Design-Build Services for a Hydrogen Fueling Station

Closed State & local contract opportunity

Solicitation number
2026-RFP-0123
State
California
Responses due

Opportunity facts

Jurisdiction
Point of contact

Opportunity details come from procurement.opengov.com. Updated .

About this opportunity

The City of Pasadena is soliciting design-build-operate-maintain (DBOM) services for a hydrogen fueling station project through a competitive best-value selection process. The project involves designing, constructing, operating, and maintaining a stand-alone hydrogen fueling facility located at 159 South Kinneloa Avenue, Pasadena, California, that will utilize delivered liquid hydrogen (LH2) as the primary storage medium to support the city's planned fleet of fuel cell electric buses. The facility will include an 18,000-gallon gross capacity LH2 storage tank, two LH2 product pumps, two gaseous hydrogen (GH2) dispensers rated for H35 (350 bar) fills, vaporizers, chillers, priority-valve panels, GH2 storage vessels, a fixed LH2 offload pump, site improvements including paving, landscaping compliant with low-impact development standards, masonry fencing with automated gates, a fueling canopy, utility building with restrooms, backup generator with diesel tank, bus-parking canopy, and surveillance cameras. The Design-Builder must hold an active California Contractors State License Board license in Class A (General Engineering Contractor) or Class B (General Building Contractor), with lead architects and engineers holding active California licenses; demonstrate a minimum of five years in business; complete at least three prevailing wage public contracts in California and three similar projects valued at more than $8 million each within seven years; maintain an Experience Modification Rate (EMR) of 1.25 or less; possess bonding capacity exceeding the estimated direct cost; and demonstrate financial strength and a satisfactory safety record. The mandatory pre-proposal meeting is scheduled for April 23, 2026, at 10:00 AM, with questions due by May 22, 2026, at 2:00 PM, and proposals due June 8, 2026, at 2:00 PM. The estimated design phase will commence in July 2026 for six months, construction will begin in February 2027 and last approximately 20 months, with substantial completion required by September 2028 and full commissioning by December 2028. Evaluation criteria include experience and references (20 points), organization and key personnel qualifications (20 points), proposed approach and methodology (30 points), financial strength and stability (5 points), safety record/Experience Modification Rate (5 points), local Pasadena business preference (5 points), small or micro-business certification (5 points), price proposal using a ratio method (10 points), and interview scores (up to 50 points).

The procurement does not impose mandatory set-asides for disadvantaged enterprises but does provide preference scoring for small and micro-business certifications and local Pasadena business status. Proposers are required to complete the Design-Builder Qualification Statement, disclose all subcontractors whose work exceeds 0.5% of the total base bid or $10,000, and identify Disadvantaged Business Enterprise (DBE) and Small Business Enterprise (SBE) certifications for listed subcontractors. The project incorporates existing infrastructure and environmental considerations, including a Soil Management Plan addressing volatile organic compounds, semi-volatile organic compounds, and heavy metals identified in previous environmental investigations, along with a Health and Safety Plan complying with OSHA and California Code of Regulations. The geotechnical investigation and conceptual drawings prepared by Stantec Consulting Services and DiazYourman & Associates provide baseline technical requirements for design and construction. The project is funded in part by the California Energy Commission's Clean Transportation Program, EnergIIZe, and the California State Transportation Agency's Transit and Intercity Rail Capital Program (TIRCP), which impose federal compliance requirements including adherence to 2 CFR 200. The estimated cost of the design-build scope of work is $16,000,000, and proposals are limited to 75 total pages for technical components, with submission via the City's eProcurement Portal and six bound copies plus one unbound original delivered to the Department of Public Works within three business days of electronic submission.

Opportunity text

The City of Pasadena is seeking the services of a qualified design-build contractor ("Design-Builder" or "DB" or "Contractor" or "Proposer") to design, build, operate and maintain ("DBOM") a new stand-alone hydrogen-fueling station by requesting DB Qualification Statements, technical proposals, price proposals, and required completed forms and attachments in response to this RFP ("Proposals") from highly qualified and experience vendors with the capability, responsibility, experience, and accountability to design and construct a stand-alone hydrogen-fueling station that will use delivered liquid hydrogen ("LH2") as the primary storage medium that will support the City's planned fleet of fuel cell electric buses ("FCEBs") and described in greater detail in the City's Bridging Documents, and Design-Build Documents enumerated in the City's Standard Form of Agreement. The City is seeking a Design-Builder that excels in five (5) key areas: project experience, team composition, project approach and methodology, financial strength, and safety record, while also demonstrating a collaborative mindset to achieve optimal value within the City's Project budget and required schedule.

A Selection Committee shall review the Proposals received and, based on the criteria identified in the RFP, and complete final scoring, pursuant to the Pasadena Municipal Code ("P.M.C.") section 4.08.047, competitive selection, using the Design-Build alternative project delivery method. The Proposer recommended for award of the contract will be evaluated and determined on a best value basis, based on qualifications, organization/team composition, technical proposal, financial strength, safety record, local business, small business, price proposal, and interview scores.

The Project shall utilize a single-phased delivery process and award a Stipulated Sum Design-Build Contract.

The Project is funded, in part, by the California Energy Commission's Clean Transportation Program, EnergIIZe, and the California State Transportation Agency's Transit and Intercity Rail Capital Program ("TIRCP") grants, which requires Contractors and Subcontractors to follow TIRCP requirements as detailed in the Design-Build Documents, which include compliance with 2 CFR 200 for Proposals and and the Contract, Generally Accepted Accounting Principles, audit, record retention, reporting, and non-discrimination.

Project Timeline

Estimated Cost of Design-Build Scope of Work

$16,000,000

Estimated Commencement of Design Phase (6 month duration)

July 2026

Estimated Notice to Proceed (NTP)- Construction Work Commencement (20 month duration)

February 2027

Construction Work Substantial Completion (Partial Occupancy or Use)*

September 2028

Construction Work/Commissioning Complete*

December, 2028

*The Project must reach Substantial Completion by No Later Than ("NLT") September 2028 to ensure a seamless transition and uninterrupted operation of Pasadena Transit's services.

Files

File Type Posted
Design-Build_Services_for_a_Hydrogen_Fueling_Station_(Addendum_#11_Revision).pdf PDF
Hydrogen_Fueling_Agreement_General_Conditions_Exhibits_and_Appendices.pdf PDF
Design-Build_Services_for_a_Hydrogen_Fueling_Station_(Addendum_#9_Revision).pdf PDF
Design-Build_Services_for_a_Hydrogen_Fueling_Station_(Addendum_#8_Revision).pdf PDF
AA_Price_Proposal.xlsx XLSX spreadsheet
Design-Build_Services_for_a_Hydrogen_Fueling_Station_(Addendum_#3_Revision).pdf PDF
Insurance_Requirements.pdf PDF
Design-Build_Services_for_a_Hydrogen_Fueling_Station.pdf PDF
[I]_-_Insurance_Requirements.pdf PDF
DESIGNATED_REPRESENTATIVESdocx.pdf PDF
DESIGNATED_REPRESENTATIVESdocx.pdf PDF
Proof_of_Authority.pdf PDF
AFFIDAVIT_OF_JOINT_VENTURE.pdf PDF
Civil_Litigation_History_Certification_ver02.pdf PDF
Civil_Litigation_History_Certification_ver02.pdf PDF
Declaration_of_Elibility_to_Contract_(not_debarred).pdf PDF
Public_Contract_Code_Disclosure.pdf PDF
Indemnity_Agreement_Form.pdf PDF
AFFIDAVIT_OF_JOINT_VENTURE.pdf PDF
Declaration_of_Elibility_to_Contract_(not_debarred).pdf PDF
Price_Proposal.xlsx XLSX spreadsheet
Public_Contract_Code_Disclosure.pdf PDF
DB_Qualificiation_Statement_FINAL.docx DOCX document
Proof_of_Authority.pdf PDF
Indemnity_Agreement_Form.pdf PDF
Subcontractor_Listing.pdf PDF
Price_Proposal.xlsx XLSX spreadsheet
Subcontractor_Listing.pdf PDF
DB_Qualificiation_Statement_FINAL.docx DOCX document
CONFLICT_OF_INTEREST_(5).pdf PDF
Pasadena_Taxpayer_Protection_Amendment_Disclosure_(2).pdf PDF
DISQUALIFICATION_DISCLOSURE_(4).pdf PDF
CONFLICT_OF_INTEREST_(5).pdf PDF
Pasadena_Taxpayer_Protection_Amendment_Disclosure_(2).pdf PDF
REQUIRED_FORMS_-_AAs_-_SIG-LEGAL-STATUS_-_DECLARATION_OF_NONCOLUSION_08022024_v2.pdf PDF
DISQUALIFICATION_DISCLOSURE_(4).pdf PDF
REQUIRED_FORMS_-_AAs_-_SIG-LEGAL-STATUS_-_DECLARATION_OF_NONCOLUSION_08022024_v2.pdf PDF
Health_and_Safety_Plan.pdf PDF
Health_and_Safety_Plan.pdf PDF
City's_Standard_Form_(Traditional)_Design-Build_Agreement.pdf PDF
City's_Standard_Form_(Traditional)_Design-Build_Agreement.pdf PDF
Soil_Management_Plan.pdf PDF
Geotechnical_Report.pdf PDF
Geotechnical_Report.pdf PDF
Soil_Management_Plan.pdf PDF
Project_Manual.pdf PDF
Conceptual_Drawings.pdf PDF
Project_Manual.pdf PDF
Conceptual_Drawings.pdf PDF
Emergency_FEMA_TC.pdf PDF
Show 40 more

50 files listed here. See the rest on GovTribe.

On GovTribe

Work this opportunity

  • Track it in your pipeline
  • Similar opportunities
  • Ask GovTribe AI about this opportunity