Z1DA--NRM-CONST | 528A7-19-720 | Repair SPS Deficiencies

Closed Solicitation Posted

Solicitation number
36C24226B0029
Agency
Responses due
Set-aside
No set-aside

Opportunity facts

Notice details come from SAM.gov. Updated .

About this opportunity

The Department of Veterans Affairs Veterans Health Administration Veterans Integrated Service Network 2 seeks sealed bids for repair of Sterile Processing Service deficiencies at Syracuse VA Medical Center, with bids due May 29, 2026, at 2:00 PM EDT and opening at 2:15 PM the same day via Microsoft Teams. This is a 100 percent Service-Disabled Veteran-Owned Small Business (SDVOSB) set-aside.

Place of performance is Syracuse, New York (800 Irving Avenue, Syracuse, NY 13210). The project is divided into five sequential phases totaling 550 calendar days from Notice to Proceed: 120 calendar days for submittals and 430 calendar days for construction. Work includes repairing and replacing noncompliant ceilings, floors, and walls with seamless, cleanable impervious materials; creating full separation between cleaning and preparation areas; installing a pass-through window with vented cabinet; relocating endoscope processing; constructing a cool-down room; installing automated doors; and removing, storing, and reinstalling existing equipment including sterilizers, washers, and cart washers with stainless steel trim. Climate control must maintain 68°F ±2°F and 40% ±5% relative humidity during stored equipment periods. Contractors are responsible for all utility disconnections and reconnections (steam, air, water, reverse osmosis water, data, electrical, drains) and drain repairs. The contractor must include temporary SPS trailer rental and rigging in the bid; crane operations are limited to one consecutive day with picks only on weekends or after-hours. No designated laydown areas exist on-site; contractors have access to one dumpster or one parking spot only. The government will not reimburse stored material costs and will not accept material submissions beyond the initial performance period.

The project magnitude is between $1,000,000 and $5,000,000. NAICS code is 236220, General Contractors. A bid bond of 20 percent of bid price (not to exceed $3,000,000) is required for bids exceeding $150,000. New York State sales tax exemption applies to construction materials incorporated into VA real property; contractors must complete Form ST-13. All bids must remain valid for 120 calendar days after submission. Electronic bids are emailed to terry.fraser@va.gov; no hand-carried or mailed bids are accepted. Bids must include acknowledgment of all amendments, completed FAR 52.225-2 Buy America Certificate, completed VA Notice of Limitations in Subcontractors Compliance Certificate (852.219-75), verified SBA SDVOSB certification, and proof of VETS 4212 Federal Contractor compliance. Performance and payment bonds are required upon award. Apco Signs is the basis of design for signage and is not sole source.

Notice text

9 versions

Update #9 · Latest ·

Page 4 of 4

INSTRUCTIONS, CONDITIONS AND OTHER STATEMENTS TO BIDDERS/OFFERORS

2.1 BID OPENING INFORMATION

In accordance with FAR 14.202-8, the government is authorizing electronic bids on this solicitation. ALL bids shall be emailed to terry.fraser@va.gov Contracting Officer and timestamped by May 29, 2026, at 2:00pm EST prior to the bid opening time. The bids shall include copies of a bid bond. The bid opening shall take place on May 29, 2026, at 2:15pm EST. No hand-carried or mailed bids will be accepted.

The bid opening will take place via Microsoft Teams conference call. To access the conference, please access:

To join by phone please dial 1-347-566-4838

Phone conference ID: 196 379 950#

2.2 Special Notes regarding FAR 52.229-3: Federal, State and Local Taxes:Â Â

Offerors are hereby notified that under the New York Statutes Annotated, 54:32B-9 (2), the United States of America, any of its agencies and instrumentalities, are not subject to sales or use tax  when it is the purchaser, user, or consumer of personal property. Pursuant to New York Administrative Code § 18:24-5.3,  a contractor s purchase of such building and construction materials within the State of New York to be incorporated into the real property belonging to the U.S. Department of Veterans Affairs (VA) is subject to the exemption from the state of New York sales tax. To take advantage of the tax exemption the successful offeror under this solicitation must complete FORM ST-13 Contractor s Exempt Purchase Certificate when it purchases construction materials for this contract and keep on file as required by the state of New York tax laws.Â

 Notwithstanding FAR 52.229-3, all bids received in response to this solicitation are presumed to reflect this tax exemption and therefore should not include the state of New York sales tax for incorporation into VA real estate under this contract.Â

1.1 BID PRICING SHEET

Bids providing less that 120 Calendar Days of Government Acceptance after the date bids are due will not be considered and will be rejected.

The bidder agrees to perform the work required at the prices specified below in strict accordance with the terms of the solicitation, if this bid is accepted by the Government in writing within 120 calendar days after the date bidders are due.

BASE BID

A. ITEM I, GENERAL CONSTRUCTION: BASE BID: Work includes general construction, electrical and Fire alarm upgrades and certain other items.

The Contract period of performance for Base Bid construction shall be 550 calendar days from Notice to Proceed (NTP).

Base Bid $ ___________________________

Offers shall provide a complete package to include the completed bid sheet along with the following to be determined responsive, responsible, and considered for award:

Bid Bond and associated documents on correct forms.

Acknowledgement of all amendments.

Completed 52.225-2 Buy America Certificate.

Completed 852.219-75 VA Notice of Limitations in Subcontractors Compliance Certificate.

Verified/visible/certified on the Small Business Administration Certification on SBA - Dynamic Small Business Search.

Proof of compliance with VETS 4212 Federal Contractor Reporting.

(a) Bidding materials consisting of Invitation for Bids, drawings, specifications and contract forms will be available on https://beta.sam.gov/ in electronic format only by searching for solicitation number 36C24226B0029. All interested parties (subs & primes) should register at https://beta.sam.gov/ as an Interested Vendor so that others will know of our interest in participating in this procurement. A Bidder s mailing list WILL NOT BE prepared by the Contract Specialist. SOLICITATION AMENDMENTS: Amendments to the solicitation will be posted at SAM.gov/. Paper copies of the amendments will NOT be individually mailed. By registering to Receive Notification , you will be notified by e-mail of any new amendments that have been issued and posted. No other notification of amendments will be provided. Bidders are reminded that they are responsible for obtaining and acknowledging all amendments to this solicitation prior to the time for receipt of bids.

(b) If bid exceeds $150,000 a bid bond must be submitted. A bid guarantee is required in an amount not less than 20 percent of the bid price but shall not exceed $3,000,000. Failure to furnish the required bid guarantee in the proper form and amount, by the time set for opening of bids, will require rejection of the bid in all cases except those listed in FAR 28.101-4, and may be cause for rejection even then.

(c) If the contract will exceed $150,000 (see FAR 28.102-1 for lesser amount), the bidder to whom award is made will be required to furnish two bonds, a Payment Bond, SF 25A, and a Performance Bond, SF 25, each in the penal sum as noted in the General Conditions of the Specification. Copies of SFs 25 and 25A may be obtained upon application to the issuing office.

(d) If the bid is between $30,000 - $150,000. The bidder to whom award is made will be required to furnish a Payment Bond, Standard Form 25A or alternative payment protection which conforms to the requirements set forth in FAR Clause 52.228-13, Alternative Payment Protections, as noted in the General Conditions of this Specification. Copies of the Standard Form of Payment Bond may be obtained upon application to the Issuing Office.

DESCRIPTION OF WORK: GENERAL CONSTRUCTION: The Contractor shall furnish all necessary professional Construction services to provide complete scope of work for Project 528A7-19-720 in accordance with the project drawings and specifications for the Albany VAMC.

Magnitude of Construction: $1,000,000 and $5,000,000

Update #8 ·

Bid Update

Solicitation: 36C24226B0029/Project: 528A7-19-720 Repair SPS Deficiencies

Answered By: Emery P. Gasparek Jr; Jim Granier Date: 04-28-2026.

Is there a lay-down area designated for this project?

Answer: There are no designated laydown areas on the drawings. AHU-2., Limited space on roof near Temp Unit, and limited space on 10th floor near AHU-2 area. AHU-11, Limited Space on Shaft 5 Roof, and inside near unit. AHU-7 extremely limited space inside Shaft 2, near units. There is nothing on drawings showing any pre-determined areas so contractors should assume no laydown area permitted.

Is parking available for contractors on-site?

Answer: No. One dumpster or one parking spot.

Due to volatile material price fluctuations and unpredictability of the market, will the government agree to pay for Stored Materials on this project to avoid price increases post bid? Documentation of material invoice/packing slips, photo, and insurance backup information for each relevant charge would be provided.

Answer: No

If a project runs past initial period of performance, can material costs be submitted then? Supplier & Manufacturers don t wait to bill, having to hold/extend carrying these costs puts an extreme burden on contractors.

Answer: No

Section 28 13 00: Physical Access Control System is missing from project

specifications.

Answer: Will include

3/AS-902 mentions Apco Signs. Is Apco sole source, or can other sign manufacturers be

utilized?

Answer: Apco is the Basis of Design for the hospital

Confirm temp SPS trailer is in GC contract.

Answer: Yes it is to be included in the Bid

Please define GC responsibility for remove, storage, and reinstallation of existing equipment. For example, built-in units (washers, cart washers, and sterilizers) have

stainless steel trim surrounds, in-wall and floor utility connections. Will vendors make disconnections and package these units for storage?

Answer:

- VA will have Equipment MFG s shut down and secure equipment.

-Contractor will disconnect all utilities.

-Contractor will move equipment to Contractor s warehouse for storage.

-Contractor will store in warehouse for the duration of Phase 2.

-Contractor will move equipment back to VA or install new Identical Equipment.

-Contraction will make all utility connects to equipment including but not limited to (Steam, Air , Water, RO Water, Data, Electrical, and Drains).

-All Stainless Panels near Sterilizers are to be removed and re-installed by Contractor. This includes fitment to new Sterilizers.

-VA will have all Equipment new or used Started up and Commissioned by MFG s.

What are climate control requirements for the equipment?

Answer: Temperature 68 degrees +/- 2; Humidity 40% +/- 5%

Who is responsible for utility connections on reinstallation?

Answer: Contractors Bidding this Project

Who is responsible for reinstalling stainless trim surrounds?

Answer: Contractors Bidding this Project

At site visit, we were told the cart washer drain is leaking. This equipment is to remain,

and the drain seems to be underneath the unit who is responsible for

disassembling and reassembling the unit for drain work?

Answer: Contractors Bidding this Project

Who is responsible for providing the commissioning agent, the VA or general contractor?

Answer: Contractor is responsible for commissioning all aspects of project except for the equipment. VA will commission all equipment

Will there be specific haul routes required for ingress of materials and equipment and/or egress of removed equipment and debris?

Answer: Contractor to decide, however, there are specific requirements with moving materials through Patient Care areas including moving materials off hours. All carts and materials/debris are required to be covered. Each area was walked during the site visit. See drawings and specs for additional details

How many consecutive days would crane be allowed to stay set up?

Answer: One day. All Crane picks are performed on weekends or after hours with Contractors providing all supervision, safety, and associated required personnel. A required Crane Permit is required to be submitted by Contractor to VA for approval.

Confirm temp SPS trailer rental and rigging is to be included in GC contract

Answer: Contractors Bidding this Project need to include this in their Bid

Please define GC responsibility for remove, storage, and reinstallation of existing equipment.

-Built-in units (washers, cart washers, and sterilizers) have stainless steel trim surrounds,

Answer: the Cart Washer does not get moved and has to be protected in place by Contractors bidding this Project. Contractors bidding this Project are required to repair the leaking drain under the Cart Washer which requires the disconnect and removal of some piping and components which are in the Scope of this Project by Contractors bidding this Project. All other built-in units will be including Stainless Steel Surrounds, removing, moving to storage, storage, and re-installation are the responsibility of Contractors bidding this Project. VA will have Equipment MFG s shut down and secure equipment. Before it is to be moved. All other Mechanical, Electrical and other work is the responsibility of contractors bidding this Project.

Built In Units and Sterilizers are in the Scope of this Project, and Contractor bidding this Project are required to include it.

-in-wall and floor utility connections.

Answer: Contractors Bidding this Project are responsible for this work

Will vendors make disconnections and package these units for storage?

Answer: NO Contractors Bidding this Project need to include this in their Bid. VA will have Equipment MFG s shut down and secure equipment. Before it is to be moved.

What are climate control requirements for the equipment?

Answer: Temperature 68 degrees +/- 2; Humidity 40% +/- 5%

Who is responsible for utility connections on reinstallation?

Answer: Contractors Bidding this Project

Who is responsible for reinstalling stainless trim surrounds?

Answer: Contractors Bidding this Project

At site visit we were told the cart washer drain is leaking. This equipment is to-remain, and the drain seems to be underneath the unit who is responsible for disassembling and reassembling the unit for drain work?

Answer: the Cart Washer does not get moved and has to be protected in place by Contractors bidding this Project. Contractors bidding this Project are required to repair the leaking drain under the Cart Washer which requires the disconnect and removal of some piping and components which are in the Scope of this Project by Contractors bidding this Project.

Please provide full-size drawings, drawings released on SAM are 8.5 x 11 .

Answer: Provided.

Requesting an extension due to lack of full size drawings.

Answer: Bid date extended to 5/15/26

STEP 1 Contractors can open the drawings and select Print as a PDF

STEP 2 Â Click Page Set-up in lower left corner and select the size they want to plot. Save it and plot the larger PDF

On plan page AS-801-AD there are three openings which state the existing doors are to be removed, stored, cleaned and reinstalled. These are units #78-1, 84 and 85. That same comment states to provide new hardware. May I assume the frames will also be ETR and only price the hardware? Please confirm and thank you again.

Answer: Price Only the Hardware

I am looking at the door types on plan page AS-801-AD and they have referenced some which do not exist. If you look at the door type column several of the units are listed as 2F or 2T. These codes do not relate to the door elevations. Please reach out to the architect and send answers as soon as possible, so I may keep moving ahead on this one. Thanks!

Answer: 2F should be Metal; 2T should be Wood DISREGARD THIS ANSWER

Specifically, Door Type 2 appears to correspond to a consistent door elevation (narrow lite vision panel), with the suffix F or T potentially indicating glazing type (fire-rated vs. tempered), rather than door material. Additionally, the current clarification results in changes to door materials that may not align with the indicated fire ratings, hardware groups, and typical use conditions.

Answer: F or T indicates glazing type (fire-rated vs. tempered) use Door Schedule for Door Material

Update #7 ·

Final Bid RFI Update

Solicitation: 36C24226B0029/Project: 528A7-19-720 Repair SPS Deficiencies

Answered By: Emery P. Gasparek Jr; Jim Granier Date: 04-28-2026.

Is there a lay-down area designated for this project?

Answer: There are no designated laydown areas on the drawings. AHU-2., Limited space on roof near Temp Unit, and limited space on 10th floor near AHU-2 area. AHU-11, Limited Space on Shaft 5 Roof, and inside near unit. AHU-7 extremely limited space inside Shaft 2, near units. There is nothing on drawings showing any pre-determined areas so contractors should assume no laydown area permitted.

Is parking available for contractors on-site?

Answer: No. One dumpster or one parking spot.

Due to volatile material price fluctuations and unpredictability of the market, will the government agree to pay for Stored Materials on this project to avoid price increases post bid? Documentation of material invoice/packing slips, photo, and insurance backup information for each relevant charge would be provided.

Answer: No

If a project runs past initial period of performance, can material costs be submitted then? Supplier & Manufacturers don t wait to bill, having to hold/extend carrying these costs puts an extreme burden on contractors.

Answer: No

Section 28 13 00: Physical Access Control System is missing from project

specifications.

Answer: Will include

3/AS-902 mentions Apco Signs. Is Apco sole source, or can other sign manufacturers be

utilized?

Answer: Apco is the Basis of Design for the hospital

Confirm temp SPS trailer is in GC contract.

Answer: Yes it is to be included in the Bid

Please define GC responsibility for remove, storage, and reinstallation of existing equipment. For example, built-in units (washers, cart washers, and sterilizers) have

stainless steel trim surrounds, in-wall and floor utility connections. Will vendors make disconnections and package these units for storage?

Answer:

- VA will have Equipment MFG s shut down and secure equipment.

-Contractor will disconnect all utilities.

-Contractor will move equipment to Contractor s warehouse for storage.

-Contractor will store in warehouse for the duration of Phase 2.

-Contractor will move equipment back to VA or install new Identical Equipment.

-Contraction will make all utility connects to equipment including but not limited to (Steam, Air , Water, RO Water, Data, Electrical, and Drains).

-All Stainless Panels near Sterilizers are to be removed and re-installed by Contractor. This includes fitment to new Sterilizers.

-VA will have all Equipment new or used Started up and Commissioned by MFG s.

What are climate control requirements for the equipment?

Answer: Temperature 68 degrees +/- 2; Humidity 40% +/- 5%

Who is responsible for utility connections on reinstallation?

Answer: Contractors Bidding this Project

Who is responsible for reinstalling stainless trim surrounds?

Answer: Contractors Bidding this Project

At site visit, we were told the cart washer drain is leaking. This equipment is to remain,

and the drain seems to be underneath the unit who is responsible for

disassembling and reassembling the unit for drain work?

Answer: Contractors Bidding this Project

Who is responsible for providing the commissioning agent, the VA or general contractor?

Answer: Contractor is responsible for commissioning all aspects of project except for the equipment. VA will commission all equipment

Will there be specific haul routes required for ingress of materials and equipment and/or egress of removed equipment and debris?

Answer: Contractor to decide, however, there are specific requirements with moving materials through Patient Care areas including moving materials off hours. All carts and materials/debris are required to be covered. Each area was walked during the site visit. See drawings and specs for additional details

How many consecutive days would crane be allowed to stay set up?

Answer: One day. All Crane picks are performed on weekends or after hours with Contractors providing all supervision, safety, and associated required personnel. A required Crane Permit is required to be submitted by Contractor to VA for approval.

Confirm temp SPS trailer rental and rigging is to be included in GC contract

Answer: Contractors Bidding this Project need to include this in their Bid

Please define GC responsibility for remove, storage, and reinstallation of existing equipment.

-Built-in units (washers, cart washers, and sterilizers) have stainless steel trim surrounds,

Answer: the Cart Washer does not get moved and has to be protected in place by Contractors bidding this Project. Contractors bidding this Project are required to repair the leaking drain under the Cart Washer which requires the disconnect and removal of some piping and components which are in the Scope of this Project by Contractors bidding this Project. All other built-in units will be including Stainless Steel Surrounds, removing, moving to storage, storage, and re-installation are the responsibility of Contractors bidding this Project. VA will have Equipment MFG s shut down and secure equipment. Before it is to be moved. All other Mechanical, Electrical and other work is the responsibility of contractors bidding this Project.

Built In Units and Sterilizers are in the Scope of this Project, and Contractor bidding this Project are required to include it.

-in-wall and floor utility connections.

Answer: Contractors Bidding this Project are responsible for this work

Will vendors make disconnections and package these units for storage?

Answer: NO Contractors Bidding this Project need to include this in their Bid. VA will have Equipment MFG s shut down and secure equipment. Before it is to be moved.

What are climate control requirements for the equipment?

Answer: Temperature 68 degrees +/- 2; Humidity 40% +/- 5%

Who is responsible for utility connections on reinstallation?

Answer: Contractors Bidding this Project

Who is responsible for reinstalling stainless trim surrounds?

Answer: Contractors Bidding this Project

At site visit we were told the cart washer drain is leaking. This equipment is to-remain, and the drain seems to be underneath the unit who is responsible for disassembling and reassembling the unit for drain work?

Answer: the Cart Washer does not get moved and has to be protected in place by Contractors bidding this Project. Contractors bidding this Project are required to repair the leaking drain under the Cart Washer which requires the disconnect and removal of some piping and components which are in the Scope of this Project by Contractors bidding this Project.

Please provide full-size drawings, drawings released on SAM are 8.5 x 11 .

Answer: Bring this up to the Contracting Officers attention

Requesting an extension due to lack of full size drawings.

Answer: Bring this up to the Contracting Officers attention

Full size drawings sent along with work around below

STEP 1 Contractors can open the drawings and select Print as a PDF

STEP 2 Â Click Page Set-up in lower left corner and select the size they want to plot. Save it and plot the larger PDF

On plan page AS-801-AD there are three openings which state the existing doors are to be removed, stored, cleaned and reinstalled. These are units #78-1, 84 and 85. That same comment states to provide new hardware. May I assume the frames will also be ETR and only price the hardware? Please confirm and thank you again.

Answer: Price Only the Hardware

I am looking at the door types on plan page AS-801-AD and they have referenced some which do not exist. If you look at the door type column several of the units are listed as 2F or 2T. These codes do not relate to the door elevations. Please reach out to the architect and send answers as soon as possible, so I may keep moving ahead on this one. Thanks!

Answer: 2F should be Metal; 2T should be Wood DISREGARD THIS ANSWER

Specifically, Door Type 2 appears to correspond to a consistent door elevation (narrow lite vision panel), with the suffix F or T potentially indicating glazing type (fire-rated vs. tempered), rather than door material. Additionally, the current clarification results in changes to door materials that may not align with the indicated fire ratings, hardware groups, and typical use conditions.

Answer: F or T indicates glazing type (fire-rated vs. tempered) use Door Schedule for Door Material

Amendment 6; Attachment VA+SYRACUSE+SPS++Drawings++2

Drawing PD-101.1 marked Reference Only Use Addendum Sheet

No addendum sheet found. Please provide.

Answer: PD-101.1 was mistakenly Marked as an Addendum Sheet should have been PD-101.2. New drawings attached

Amendment 6:Â Â Found in attachment VA+SYRACUSE+SPS++Drawings++2 AND VA+SYRACUSE+SPS++Drawings++4

Drawing PD-101.2 is included twice in documents. The work shown is different. Neither is marked Reference Only Use Addendum Sheet . It is unclear what to bid. Please clarify.

Answer: PD-101.2 is an Addendum drawing which was included. The two attached drawings clarify this issue. Related to question 23 above

Multiple contractors have expressed confusion and concern with drawings marked Reference Only Use Addendum Sheet .Â

Can the VA clarify why they are included if they are being replaced with other drawings?

Answer: There were changes required

b. If we are not to use them, can they be removed and one complete drawing set provided to avoid confusion?

Answer: No, they are for reference.

Amendment 6 RFI Answer 17: The Cart Washer does not get moved and has to be protected in place by Contractors bidding this Project. Contractors bidding this Project are required to repair the leaking drain under the Cart Washer which requires the disconnect and removal of some piping and components which are in the Scope of this Project by Contractors bidding this Project.

The response provided does not adequately define or quantify the required scope of work for bidding purposes under this firm fixed-price contract. Additional information is required to establish an accurate takeoff and pricing, including, but not limited to: piping material type, pipe size, estimated linear footage of repair/replacement, existing drain conditions, required demolition limits, and clarification as to whether the existing drain is to be repaired partially or replaced in its entirety. Detailed drawings and/or a clearly defined scope of work should be provided.

Answer: From the Solicitation Narrative, The (3) drains for the pass thru Sterilizers and the (1) drain for the existing Cart Washer need to be repaired to stop them from leaking. This includes work on the floor below in the generator room and electrical substation area. Minimum scope of work includes:

a. Hand chipping around each drain perimeter

b. Cleaning surrounding area

c. Resealing existing drain to existing concrete

d. Replacing drain piping/fittings that are rotted and leaking

e. Replacing drain if it is damaged during repairs

Adding the following additional information:

f. Contractor to include 10 LF of drain piping , one elbow, one coupling for each drain

g. VA will remove all Cart Washer ancillary equipment to expose drain area for repairs

Question 5: Drawing set VA+SYRACUSE+SPS++Drawings++4 identifies Fellenzer Engineering LLP as the Engineer of Record; however, the revised/addendum sheets do not appear to bear an engineer s stamp/signature. The previous sheets marked Reference Only Use Addendum Sheet contain the Engineer of Record stamp, but the corresponding replacement sheets in Drawing Set ++4 do not.

Please clarify whether the revised/addendum sheets were intentionally issued without an Engineer of Record stamp and confirm that these drawings were reviewed and approved for bidding and construction use.

Answer: The VA reserves the right to modify drawings as they see fit. All changes were made prior to this solicitation, and with any drawing that was changed to PE stamp was removed as a result. Additionally, the VA has the right to issue drawings or projects without stamped drawings It is not within the Contractors right to question if the drawings have been reviewed or approved.

Update #6 ·

Page 4 of 4

INSTRUCTIONS, CONDITIONS AND OTHER STATEMENTS TO BIDDERS/OFFERORS

2.1 BID OPENING INFORMATION

In accordance with FAR 14.202-8, the government is authorizing electronic bids on this solicitation. ALL bids shall be emailed to terry.fraser@va.gov Contracting Officer and timestamped by May 26, 2026, at 2:00pm EST prior to the bid opening time. The bids shall include copies of a bid bond. The bid opening shall take place on May 26, 2026, at 2:15pm EST. No hand-carried or mailed bids will be accepted.

The bid opening will take place via Microsoft Teams conference call. To access the conference, please access:

To join by phone please dial 1-347-566-4838

Phone conference ID: 196 379 950#

2.2 Special Notes regarding FAR 52.229-3: Federal, State and Local Taxes:Â Â

Offerors are hereby notified that under the New York Statutes Annotated, 54:32B-9 (2), the United States of America, any of its agencies and instrumentalities, are not subject to sales or use tax  when it is the purchaser, user, or consumer of personal property. Pursuant to New York Administrative Code § 18:24-5.3,  a contractor s purchase of such building and construction materials within the State of New York to be incorporated into the real property belonging to the U.S. Department of Veterans Affairs (VA) is subject to the exemption from the state of New York sales tax. To take advantage of the tax exemption the successful offeror under this solicitation must complete FORM ST-13 Contractor s Exempt Purchase Certificate when it purchases construction materials for this contract and keep on file as required by the state of New York tax laws.Â

 Notwithstanding FAR 52.229-3, all bids received in response to this solicitation are presumed to reflect this tax exemption and therefore should not include the state of New York sales tax for incorporation into VA real estate under this contract.Â

1.1 BID PRICING SHEET

Bids providing less that 120 Calendar Days of Government Acceptance after the date bids are due will not be considered and will be rejected.

The bidder agrees to perform the work required at the prices specified below in strict accordance with the terms of the solicitation, if this bid is accepted by the Government in writing within 120 calendar days after the date bidders are due.

BASE BID

A. ITEM I, GENERAL CONSTRUCTION: BASE BID: Work includes general construction, electrical and Fire alarm upgrades and certain other items.

The Contract period of performance for Base Bid construction shall be 550 calendar days from Notice to Proceed (NTP).

Base Bid $ ___________________________

Offers shall provide a complete package to include the completed bid sheet along with the following to be determined responsive, responsible, and considered for award:

Bid Bond and associated documents on correct forms.

Acknowledgement of all amendments.

Completed 52.225-2 Buy America Certificate.

Completed 852.219-75 VA Notice of Limitations in Subcontractors Compliance Certificate.

Verified/visible/certified on the Small Business Administration Certification on SBA - Dynamic Small Business Search.

Proof of compliance with VETS 4212 Federal Contractor Reporting.

(a) Bidding materials consisting of Invitation for Bids, drawings, specifications and contract forms will be available on https://beta.sam.gov/ in electronic format only by searching for solicitation number 36C24226B0029. All interested parties (subs & primes) should register at https://beta.sam.gov/ as an Interested Vendor so that others will know of our interest in participating in this procurement. A Bidder s mailing list WILL NOT BE prepared by the Contract Specialist. SOLICITATION AMENDMENTS: Amendments to the solicitation will be posted at SAM.gov/. Paper copies of the amendments will NOT be individually mailed. By registering to Receive Notification , you will be notified by e-mail of any new amendments that have been issued and posted. No other notification of amendments will be provided. Bidders are reminded that they are responsible for obtaining and acknowledging all amendments to this solicitation prior to the time for receipt of bids.

(b) If bid exceeds $150,000 a bid bond must be submitted. A bid guarantee is required in an amount not less than 20 percent of the bid price but shall not exceed $3,000,000. Failure to furnish the required bid guarantee in the proper form and amount, by the time set for opening of bids, will require rejection of the bid in all cases except those listed in FAR 28.101-4, and may be cause for rejection even then.

(c) If the contract will exceed $150,000 (see FAR 28.102-1 for lesser amount), the bidder to whom award is made will be required to furnish two bonds, a Payment Bond, SF 25A, and a Performance Bond, SF 25, each in the penal sum as noted in the General Conditions of the Specification. Copies of SFs 25 and 25A may be obtained upon application to the issuing office.

(d) If the bid is between $30,000 - $150,000. The bidder to whom award is made will be required to furnish a Payment Bond, Standard Form 25A or alternative payment protection which conforms to the requirements set forth in FAR Clause 52.228-13, Alternative Payment Protections, as noted in the General Conditions of this Specification. Copies of the Standard Form of Payment Bond may be obtained upon application to the Issuing Office.

DESCRIPTION OF WORK: GENERAL CONSTRUCTION: The Contractor shall furnish all necessary professional Construction services to provide complete scope of work for Project 528A7-19-720 in accordance with the project drawings and specifications for the Albany VAMC.

Magnitude of Construction: $1,000,000 and $5,000,000

Update #5 ·

Bid RFI Update

Solicitation: 36C24226B0029/Project: 528A7-19-720 Repair SPS Deficiencies

Answered By: Emery P. Gasparek Jr; Jim Granier Date: 04-28-2026.

Is there a lay-down area designated for this project?

Answer: There are no designated laydown areas on the drawings. AHU-2., Limited space on roof near Temp Unit, and limited space on 10th floor near AHU-2 area. AHU-11, Limited Space on Shaft 5 Roof, and inside near unit. AHU-7 extremely limited space inside Shaft 2, near units. There is nothing on drawings showing any pre-determined areas so contractors should assume no laydown area permitted.

Is parking available for contractors on-site?

Answer: No. One dumpster or one parking spot.

Due to volatile material price fluctuations and unpredictability of the market, will the government agree to pay for Stored Materials on this project to avoid price increases post bid? Documentation of material invoice/packing slips, photo, and insurance backup information for each relevant charge would be provided.

Answer: No

If a project runs past initial period of performance, can material costs be submitted then? Supplier & Manufacturers don t wait to bill, having to hold/extend carrying these costs puts an extreme burden on contractors.

Answer: No

Section 28 13 00: Physical Access Control System is missing from project

specifications.

Answer: Will include

3/AS-902 mentions Apco Signs. Is Apco sole source, or can other sign manufacturers be

utilized?

Answer: Apco is the Basis of Design for the hospital

Confirm temp SPS trailer is in GC contract.

Answer: Yes it is to be included in the Bid

Please define GC responsibility for remove, storage, and reinstallation of existing equipment. For example, built-in units (washers, cart washers, and sterilizers) have

stainless steel trim surrounds, in-wall and floor utility connections. Will vendors make disconnections and package these units for storage?

Answer:

- VA will have Equipment MFG s shut down and secure equipment.

-Contractor will disconnect all utilities.

-Contractor will move equipment to Contractor s warehouse for storage.

-Contractor will store in warehouse for the duration of Phase 2.

-Contractor will move equipment back to VA or install new Identical Equipment.

-Contraction will make all utility connects to equipment including but not limited to (Steam, Air , Water, RO Water, Data, Electrical, and Drains).

-All Stainless Panels near Sterilizers are to be removed and re-installed by Contractor. This includes fitment to new Sterilizers.

-VA will have all Equipment new or used Started up and Commissioned by MFG s.

What are climate control requirements for the equipment?

Answer: Temperature 68 degrees +/- 2; Humidity 40% +/- 5%

Who is responsible for utility connections on reinstallation?

Answer: Contractors Bidding this Project

Who is responsible for reinstalling stainless trim surrounds?

Answer: Contractors Bidding this Project

At site visit, we were told the cart washer drain is leaking. This equipment is to remain,

and the drain seems to be underneath the unit who is responsible for

disassembling and reassembling the unit for drain work?

Answer: Contractors Bidding this Project

Who is responsible for providing the commissioning agent, the VA or general contractor?

Answer: Contractor is responsible for commissioning all aspects of project except for the equipment. VA will commission all equipment

Will there be specific haul routes required for ingress of materials and equipment and/or egress of removed equipment and debris?

Answer: Contractor to decide, however, there are specific requirements with moving materials through Patient Care areas including moving materials off hours. All carts and materials/debris are required to be covered. Each area was walked during the site visit. See drawings and specs for additional details

How many consecutive days would crane be allowed to stay set up?

Answer: One day. All Crane picks are performed on weekends or after hours with Contractors providing all supervision, safety, and associated required personnel. A required Crane Permit is required to be submitted by Contractor to VA for approval.

Confirm temp SPS trailer rental and rigging is to be included in GC contract

Answer: Contractors Bidding this Project need to include this in their Bid

Please define GC responsibility for remove, storage, and reinstallation of existing equipment.

-Built-in units (washers, cart washers, and sterilizers) have stainless steel trim surrounds,

Answer: the Cart Washer does not get moved and has to be protected in place by Contractors bidding this Project. Contractors bidding this Project are required to repair the leaking drain under the Cart Washer which requires the disconnect and removal of some piping and components which are in the Scope of this Project by Contractors bidding this Project. All other built-in units will be including Stainless Steel Surrounds, removing, moving to storage, storage, and re-installation are the responsibility of Contractors bidding this Project. VA will have Equipment MFG s shut down and secure equipment. Before it is to be moved. All other Mechanical, Electrical and other work is the responsibility of contractors bidding this Project.

Built In Units and Sterilizers are in the Scope of this Project, and Contractor bidding this Project are required to include it.

-in-wall and floor utility connections.

Answer: Contractors Bidding this Project are responsible for this work

Will vendors make disconnections and package these units for storage?

Answer: NO Contractors Bidding this Project need to include this in their Bid. VA will have Equipment MFG s shut down and secure equipment. Before it is to be moved.

What are climate control requirements for the equipment?

Answer: Temperature 68 degrees +/- 2; Humidity 40% +/- 5%

Who is responsible for utility connections on reinstallation?

Answer: Contractors Bidding this Project

Who is responsible for reinstalling stainless trim surrounds?

Answer: Contractors Bidding this Project

At site visit we were told the cart washer drain is leaking. This equipment is to-remain, and the drain seems to be underneath the unit who is responsible for disassembling and reassembling the unit for drain work?

Answer: the Cart Washer does not get moved and has to be protected in place by Contractors bidding this Project. Contractors bidding this Project are required to repair the leaking drain under the Cart Washer which requires the disconnect and removal of some piping and components which are in the Scope of this Project by Contractors bidding this Project.

Please provide full-size drawings, drawings released on SAM are 8.5 x 11 .

Answer: Full size drawings work around below to try. Also working with AE for new PDF of drawings. CO will send in another amendment.

Requesting an extension due to lack of full size drawings.

Answer: Bid Due Date has been extended to May 13th 2PM.

STEP 1 Contractors can open the drawings and select Print as a PDF

STEP 2 Â Click Page Set-up in lower left corner and select the size they want to plot. Save it and plot the larger PDF

On plan page AS-801-AD there are three openings which state the existing doors are to be removed, stored, cleaned and reinstalled. These are units #78-1, 84 and 85. That same comment states to provide new hardware. May I assume the frames will also be ETR and only price the hardware? Please confirm and thank you again.

Answer: Price Only the Hardware

I am looking at the door types on plan page AS-801-AD and they have referenced some which do not exist. If you look at the door type column several of the units are listed as 2F or 2T. These codes do not relate to the door elevations. Please reach out to the architect and send answers as soon as possible, so I may keep moving ahead on this one. Thanks!

Answer: 2F should be Metal; 2T should be Wood

Update #4 ·

Bid RFI Answers

Solicitation: 36C24226B0029/Project: 528A7-19-720 Repair SPS Deficiencies

Answered By: Emery P. Gasparek Jr; Jim Granier

Is there a lay-down area designated for this project?

Answer: There are no designated laydown areas on the drawings. AHU-2., Limited space on roof near Temp Unit, and limited space on 10th floor near AHU-2 area. AHU-11, Limited Space on Shaft 5 Roof, and inside near unit. AHU-7 has extremely limited space inside Shaft 2, near units. There is nothing on drawings showing any pre-determined areas so contractors should assume no laydown area permitted.

Is parking available for contractors on-site?

Answer: No. One dumpster or one parking spot.

Due to volatile material price fluctuations and unpredictability of the market, will the government agree to pay for Stored Materials on this project to avoid price increases post bid? Documentation of material invoice/packing slips, photo, and insurance backup information for each relevant charge would be provided.

Answer: No

If a project runs past initial period of performance, can material costs be submitted then? Supplier & Manufacturers don t wait to bill, having to hold/extend carrying these costs puts an extreme burden on contractors.

Answer: No

Section 28 13 00: Physical Access Control System is missing from project

specifications.

Answer: Will include

3/AS-902 mentions Apco Signs. Is Apco sole source, or can other sign manufacturers be

utilized?

Answer: Apco is the Basis of Design for the hospital

Confirm temp SPS trailer is in GC contract.

Answer: Yes, it is to be included in the Bid

Please define GC responsibility for remove, storage, and reinstallation of existing equipment. For example, built-in units (washers, cart washers, and sterilizers) have

stainless steel trim surrounds, in-wall and floor utility connections. Will vendors make disconnections and package these units for storage?

Answer:

- VA will have Equipment MFG s shut down and secure equipment.

-Contractor will disconnect all utilities.

-Contractor will move equipment to Contractor s warehouse for storage.

-Contractor will store in warehouse for the duration of Phase 2.

-Contractor will move equipment back to VA or install new Identical Equipment.

-Contraction will make all utility connects to equipment including but not limited to (Steam, Air , Water, RO Water, Data, Electrical, and Drains).

-All Stainless Panels near Sterilizers are to be removed and re-installed by Contractor. This includes fitment to new Sterilizers.

-VA will have all Equipment new or used Started up and Commissioned by MFG s.

What are climate control requirements for the equipment?

Answer: Temperature 68 degrees +/- 2; Humidity 40% +/- 5%

Who is responsible for utility connections on reinstallation?

Answer: Contractors Bidding this Project

Who is responsible for reinstalling stainless trim surrounds?

Answer: Contractors Bidding this Project

At site visit, we were told the cart washer drain is leaking. This equipment is to remain,

and the drain seems to be underneath the unit who is responsible for

disassembling and reassembling the unit for drain work?

Answer: Contractors Bidding this Project

Who is responsible for providing the commissioning agent, the VA or general contractor?

Answer: Contractor is responsible for commissioning all aspects of project except for the equipment. VA will commission all equipment

Will there be specific haul routes required for ingress of materials and equipment and/or egress of removed equipment and debris?

Answer: Contractor to decide, however, there are specific requirements with moving materials through Patient Care areas including moving materials off hours. All carts and materials/debris are required to be covered. Each area was walked during the site visit. See drawings and specs for additional details

How many consecutive days would crane be allowed to stay set up?

Answer: One day. All Crane picks are performed on weekends or after hours with Contractors providing all supervision, safety, and associated required personnel. A required Crane Permit is required to be submitted by Contractor to VA for approval.

Confirm temp SPS trailer rental and rigging is to be included in GC contract

Answer: Contractors Bidding this Project need to include this in their Bid

Please define GC responsibility for remove, storage, and reinstallation of existing equipment.

-Built-in units (washers, cart washers, and sterilizers) have stainless steel trim surrounds,

Answer: the Cart Washer does not get moved and has to be protected in place by Contractors bidding this Project. Contractors bidding this Project are required to repair the leaking drain under the Cart Washer which requires the disconnect and removal of some piping and components which are in the Scope of this Project by Contractors bidding this Project. All other built-in units will be including Stainless Steel Surrounds, removing, moving to storage, storage, and re-installation are the responsibility of Contractors bidding this Project. VA will have Equipment MFG s shut down and secure equipment. Before it is to be moved. All other Mechanical, Electrical and other work is the responsibility of contractors bidding this Project.

Built In Units and Sterilizers are in the Scope of this Project, and Contractor bidding this Project are required to include it.

-in-wall and floor utility connections.

Answer: Contractors Bidding this Project are responsible for this work

Will vendors make disconnections and package these units for storage?

Answer: NO Contractors Bidding this Project need to include this in their Bid. VA will have Equipment MFG s shut down and secure equipment. Before it is to be moved.

What are climate control requirements for the equipment?

Answer: Temperature 68 degrees +/- 2; Humidity 40% +/- 5%

Who is responsible for utility connections on reinstallation?

Answer: Contractors Bidding this Project

Who is responsible for reinstalling stainless trim surrounds?

Answer: Contractors Bidding this Project

At site visit we were told the cart washer drain is leaking. This equipment is to-remain, and the drain seems to be underneath the unit who is responsible for disassembling and reassembling the unit for drain work?

Answer: the Cart Washer does not get moved and has to be protected in place by Contractors bidding this Project. Contractors bidding this Project are required to repair the leaking drain under the Cart Washer which requires the disconnect and removal of some piping and components which are in the Scope of this Project by Contractors bidding this Project.

Please provide full-size drawings, drawings released on SAM are 8.5 x 11 .

Answer: Should be able to plot drawings full size on a plotter.

Update #3 ·

Page 4 of 4

INSTRUCTIONS, CONDITIONS AND OTHER STATEMENTS TO BIDDERS/OFFERORS

2.1 BID OPENING INFORMATION

In accordance with FAR 14.202-8, the government is authorizing electronic bids on this solicitation. ALL bids shall be emailed to terry.fraser@va.gov Contracting Officer and timestamped by April 30, 2026, at 2:00pm EST prior to the bid opening time. The bids shall include copies of a bid bond. The bid opening shall take place on April 30, 2026, at 2:15pm EST. No hand-carried or mailed bids will be accepted.

The bid opening will take place via Microsoft Teams conference call. To access the conference, please access:

To join by phone please dial 1-347-566-4838

Phone conference ID: 196 379 950#

2.2 Special Notes regarding FAR 52.229-3: Federal, State and Local Taxes:Â Â

Offerors are hereby notified that under the New York Statutes Annotated, 54:32B-9 (2), the United States of America, any of its agencies and instrumentalities, are not subject to sales or use tax  when it is the purchaser, user, or consumer of personal property. Pursuant to New York Administrative Code § 18:24-5.3,  a contractor s purchase of such building and construction materials within the State of New York to be incorporated into the real property belonging to the U.S. Department of Veterans Affairs (VA) is subject to the exemption from the state of New York sales tax. To take advantage of the tax exemption the successful offeror under this solicitation must complete FORM ST-13 Contractor s Exempt Purchase Certificate when it purchases construction materials for this contract and keep on file as required by the state of New York tax laws.Â

 Notwithstanding FAR 52.229-3, all bids received in response to this solicitation are presumed to reflect this tax exemption and therefore should not include the state of New York sales tax for incorporation into VA real estate under this contract.Â

1.1 BID PRICING SHEET

Bids providing less that 120 Calendar Days of Government Acceptance after the date bids are due will not be considered and will be rejected.

The bidder agrees to perform the work required at the prices specified below in strict accordance with the terms of the solicitation, if this bid is accepted by the Government in writing within 120 calendar days after the date bidders are due.

BASE BID

A. ITEM I, GENERAL CONSTRUCTION: BASE BID: Work includes general construction, electrical and Fire alarm upgrades and certain other items.

The Contract period of performance for Base Bid construction shall be 550 calendar days from Notice to Proceed (NTP).

Base Bid $ ___________________________

Offers shall provide a complete package to include the completed bid sheet along with the following to be determined responsive, responsible, and considered for award:

Bid Bond and associated documents on correct forms.

Acknowledgement of all amendments.

Completed 52.225-2 Buy America Certificate.

Completed 852.219-75 VA Notice of Limitations in Subcontractors Compliance Certificate.

Verified/visible/certified on the Small Business Administration Certification on SBA - Dynamic Small Business Search.

Proof of compliance with VETS 4212 Federal Contractor Reporting.

(a) Bidding materials consisting of Invitation for Bids, drawings, specifications and contract forms will be available on https://beta.sam.gov/ in electronic format only by searching for solicitation number 36C24226B0029. All interested parties (subs & primes) should register at https://beta.sam.gov/ as an Interested Vendor so that others will know of our interest in participating in this procurement. A Bidder s mailing list WILL NOT BE prepared by the Contract Specialist. SOLICITATION AMENDMENTS: Amendments to the solicitation will be posted at SAM.gov/. Paper copies of the amendments will NOT be individually mailed. By registering to Receive Notification , you will be notified by e-mail of any new amendments that have been issued and posted. No other notification of amendments will be provided. Bidders are reminded that they are responsible for obtaining and acknowledging all amendments to this solicitation prior to the time for receipt of bids.

(b) If bid exceeds $150,000 a bid bond must be submitted. A bid guarantee is required in an amount not less than 20 percent of the bid price but shall not exceed $3,000,000. Failure to furnish the required bid guarantee in the proper form and amount, by the time set for opening of bids, will require rejection of the bid in all cases except those listed in FAR 28.101-4, and may be cause for rejection even then.

(c) If the contract will exceed $150,000 (see FAR 28.102-1 for lesser amount), the bidder to whom award is made will be required to furnish two bonds, a Payment Bond, SF 25A, and a Performance Bond, SF 25, each in the penal sum as noted in the General Conditions of the Specification. Copies of SFs 25 and 25A may be obtained upon application to the issuing office.

(d) If the bid is between $30,000 - $150,000. The bidder to whom award is made will be required to furnish a Payment Bond, Standard Form 25A or alternative payment protection which conforms to the requirements set forth in FAR Clause 52.228-13, Alternative Payment Protections, as noted in the General Conditions of this Specification. Copies of the Standard Form of Payment Bond may be obtained upon application to the Issuing Office.

DESCRIPTION OF WORK: GENERAL CONSTRUCTION: The Contractor shall furnish all necessary professional Construction services to provide complete scope of work for Project 528A7-19-720 in accordance with the project drawings and specifications for the Albany VAMC.

Magnitude of Construction: $1,000,000 and $5,000,000

Update #2 ·

Page 4 of 4

INSTRUCTIONS, CONDITIONS AND OTHER STATEMENTS TO BIDDERS/OFFERORS

2.1 BID OPENING INFORMATION

In accordance with FAR 14.202-8, the government is authorizing electronic bids on this solicitation. ALL bids shall be emailed to terry.fraser@va.gov Contracting Officer and timestamped by April 23, 2026, at 2:00pm EST prior to the bid opening time. The bids shall include copies of a bid bond. The bid opening shall take place on April 23, 2026, at 2:15pm EST. No hand-carried or mailed bids will be accepted.

The bid opening will take place via Microsoft Teams conference call. To access the conference, please access:

To join by phone please dial 1-347-566-4838

Phone conference ID: 196 379 950#

2.2 Special Notes regarding FAR 52.229-3: Federal, State and Local Taxes:Â Â

Offerors are hereby notified that under the New York Statutes Annotated, 54:32B-9 (2), the United States of America, any of its agencies and instrumentalities, are not subject to sales or use tax  when it is the purchaser, user, or consumer of personal property. Pursuant to New York Administrative Code § 18:24-5.3,  a contractor s purchase of such building and construction materials within the State of New York to be incorporated into the real property belonging to the U.S. Department of Veterans Affairs (VA) is subject to the exemption from the state of New York sales tax. To take advantage of the tax exemption the successful offeror under this solicitation must complete FORM ST-13 Contractor s Exempt Purchase Certificate when it purchases construction materials for this contract and keep on file as required by the state of New York tax laws.Â

 Notwithstanding FAR 52.229-3, all bids received in response to this solicitation are presumed to reflect this tax exemption and therefore should not include the state of New York sales tax for incorporation into VA real estate under this contract.Â

1.1 BID PRICING SHEET

Bids providing less that 120 Calendar Days of Government Acceptance after the date bids are due will not be considered and will be rejected.

The bidder agrees to perform the work required at the prices specified below in strict accordance with the terms of the solicitation, if this bid is accepted by the Government in writing within 120 calendar days after the date bidders are due.

BASE BID

A. ITEM I, GENERAL CONSTRUCTION: BASE BID: Work includes general construction, electrical and Fire alarm upgrades and certain other items.

The Contract period of performance for Base Bid construction shall be 550 calendar days from Notice to Proceed (NTP).

Base Bid $ ___________________________

Offers shall provide a complete package to include the completed bid sheet along with the following to be determined responsive, responsible, and considered for award:

Bid Bond and associated documents on correct forms.

Acknowledgement of all amendments.

Completed 52.225-2 Buy America Certificate.

Completed 852.219-75 VA Notice of Limitations in Subcontractors Compliance Certificate.

Verified/visible/certified on the Small Business Administration Certification on SBA - Dynamic Small Business Search.

Proof of compliance with VETS 4212 Federal Contractor Reporting.

(a) Bidding materials consisting of Invitation for Bids, drawings, specifications and contract forms will be available on https://beta.sam.gov/ in electronic format only by searching for solicitation number 36C24226B0029. All interested parties (subs & primes) should register at https://beta.sam.gov/ as an Interested Vendor so that others will know of our interest in participating in this procurement. A Bidder s mailing list WILL NOT BE prepared by the Contract Specialist. SOLICITATION AMENDMENTS: Amendments to the solicitation will be posted at SAM.gov/. Paper copies of the amendments will NOT be individually mailed. By registering to Receive Notification , you will be notified by e-mail of any new amendments that have been issued and posted. No other notification of amendments will be provided. Bidders are reminded that they are responsible for obtaining and acknowledging all amendments to this solicitation prior to the time for receipt of bids.

(b) If bid exceeds $150,000 a bid bond must be submitted. A bid guarantee is required in an amount not less than 20 percent of the bid price but shall not exceed $3,000,000. Failure to furnish the required bid guarantee in the proper form and amount, by the time set for opening of bids, will require rejection of the bid in all cases except those listed in FAR 28.101-4, and may be cause for rejection even then.

(c) If the contract will exceed $150,000 (see FAR 28.102-1 for lesser amount), the bidder to whom award is made will be required to furnish two bonds, a Payment Bond, SF 25A, and a Performance Bond, SF 25, each in the penal sum as noted in the General Conditions of the Specification. Copies of SFs 25 and 25A may be obtained upon application to the issuing office.

(d) If the bid is between $30,000 - $150,000. The bidder to whom award is made will be required to furnish a Payment Bond, Standard Form 25A or alternative payment protection which conforms to the requirements set forth in FAR Clause 52.228-13, Alternative Payment Protections, as noted in the General Conditions of this Specification. Copies of the Standard Form of Payment Bond may be obtained upon application to the Issuing Office.

DESCRIPTION OF WORK: GENERAL CONSTRUCTION: The Contractor shall furnish all necessary professional Construction services to provide complete scope of work for Project 528A7-19-720 in accordance with the project drawings and specifications for the Albany VAMC.

Magnitude of Construction: $1,000,000 and $5,000,000

See attached

A.1 Attachements

See attached document: Drawings Addendum.

See attached document: Drawings 1.

See attached document: Drawings 2.

See attached document: Drawings 3.

See attached document: VA 528A7-19-270 Specifications - Volume I.

See attached document: VA 528A7-19-270 Specifications - Volume II.

See attached document: Basis of Design.

See attached document: Proposed New Equipment Combined.

Update #1 ·

See attached

Files

File Type Posted
36C24226B0029 0010.docx DOCX document
VA SYRACUSE SPS 528A7-19-720 Part 2 of 4 ANSI E 1.pdf PDF
VA SYRACUSE SPS 528A7-19-720 Part 3 of 4 ANSI E 1.pdf PDF
36C24226B0029 0009.docx DOCX document
SPS-ADDENDUM Drawings Part 4 of 4 ANSI E 1.pdf PDF
VA SYRACUSE SPS 528A7-19-720 Part 1 of 4 ANSI E 1.pdf PDF
PD-101-2 bid rfi 5-15-26.pdf PDF
PDP-101-1 bid rfi 5-15-26.pdf PDF
36C24226B0029 0008.docx DOCX document
36C24226B0029 0007.docx DOCX document
36C24226B0029 0006.docx DOCX document
VA SYRACUSE SPS Drawings 3.pdf PDF
VA SYRACUSE SPS Drawings 2.pdf PDF
VA SYRACUSE SPS Drawings 1.pdf PDF
VA SYRACUSE SPS Drawings 4.pdf PDF
230923 CURRENT Controls Spec.pdf PDF
36C24226B0029 0005.docx DOCX document
Site Visit Sign In Sheet.pdf PDF
36C24226B0029 0004.docx DOCX document
36C24226B0029 0003.docx DOCX document
36C24226B0029 0002.docx DOCX document
Drawings2.pdf PDF
Drawing Addendum.pdf PDF
Drawings1.pdf PDF
Drawings3.pdf PDF
36C24226B0029 0001.docx DOCX document
Drawings 3.pdf PDF
Drawings 2.pdf PDF
Drawings 1.pdf PDF
Drawings Addendum.pdf PDF
VA 528A7-19-270 Specifications - Volume II.pdf PDF
Buy American Certificate.pdf PDF
Proposed New Equipment Combined.pdf PDF
VA 528A7-19-270 Specifications - Volume I.pdf PDF
Basis of Design.pdf PDF
Wage Determination.pdf PDF
852.219-75 Limitation on Subcontracting.pdf PDF
36C24226B0029_1.docx DOCX document
Show all 38

Notice history

Notice Type Posted
This notice Latest solicitation Solicitation
Z1DA--NRM-CONST | 528A7-19-720 | Repair SPS Deficiencies Original Pre-Solicitation

Similar open opportunities

Opportunity Agency Set-aside Responses due
Z2DA--561-26-104 Repair Operating Room (OR) & Bathroom Leaks NAICS 236220 Veterans Integrated Service Network 2 No set-aside
Y1DA--NRM-CONST 528-CSI-102 Urology Equipment Site Prep | FY27 NRM Buffalo, New York 14215, United States · NAICS 236220 Veterans Integrated Service Network 2 Service-Disabled Veteran-Owned Small Business
F108--620-26-206 Asbestos Abatement NAICS 562910 Veterans Integrated Service Network 2 No set-aside
Z1DA--Sources Sought Notice/Market Research Project: Renovate SPS Phase 3 Central Virginia VA Healthcare System Cvhcs Richmond Virginia 23249 · NAICS 236220 Veterans Integrated Service Network 6 No set-aside
Z2DA--Copy of FY27Q1-CON 668-24-106 Renovate CLC East Wing and Courtyard NAICS 236220 Veterans Integrated Service Network 20 No set-aside

On GovTribe

Work this opportunity

  • Track it in your pipeline
  • Find teaming partners
  • Similar opportunities
  • Ask GovTribe AI about this opportunity

GovTribe for Federal Contractors