Attachment 12_SOMS dated 14 May 2020.xlsx

XLSX spreadsheet 23 KB Posted

Attached to
Replace Primary & Secondary Electrical Distribution Phase 3 Federal contract opportunity
Solicitation number
FA4855-20-B-0006
Issued by
Department of the Air Force Special Operations Command

About this file

This document outlines submittal requirements for a firm-fixed-price construction project to replace the primary and secondary electrical distribution system at Cannon Air Force Base in New Mexico. The contractor shall install an underground distribution system via boring and trenching to replace the existing overhead system. Thirty-one submittals are required at various stages of the project, including a quality control plan, project schedule, environmental and waste management plans, safety documentation, as-built drawings, operation and maintenance manuals, low-voltage protective system shop drawings and documentation. Response dates range from 10 to 30 calendar days after contract award or notice to proceed. The Department of the Air Force Special Operations Command is the contracting agency.

View the file

Other files for this federal contract opportunity

Show all 16

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Sheet1

AF FORM 66 SCHEDULE OF MATERIALS SUBMITTALS - 14 May 2020PROJECT #PROJECT TITLESOLICITATION/CONTRACT NO.
CZQZ131130Primary and Secondary Electrical Distribution Phase 3FA485520B0006
TO BE COMPLETED BY PROJECT ENGINEERTO BE COMPLETED BY CONTRACT ADMINISTRATOR
NUMBER OF COPIES REQUIRED
LINE NUMBERITEM, DESCRIPTION OF ITEM, CONTRACT REFERENCE, TYPE OF SUBMITTALCERTIF OF COMPLIANCESCHEDULES/PLANSSHOP DRAWINGSSAMPLES / COLOR SELECTTEST RESULTSMANF'R RECOMMENDATIONSMANF'R. WARRANTYLICENSED APPLICATORMANUF'S TECHNICAL DATAO&M MANUALSOTHERREQUIRED SUBMISSION DATEDATE RECEIVED IN CONTRACTINGDATE TO CIVIL ENGINEERINGRETURN SUSPENSE DATEFOLLOW-UPCONTRACTOR NOTIFIED: Approval DateCONTRACTOR NOTIFIED: Disapproval DateCONTRACTOR RE-SUBMITTALFINAL APPROVALREMARKS
101 45 00. 05 20 Paragraph 1.3.3 Quality Control Plan(QCP)115 calendar days after NTP
201 32 01.00 10 Paragraph 3.1 subparagraphs .1 thru .5- Project Schedule -114 calendar days after NTP
301 35 40.00 20 paragraph 1.8 Environmental Protection Plan114 calendar days after NTP
401 74 19 Paragraph 1.3 Waste Management Plan115 business days after Award
501 35 26.paragraph 1.7 Accident Prevention Plan114 calendar days after NTP
601 35 26 Paragraph 1.9 Activity Hazard Analysis115 business days prior to each Definable Feature of Work/Phase
701 01 00.Paragraph 1.9 - AF Form 103 - Work Clearance Request110 business days prior to work start (follow form instructions for approval/renewal)
801 01 00 Paragraph 1.8 Utility Outage Request (CAFB IMT 3624)2NLT 21 calendar days prior to Outage
901 35 26 Paragraph 1.13.B Accident Report-1As Incident Occurs
1001 35 26 Paragraph 1.14 Hot Work Permit12 business days prior to Hot Work
1101 33 00 paragraph 11.c SD-11 Closeout Submittals130 days Prior to BOD
1201 78 23 Paragraph 1.5.5.a Electronic As-Built110 business days after BOD
1301 78 23 paragraph 1.5.5.b Hardcopy As-Builts110 business days after BOD
1401 33 00 paragraph 1.1.A.10 Operation and Mainteanance Data2222NLT 10 business days after BOD and prior to final payment
1501 33 00 paragraph 1.1.A.4 Product Data215 business days prior to each Definable Feature of Work/Phase
1626 41 00 para 1.4.1.1 LPS shop drawings114 business days prior to Construction
1726 41 00 para 1.2.3 LPS Installer Documentation214 business days prior to Construction
18Draft DD 1354130 calendar days after NTP
19Final Interim DD 13541Project Completion
20Builder Report1Project Completion
21Cable pulling tensions stamped by a PE licensed in the state of NM1Project Completion
22NMDOT Traffic Control Plan1Must be approved 14 calendar days prior to work start
23Daily Work Schedule17 calendar days prior to work execution
24Waste disposal and recycling data1Monthly
25HAZMAT information121 calendar days prior to the start of on-installation activities involving Hazardous Materials
26HAZMAT worksheet1Monthly
27Base Access Request Form15 Business Days prior to base access
28Project Phasing Plan114 calendar days after NTP
29Warranty Information2Prior to Final Payment