Replace Primary & Secondary Electrical Distribution Phase 3
Closed Solicitation Posted
This opportunity was awarded. See the award notice from .
- Solicitation number
- FA4855-20-B-0006
- Agency
- Air Force Special Operations Command Air Force, Department of Defense
- Responses due
- Set-aside
- Service-Disabled Veteran-Owned Small Business
Opportunity facts
- NAICS code
- 237130 Power and Communication Line and Related Structures Construction
- PSC
- Y1NZ Construction Of Other Utilities
- Place of performance
- Cannon Afb Nm 88103 USA
Notice details come from SAM.gov. Updated .
About this opportunity
This solicitation seeks a firm-fixed-price construction contract to replace the primary and secondary electrical distribution systems at Cannon Air Force Base in New Mexico. The Department of the Air Force Special Operations Command is procuring these services. The contractor must replace the existing overhead distribution lines with an underground system installed via horizontal directional boring and trenching methods, in accordance with provided specifications, drawings, and statements of work. Responses are due by August 6, 2020, and the Air Force will use Two-Step Sealed Bidding procedures to evaluate technically acceptable bids received.
This opportunity is set aside for Service-Disabled Veteran-Owned Small Businesses. The projected NAICS codes are 238210 and 238910, with an estimated period of performance of 210 calendar days. The place of performance will be Cannon Air Force Base located in Curry County, New Mexico. The contractor must meet all standards of the Burlington North Santa Fe Railroad, New Mexico Department of Transportation, New Mexico Department of Safety, Xcel Energy, Blue Stake/811, and Eastern New Mexico Water Use Authority for work outside of Air Force jurisdiction.
Notice text
4 versions
Update #4 · Latest ·
UPDATE 2: IAW FAR 14.503-2(b), the following two companies will move on to Step Two of this Two-Step Sealed Bidding process.
1. Hartland-Reliant JV LLC, CAGE: 86J71, Address: 854 S Charlo Dr, Pueblo West, CO 81007
2. R-con Construction, Inc, CAGE: 1L0D3, Address: 5195 Bataan Memorial W, Las Cruces, NM 88012
AMENDMENT 1: The purpose of this amendment is to update the Statement of Work (SOW) with a revised version entitled 'SOW Rev 1 dated 27 July 2020' based on the Q&As and extend the proposal due date to 6 August 2020, no later than 2pm (MT).
*Note: Solicitation Amendment 0001 dated 28 July 2020 and SOW Rev 1 dated 27 July 2020 are attached.
UPDATE 1: The purpose of this update is to attach the questions and answers (Q&As) and attendance sheet from the site visit. An Amendment to the solicitation to reflect these changes is forthcoming.
This construction project is to replace the Primary and Secondary Electrical Distribution at CAFB, NM in accordance with the Statement of Work, Specifications and Drawings. The contractor shall replace the overhead distribution system with an underground system. The underground system shall be installed via boring and trenching and shall meet specifications referenced within the solicitation. Additionally, the work to be completed shall meet standards of the governing agency when it falls outside the jurisdiction of the Air Force, including but not limited to Burlington North Santa Fe (BNSF)/Jones Lang LaSalle (JLL), New Mexico Department of Transportation (NMDOT), New Mexico Department of Safety, Xcel Energy, Blue Stake/811, and the Eastern New Mexico Water Use
Authority (ENMWUA).
This project is a firm-fixed-price solicitation, utilizing Two-Step Sealed Bidding procedures prescribed at FAR Subpart 14.5.
Update #3 ·
AMENDMENT 1: The purpose of this amendment is to update the Statement of Work (SOW) with a revised version entitled 'SOW Rev 1 dated 27 July 2020' based on the Q&As and extend the proposal due date to 6 August 2020, no later than 2pm (MT).
*Note: Solicitation Amendment 0001 dated 28 July 2020 and SOW Rev 1 dated 27 July 2020 are attached.
UPDATE 1: The purpose of this update is to attach the questions and answers (Q&As) and attendance sheet from the site visit. An Amendment to the solicitation to reflect these changes is forthcoming.
This construction project is to replace the Primary and Secondary Electrical Distribution at CAFB, NM in accordance with the Statement of Work, Specifications and Drawings. The contractor shall replace the overhead distribution system with an underground system. The underground system shall be installed via boring and trenching and shall meet specifications referenced within the solicitation. Additionally, the work to be completed shall meet standards of the governing agency when it falls outside the jurisdiction of the Air Force, including but not limited to Burlington North Santa Fe (BNSF)/Jones Lang LaSalle (JLL), New Mexico Department of Transportation (NMDOT), New Mexico Department of Safety, Xcel Energy, Blue Stake/811, and the Eastern New Mexico Water Use
Authority (ENMWUA).
This project is a firm-fixed-price solicitation, utilizing Two-Step Sealed Bidding procedures prescribed at FAR Subpart 14.5.
Update #2 ·
UPDATE 1: The purpose of this update is to attach the questions and answers (Q&As) and attendance sheet from the site visit. An Amendment to the solicitation to reflect these changes is forthcoming.
This construction project is to replace the Primary and Secondary Electrical Distribution at CAFB, NM in accordance with the Statement of Work, Specifications and Drawings. The contractor shall replace the overhead distribution system with an underground system. The underground system shall be installed via boring and trenching and shall meet specifications referenced within the solicitation. Additionally, the work to be completed shall meet standards of the governing agency when it falls outside the jurisdiction of the Air Force, including but not limited to Burlington North Santa Fe (BNSF)/Jones Lang LaSalle (JLL), New Mexico Department of Transportation (NMDOT), New Mexico Department of Safety, Xcel Energy, Blue Stake/811, and the Eastern New Mexico Water Use
Authority (ENMWUA).
This project is a firm-fixed-price solicitation, utilizing Two-Step Sealed Bidding procedures prescribed at FAR Subpart 14.5.
Update #1 ·
This construction project is to replace the Primary and Secondary Electrical Distribution at CAFB, NM in accordance with the Statement of Work, Specifications and Drawings. The contractor shall replace the overhead distribution system with an underground system. The underground system shall be installed via boring and trenching and shall meet specifications referenced within the solicitation. Additionally, the work to be completed shall meet standards of the governing agency when it falls outside the jurisdiction of the Air Force, including but not limited to Burlington North Santa Fe (BNSF)/Jones Lang LaSalle (JLL), New Mexico Department of Transportation (NMDOT), New Mexico Department of Safety, Xcel Energy, Blue Stake/811, and the Eastern New Mexico Water Use
Authority (ENMWUA).
This project is a firm-fixed-price solicitation, utilizing Two-Step Sealed Bidding procedures prescribed at FAR Subpart 14.5.
Attachments
Show all 17
Notice history
| Notice | Type | Posted |
|---|---|---|
| Replace Primary & Secondary Electrical Distribution Phase 3 | Award Notice | |
| Replace Primary & Secondary Electrical Distribution Phase 3 | Solicitation | |
| Replace Primary & Secondary Electrical Distribution Phase 3 | Pre-Solicitation | |
| Replace Primary & Secondary Electrical Distribution Phase 3 | Pre-Solicitation |
On GovTribe
Work this opportunity on GovTribe
- Track it in your pipeline
- Find teaming partners
- Similar opportunities
- Ask GovTribe AI about this opportunity