Opportunity facts

NAICS code
115310 Support Activities for Forestry
PSC
F099 Natural Resources/Conservation- Other
Place of performance
Sandy, Oregon 97055, United States
Points of contact

Notice details come from SAM.gov. Updated .

About this opportunity

The U.S. Department of Agriculture Forest Service is soliciting the Rivbulio Fire Recovery Integrated Resource Service Contract (IRSC) to procure services for roadside hazard tree abatement, road repair, and reconstruction work in response to a disaster declaration on the Mount Hood National Forest in Oregon. The objective is to reduce roadside fuel loading and provide safe access for public road users. Key activities include identifying and cutting fire-damaged trees, removing cut timber, managing roadside slash and fuels, and performing road maintenance and reconstruction. The anticipated period of performance is through December 31, 2027, and a mandatory site visit for prospective contractors is scheduled for August 6, 2024.

This solicitation is open to full and open competition under NAICS code 115310 for Support Activities for Forestry with a $34M size standard. The total estimated project area is 2,314 acres, with 48,901 CCF of biomass/cull material across four distinct geographic areas. Multiple awards may be made under this stewardship contract opportunity. The work is anticipated to take place in the Memaloose/Hillockburn, Fish Creek, Bull Complex, and Olallie areas southeast of Estacada, Oregon.

Notice text

2 versions

Update #2 · Latest ·

** Amendment 002 issued 8/15/2024**

This Amendment replaces all Contract Area Maps

**Amendment 001 issued 8/8/2024**

This amendment makes the following changes to the Rivbulio IRSC Solicitation:
1. Shares the site questions and answers, and attendee list
2. Corrects Solicitation Section I.1.2. Incorrect FAR provision number for Service Contract Labor Standards was included in provisions incorporated by reference. Correct provision is FAR 52.222-41.

Background:

The USDA Forest Service and the Mount Hood National Forest are soliciting the Rivbulio Fire Recovery IRSC which shall be awarded under the following Stewardship Authority: Section 604 (16 USC 6591c) of Public Law 108-148 as amended by Section 8205 of Public Law 113-79, the Agricultural Act of 2014—Grants the U.S. Forest Service (Government) permanent authority to enter into stewardship contracts or agreements to achieve land management goals for the National Forests or public lands that meet local and rural community needs. Section 8205 supersedes the temporary authority granted to the Forest Service (Government) in section 347 of Public Law 105-277, the Omnibus Consolidated and Emergency Appropriations Act, 1999.

Stewardship authority grants the Forest Service the authority to aggregate stewardship work activity requirements and solicit those requirements utilizing full and open competition.

NAICS: 115310: Support Services for Forestry, Size Standard: $34M Fuels Management Services.

Multiple awards may be made to this solicitation. Project areas have been separated and the schedule is designed to allow for individual awards to be made that will complete all requirements within a given project area.

Project Location:

The Rivbulio Fire Recovery IRSC project is located approximately 16 miles (Memaloose) to 56 miles (Olallie) southeast of Estacada, Oregon. Access to the project area is via State Highway 224 (heading southeast from Estacada) and Forest Road 46; using Forest Service Roads (FSRs) within the Memaloose/Hillockburn, Fish Creek, Bull Complex, and Olallie areas south of State Hwy 224. The total project area is within the Clackamas Ranger District of the Mt. Hood National Forest. The proposed project area lies generally within the following township and ranges and FSRs:

  1. Memaloose/Hillockburn Area – T04S, R05E and T05S, R05E; FSR 4500, 4500220, 4500240, 4510, 4520, 4510021
  2. Fish Creek Area – T05S, R05E and T05S, R06E; FSR 5400, 5410, 5411, 5412, 5411210
  3. Bill Complex Area – T08S, R07E; FSR 6350, 6355, 4671, 4672
  4. Olallie Area - T08S, R08E and T09S, R08E; FSR 4220

Willamette Principal Meridian, Clackamas County, Oregon.  

Planned Period of Performance:

All work is tentatively anticipated to have the following final completion dates: December 31, 2027.

Description of Work:

The Rivbulio IRSC will implement roadside hazard tree abatement treatments, road repair and reconstruction work in response to disaster declaration FEMA-4562-DR. The objective is to reduce roadside fuel loading and to provide safe access for the public road users. Activities to achieve these end results include performing essential maintenance and reconstruction of roads, cutting of fire killed/damaged roadside trees, removal of cut timber, managing roadside slash and fuel accumulation which will help with site preparation for future reforestation efforts along roads and reduce future fire risk.

This contract will secure services to perform necessary hazard tree abatement work along Forest system roads that will include the removal of Forest products that meet utilization standards and associated slash work, Additional services to be procured include standard road maintenance activities, culvert cleaning and replacement, guardrail replacement, and armoring of identified system roads to facilitate the removal of Forest products.

The anticipated operational seasons for road work activities is June 1 – October 15 annually. Ground based hazard tree work is anticipated to be permitted year-round and must comply with required protections for wet season operations and IFPL.

The end result is a road system that has no standing fire killed/damaged trees within striking distance of the road (including the slide and roll area). This will be done by accomplishing the following:

  • Identifying and cutting standing fire killed/damaged trees.
  • Removing cut trees where applicable.
  • Piling, scattering, chipping, incinerating and/or removing operationally generated slash and fuels.
  • Maintaining roads within the contract area.
  • Reconstructing roads within the contract area.

Estimated Timber Volume and acres is as follows:

The entire project area is estimated at 2,314 acres of roadside hazard tree abatement with associated slash treatments in removal areas. Forest Product volume estimates for the entire project are 48,901 CCF of biomass/cull material. Volume quantities are made available with the understanding that values shown are Forest Service estimates and are not guaranteed. Interested Contractors are urged to examine the individual contract areas and make their own estimates.

  • The Hillockburn-Memaloose project area is estimated at 866 acres and 25,394 CCF of biomass/cull.
  • The Fish Creek project area is estimated at 627 acres and 15,872 CCF of biomass/cull.
  • The Bull Complex project area is estimated at 383 acres and 7,953 CCF of biomass/cull.
  • The Olallie Lake project area is estimated at 438 acres and 5,682 CCF of biomass/cull.

Solicitation Site Visit Date and Time:

The Mount Hood National Forest will hold a site visit for prospective contractors to discuss the end results of the project, and to facilitate dialogue on contractual requirements that are anticipated in the contract, and any discuss or consider any operational limitations foreseen by attendees.

The site visit will be held on August 6th, 2024, at 10:00 a.m. PT with a meeting location at the Fish Creek Campground, at the junction of OR 224 and Forest Service Road 54.

Included Attachments:

0. Rivbulio Fire Recovery IRSC Solicitation Letter

1. 12363N24R4018 Rivbulio FR IRSC

2. Rivbulio FR IRSC Appendix A

3. Rivbulio FR IRSC Appendix B

4a. Hillockburn/Memaloose Appendix C

4b. Fish Creek Appendix C

4c. Bull Complex Appendix C

4d. Olallie Appendix C

5a. Hillockburn/Memaloose Appendix D Plans

5b. Hillockburn/Memaloose Appendix D Supplemental Specifications

5c. Fish Creek Appendix D Plans

5d. Fisk Creek Appendix D Supplemental Specifications

5e. Bull Complex Appendix D Plans

5f. Bull Complex Appendix D Supplemental Specifications

5g. Olallie Appendix D Plans

5h. Olallie Appendix D Supplemental Specifications

6a. A002 Hillockburn-Memaloose CAM

6b. A002 Fish Creek CAM

6c. A002 Bull Complex CAM

6d. A002 Olallie CAM

6e. A002 Olallie Slash CAM

6f. Rivbulio IRSC Invasives Map Book

6g. Rivbulio IRSC Invasives North Tiles

6h. Rivbulio IRSC Invasives South Tiles

7. Sediment Trap Examples

8.Rivbulio FR IRSC SF-24-23a

9. Service Contract Act Wage Determination #1977-0079, Revision #76 dated 07/22/2024

10. Davis-Bacon Wage Determination #OR20240001 Modification #8 dated 06/28/2024

Update #1 ·

Background:

The USDA Forest Service and the Mount Hood National Forest are soliciting the Rivbulio Fire Recovery IRSC which shall be awarded under the following Stewardship Authority: Section 604 (16 USC 6591c) of Public Law 108-148 as amended by Section 8205 of Public Law 113-79, the Agricultural Act of 2014—Grants the U.S. Forest Service (Government) permanent authority to enter into stewardship contracts or agreements to achieve land management goals for the National Forests or public lands that meet local and rural community needs. Section 8205 supersedes the temporary authority granted to the Forest Service (Government) in section 347 of Public Law 105-277, the Omnibus Consolidated and Emergency Appropriations Act, 1999.

Stewardship authority grants the Forest Service the authority to aggregate stewardship work activity requirements and solicit those requirements utilizing full and open competition.

NAICS: 115310: Support Services for Forestry, Size Standard: $34M Fuels Management Services.

Multiple awards may be made to this solicitation. Project areas have been separated and the schedule is designed to allow for individual awards to be made that will complete all requirements within a given project area.

Project Location:

The Rivbulio Fire Recovery IRSC project is located approximately 16 miles (Memaloose) to 56 miles (Olallie) southeast of Estacada, Oregon. Access to the project area is via State Highway 224 (heading southeast from Estacada) and Forest Road 46; using Forest Service Roads (FSRs) within the Memaloose/Hillockburn, Fish Creek, Bull Complex, and Olallie areas south of State Hwy 224. The total project area is within the Clackamas Ranger District of the Mt. Hood National Forest. The proposed project area lies generally within the following township and ranges and FSRs:

  1. Memaloose/Hillockburn Area – T04S, R05E and T05S, R05E; FSR 4500, 4500220, 4500240, 4510, 4520, 4510021
  2. Fish Creek Area – T05S, R05E and T05S, R06E; FSR 5400, 5410, 5411, 5412, 5411210
  3. Bill Complex Area – T08S, R07E; FSR 6350, 6355, 4671, 4672
  4. Olallie Area - T08S, R08E and T09S, R08E; FSR 4220

Willamette Principal Meridian, Clackamas County, Oregon.  

Planned Period of Performance:

All work is tentatively anticipated to have the following final completion dates: December 31, 2027.

Description of Work:

The Rivbulio IRSC will implement roadside hazard tree abatement treatments, road repair and reconstruction work in response to disaster declaration FEMA-4562-DR. The objective is to reduce roadside fuel loading and to provide safe access for the public road users. Activities to achieve these end results include performing essential maintenance and reconstruction of roads, cutting of fire killed/damaged roadside trees, removal of cut timber, managing roadside slash and fuel accumulation which will help with site preparation for future reforestation efforts along roads and reduce future fire risk.

This contract will secure services to perform necessary hazard tree abatement work along Forest system roads that will include the removal of Forest products that meet utilization standards and associated slash work, Additional services to be procured include standard road maintenance activities, culvert cleaning and replacement, guardrail replacement, and armoring of identified system roads to facilitate the removal of Forest products.

The anticipated operational seasons for road work activities is June 1 – October 15 annually. Ground based hazard tree work is anticipated to be permitted year-round and must comply with required protections for wet season operations and IFPL.

The end result is a road system that has no standing fire killed/damaged trees within striking distance of the road (including the slide and roll area). This will be done by accomplishing the following:

  • Identifying and cutting standing fire killed/damaged trees.
  • Removing cut trees where applicable.
  • Piling, scattering, chipping, incinerating and/or removing operationally generated slash and fuels.
  • Maintaining roads within the contract area.
  • Reconstructing roads within the contract area.

Estimated Timber Volume and acres is as follows:

The entire project area is estimated at 2,314 acres of roadside hazard tree abatement with associated slash treatments in removal areas. Forest Product volume estimates for the entire project are 48,901 CCF of biomass/cull material. Volume quantities are made available with the understanding that values shown are Forest Service estimates and are not guaranteed. Interested Contractors are urged to examine the individual contract areas and make their own estimates.

  • The Hillockburn-Memaloose project area is estimated at 866 acres and 25,394 CCF of biomass/cull.
  • The Fish Creek project area is estimated at 627 acres and 15,872 CCF of biomass/cull.
  • The Bull Complex project area is estimated at 383 acres and 7,953 CCF of biomass/cull.
  • The Olallie Lake project area is estimated at 438 acres and 5,682 CCF of biomass/cull.

Solicitation Site Visit Date and Time:

The Mount Hood National Forest will hold a site visit for prospective contractors to discuss the end results of the project, and to facilitate dialogue on contractual requirements that are anticipated in the contract, and any discuss or consider any operational limitations foreseen by attendees.

The site visit will be held on August 6th, 2024, at 10:00 a.m. PT with a meeting location at the Fish Creek Campground, at the junction of OR 224 and Forest Service Road 54.

Included Attachments:

0. Rivbulio Fire Recovery IRSC Solicitation Letter

1. 12363N24R4018 Rivbulio FR IRSC

2. Rivbulio FR IRSC Appendix A

3. Rivbulio FR IRSC Appendix B

4a. Hillockburn/Memaloose Appendix C

4b. Fish Creek Appendix C

4c. Bull Complex Appendix C

4d. Olallie Appendix C

5a. Hillockburn/Memaloose Appendix D Plans

5b. Hillockburn/Memaloose Appendix D Supplemental Specifications

5c. Fish Creek Appendix D Plans

5d. Fisk Creek Appendix D Supplemental Specifications

5e. Bull Complex Appendix D Plans

5f. Bull Complex Appendix D Supplemental Specifications

5g. Olallie Appendix D Plans

5h. Olallie Appendix D Supplemental Specifications

6a. Hillockburn-Memaloose CAM*

6b. Fish Creek CAM*

6c. Bull Complex CAM*

6d. Olallie CAM*

6e. Olallie Slash CAM*

6f. Rivbulio IRSC Invasives Map Book

6g. Rivbulio IRSC Invasives North Tiles

6h. Rivbulio IRSC Invasives South Tiles

7. Sediment Trap Examples

8.Rivbulio FR IRSC SF-24-23a

9. Service Contract Act Wage Determination #1977-0079, Revision #76 dated 07/22/2024

10. Davis-Bacon Wage Determination #OR20240001 Modification #8 dated 06/28/2024

*Attachments marked with an asterisk contain errors. References to protections on all Contract Area Maps (CAMs) are incorrect and reference the draft solicitation that was shared. Corrected CAMs will be uploaded and replace the current CAMs after the site visit.

Attachments

Files attached to this notice, newest first
File Type Posted
A002 SF30 Rivbulio IRSC.pdf PDF
6a. A002 Hillockburn-Memaloose CAM.pdf PDF
6b. A001 Fish Creek CAM.pdf PDF
6c. A001 Bull Complex CAM.pdf PDF
6d. A001 Olallie CAM.pdf PDF
6e. A001 Olallie Slash CAM.pdf PDF
A001 SF30 Rivbulio IRSC.pdf PDF
5g. Olallie_Appendix D.pdf PDF
6d. Olallie CAM.pdf PDF
6e. Oallie Slash CAM.pdf PDF
6f. Rivbulio IRSC Invasives Map Book.pdf PDF
6g. Rivbulio IRSC Invasives North Tiles.pdf PDF
3. Rivbulio FR IRSC Appendix B.pdf PDF
4a. Hillockburn-Memaloose Appendix C.pdf PDF
4d. Olallie Appendix C.pdf PDF
5b. Hillockburn-Memaloose_Supplemental Specs.pdf PDF
5h. Olallie Appendix D Supplemental Specifications.pdf PDF
6a. Hillockburn-Memaloose CAM.pdf PDF
6b. FIsh Creek CAM.pdf PDF
6c. Bull Complex CAM.pdf PDF
8. Rivbulio FR IRSC SF24-23a.pdf PDF
9. SCA WD #1977-0079, v76 07222024.pdf PDF
0. Rivbulio Fire Recovery IRSC Solicitation Letter.pdf PDF
1. 12363N24R4018 Rivbulio IRSC.pdf PDF
4b. Fish Creek Appendix C.pdf PDF
4c. Bull Complex Appendix C.pdf PDF
5d. Fish Creek Supplemental Specs.pdf PDF
6h. Rivbulio IRSC Invasives South Tiles.pdf PDF
7. Sediment Trap Examples.pdf PDF
10. DBA WD OR20240001 v8 06282024.pdf PDF
2. Rivbulio FR IRSC Appendix A.pdf PDF
5a. Hillockburn-Memaloose_Appendix D.pdf PDF
5c. FishCreek_Appendix D.pdf PDF
5e. BullComplex_Appendix D.pdf PDF
5f. Bull Complex Supplemental Specifications.pdf PDF
Show all 35

Notice history

Notices posted for this opportunity, newest first
Notice Type Posted
Rivbulio Fire Recovery IRSC Award Award Notice
Rivbulio Fire Recovery IRSC This notice · Latest solicitation Solicitation
Rivbulio Fire Recovery IRSC Pre-Solicitation
Rivbulio Fire Recovery IRSC Original Pre-Solicitation

On GovTribe

Work this opportunity on GovTribe

  • Track it in your pipeline
  • Find teaming partners
  • Similar opportunities
  • Ask GovTribe AI about this opportunity