the RFP, “Offerors are asked to submit only the information/exhibits required.” Any additional information submitted will not be evaluated.
Question 11: Can we include photos as part of the description of the project on Exhibit B?
Answer: Photos are not requested for Exhibit B and will not be evaluated. We recommend that you not alter the content or format of the Exhibits. Individual blocks on the Exhibits may be expanded; however, page limits, if stipulated, must be adhered to.
Question 12: On Form SF1442 block 14, what sort of code and facility code is it asking for?
Answer: You do not need to fill out the code or facility code. In Block 14, you only need to provide the Offeror name and address.
Question 13: Might the Offeror receive a higher score if a Joint Venture is proposed for the
Offeror? Might the Offeror receive a lower score if a Joint Venture is NOT proposed?
Answer: No. The JV is evaluated in the same way as any Offeror.
Question 14: We are current and up-to-date in the System for Award Management (SAM).
Does that suffice for the Representations and Certification clauses in Section 00600 of the RFP or do I still have to fill out those clauses and submit them with my proposal?
Answer: Offerors must complete and submit Section 00600 of the RFP as part of their proposal even if the Offeror is registered in SAM. Section 00600 of the RFP contains clauses which are not found in the electronic Reps & Certs in SAM;
therefore, we require them to be completed and submitted as part of your proposal.
Note: The clauses found in Section 00600 of the RFP are also broken out as a separate form titled “Section 00600 – Representations and Certifications” which can be found with the other RFP Exhibits.
Question 15: Will the Contract require the Offerors to propose on EVERY Task Order under the
MACC, or will we have the option to make a business decision on a case-by-case basis?
Answer: As stated in the RFP in Section 00803 (Task Order Issuance Procedures), “Each
Contractor is required to submit a reasonable number of good faith proposals for PTOs. Contractors are not obligated to propose on all Task Orders; however, they are required to contact the Contracting Officer within two days of notification if they cannot participate in the walk through or submit an offer.
Failure to provide this notification may impact future consideration for PTOs and exercise of an option.”
Question 16: Is there a minimum number of projects we should submit for Experience (Exhibit
B)?
Answer: Any required minimum number of projects will be stated in the Proposal
Submission Requirements for the Experience factor.
Question 17: Does one double-sided piece of paper count as one page or two pages when referring to page limits?
Answer: As stated in the RFP, PAGE is defined as “one printed side of a piece of paper.
(For example, 5 pieces of paper printed on both sides would result in 10 pages of narrative.)”
Question 18: Do the projects we submit under the Experience factor have to be completed by the RFP issuance date?
Answer: Yes. As stated in the RFP:
“Projects submitted for the Offeror shall be 100% complete (see definition) within the past five (5) years of the date of issuance of this RFP.”
“Projects submitted for the design team shall be 100% complete (see definition) within the past five (5) years of the date of issuance of this RFP.
For design-build projects, the design portion of the contract shall have been completed within the past five (5) years of the date of issuance of this RFP.”
The definition for “100% complete” is stated in the RFP as follows:
100% COMPLETE:
For construction projects: The facility is completely constructed and ready for the intended use.
For design projects: 100% plans and specifications signed off by an Architect-Engineer and ready for construction with final cost estimate.
Does not include any Post Construction Award Support (PCAS).
Question 19: I don’t have any employees who are Veterans. Do I still have to submit a VETS-
4212 report?
Answer: You are subject to the VETS-4212 Report reporting requirements if you have:
1. A current Government contract or subcontract in the amount of $150,000 or more that was entered into on or after October 1, 2015; or
2. A current Government contract or subcontract in the amount of $100,000 or more that was entered prior to October 1, 2015.
As stated in the Instructions to Offerors, “Upon the successful submission of a VETS-4212 report, federal contractors will receive an email confirmation of receipt notification for their records. Offerors shall include a copy of their confirmation notification email in their proposal as verification of submission. DO NOT SUBMIT A COPY OF THE REPORT ITSELF. If this requirement is not applicable to your firm, provide a statement that your firm does not have any contracts subject to this requirement.”
A contract cannot be awarded to a contractor that has not submitted a required annual form VETS-4212, Federal Contractor Veterans’ Employment Report (VETS-4212 Report) if subject to the reporting requirements of 38 U.S.C. 4212(d) for that fiscal year.
Question 20: If we are unable to obtain a completed PPQ from a client for one of our projects before the proposal due date, what do we need to include on the first page of the PPQ that we submit in the proposal for that project?
Answer: Offerors are strongly encouraged to include fully completed PPQs in their proposals. If, however, you are unable to obtain a completed PPQ from a client for a project, as stated in the RFP, “the Offeror should complete and submit with the proposal the first page of the PPQ, which will provide contract and client information for the respective project(s). The Government may make reasonable attempts to contact the client noted for that project(s) to obtain the PPQ information. However, Offerors should follow-up with clients/references to help ensure timely submittal of questionnaires.” When filling out and submitting the first page of the PPQ, you MUST COMPLETE BLOCKS 1 – 5, INCLUDING THE CLIENT CONTACT INFORMATION so that we know who to contact to attempt to obtain PPQ information.
Question 21: If the proposed design firm was the designer of record for the Offeror on a design-build project, could the Offeror complete the PPQ for the design firm?
Answer: The construction prime contractor can complete an evaluation for the design firm only if the construction prime contractor is not the Offeror or any other member of the Offeror’s team proposing on the contract, as identified in Factor 1 Technical Approach. Since the Offeror and other members of the Offeror’s team are considered interested parties to this solicitation, they should not complete the evaluation; however, the design firm can request the client/owner to provide an evaluation. Past performance evaluations that are completed by the Offeror (or any other member of the Offeror’s team) for any member of the Offeror’s team will not be considered.
Question 22: RFP Part 1, Factor 3: Past performance, a. Proposal Submission Requirements, states, specific to design projects: “If a completed AE Contractor Appraisal Support System (ACASS) or CPARS evaluation is available, it shall be submitted with the proposal for each project included in Factor 2 for design experience.”
Please confirm: If the Offeror was both the Prime Contractor and Designer of Record on a project, may the same CPARS evaluation be provided for both Construction and Design Experience – or – is it preferred that a PPQ also be provided?
Answer: In order for a CPARS evaluation of a Prime Contractor to also be considered for the Designer of Record (DOR), the CPARS evaluation must specifically address the DOR’s performance on the design portion of the project. If the CPARS evaluation does not specifically address the DOR’s performance on the design portion of the project, it will not be considered for the DOR. In that case, a PPQ should be submitted to demonstrate past performance of the DOR.
Question 23: RFP Part 1, Factor 3: Past performance, a. Proposal Submission Requirements, states, specific to design projects: “If a completed AE Contractor Appraisal Support System (ACASS) or CPARS evaluation is available, it shall be submitted with the proposal for each project included in Factor 2 for design experience.”
Please confirm: If the Offeror was both the Prime Contractor and Designer of Record on a project and the project featured meets the 100% design complete definition (but is not yet construction complete), will an Interim CPARS evaluation be considered acceptable, or is it preferred that a PPQ be provided?
Answer: An Interim CPARS evaluation submitted for the design portion of a project will only be considered if it specifically addresses the Designer of Record (DOR)’s performance on the completed design portion of the project. If the Interim CPARS evaluation does not specifically address the DOR’s performance on the design portion of the project, it will not be considered for the DOR. In that case, a PPQ should be submitted to demonstrate past performance of the DOR.