Q and A from site visit_27 Jul 2020.xlsx
XLSX spreadsheet 13 KB Posted
- Attached to
- Replace Primary & Secondary Electrical Distribution Phase 3 Federal contract opportunity
- Solicitation number
- FA4855-20-B-0006
About this file
This document contains questions and answers from a site visit related to solicitation number FA4855-20-B-0006 issued by the Department of the Air Force Special Operations Command. The solicitation is for a firm-fixed-price construction project to replace the primary and secondary electrical distribution system at Cannon Air Force Base in New Mexico. The work will include replacing the overhead distribution lines with an underground system installed via directional boring and trenching, and must meet specifications and standards of the Air Force as well as other governing agencies including BNSF Railway, New Mexico transportation and safety authorities, Xcel Energy, and local water authorities. Questions addressed include dimensions of manholes, acceptable conduit sizes, loading requirements, availability of laydown yards and disposal sites, flexibility on boring locations, and qualifications for key personnel filling multiple roles.
View the file
Other files for this federal contract opportunity
Show all 16
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Sheet1 Primary and Secondary Electrical Distribution Phase 3 Site Visit Questions FA4855-20-B-0006
| Questions | Answers | Reference Document | |
| 1 | Drawing C-3.1 shows the ductbank starting off as a directional bore dropping 5ft at a right angle, after 5 ft it levels out at near another right angle, travels 205lf before moving up 4ft at another 90 degree angle and switches at another angle greater than 100 degrees for about 115ft before turning another 45 degree angle up and then leveling off at Station 3+56.00. From Station 0+24.00 to the sectional cabinet at STA 6+12.00 there is approximately over 580lf of directional bore and over 360 degrees of bends. Due to the angles and length of the area between the stations there is no good way to pull the cable without damaging it, and we are also concerned that the manufacturer of the cable would not warranty it. |
Since we can’t splice the cable in the manhole until we get to sectionalizing cabinet 2 we recommend putting a small manhole will Bilco doors under the sectionalizing cabinets and to put a sectionalizing cabinet above the manhole for splicing. From the design drawings, the largest angular change is 18.004 degrees.
Splicing in the manhole is not allowed per the UFC/specifications.
We will not approve a sectionalzing cabinet in lieu of or in conjunction with the manhole. Additionally, we will not approve a sectionalizing cabinet off Air Force property.
If required, the cable can be pulled from the middle in opposite directions.
| Design Drawings Sheet C-3-1 | ||||
| 2 | Drawing C-3.1 shows that the new electrical manhole is 9’x12’. However, The dimensions listed on the table on sheet E-6.1 have the I.D. of the manhole as 6’x6’x6.5’. What are the correct dimensions of the new manhole? | 6'x6'x6.5' is the correct size for the manhole | Design Drawings Sheet E-6.1 | |
| 3 | For directional boring can we substitute the SCH 80 5" HDPE pipe for SCH 80 6" SDR11 pipe? | For Air Force requirements, drawings (5" Sch 80 HDPE) must be followed unless the specifications explicitly allow this change. Conduit used must meet requirements of the Air Force and the Authority Having Jurisdiction (AHJ) as indicated by the drawings. The wall thickness of 5" Sch 80 meets requirements of the railroad, changing the conduit will require re-approval by BNSF. | Specifications | |
| 4 | The specifications state the manhole must be rated for H20 wheel loading at the minimum, unless the unit will be placed where 100 KIP loading is necessary. Which load rating is required for this scenario? Also, the Electrical Manhole Detail references Fed Spec A-A-60005 Figure 4 & 12 (size 28) for the ring and cover, but these units are specified for nontraffic loading. I would like to proceed with a 28” clear opening cast iron ring and cover that meets the design loading required from above. In short, please let me know if this unit will require H20 or 100 KIP loading. | H20 is the requirement. | ||
| 5 | Will an on-site office be provided? | No an on-site office will not be provided; however space can be allocated for an on-site office if requested . | ||
| 6 | Will a laydown yard be availible? | Laydown yards are given out based on availablity (location provided in drawings). If all of the laydown yards are full, another area will be coordinated prior to material/equipment arrival; however temprorary fencing will not be provided. | ||
| 7 | Is a disposal site for directional boring natural by-products, all natural, available on base? | Products which do not exceed Federal or State screening levels for chemical constituents may be reused on site. Any products in need of disposal (i.e. leftover or exceeding chemical tolerances) need to be disposed of off site and shall be included in the (contractor's waste management plan). | Specs 01 57 19 | |
| 8 | On page 5 of the SOW; 4-A-2, (5) required positions are listed. Can the project superintendant fill the role of the superintendant, project manager, quality control manager and site health & safety officer? | Key personnell required per the SOW: |
Project Superintendent Project Manager Quality Control Manager Site Safety and Health Officer Master electrician
Per the specifications: 01 35 26 para 1.5.1.1.1 The SSHO may also serve as the quality control manager. The SSHO may also serve as the superintendent.
01 30 00 para 1.6.2 The superintendent can NOT be the quality control manager (CQC) unless written approval is requested and approval is obtained from the contracting officer.
Breaking this down: dual hatting is ok as long as the specifications are followed; however one individual fulfilling more than two roles is NOT permissable (i.e. we will NOT approve the superintendent to fill the roles of both the SSHO and CQC Manager)
This was updated in the SOW to be more clear. 01 35 26 para 1.5.1.1.1 01 30 00 para 1.6.2
SOW 4-A-2
| 9 | In some of the locations identified for boring machines it was noted the possibility of utilities under said locations. Will there be leniency in relocating or adjusting the placement of the bore or boring machine? | Yes there is flexibility in the location of the boring pits to avoid existing utilities. The specifications must be followed. This will need to be coordinated with the appropriate AHJ as well. | ||
| 10 | Would it be considered to continue with boring in lieu of trenching? The area behind housing units is covered with grass and will minimize disturbance. | It is acceptable to bore longer distances as long as the specifications and depths are followed. | ||
| 11 | In Volume II- STEP ONE – Technical Proposal Submission, Section 2. Instructions to Offerors on Page 53 or 65 it talks about the Divided Sections. The example says “SECTION 4: Offeror’s Experience”, but then we only get instructions for SECTION 1: Staffing and SECTION 2: Project Execution Plan. | This is a typo. There are only two Sections. The Divided Sections are SECTION 1: Staffing and SECTION 2: Project Execution Plan | ||
| 12 | SOW lists five personnel to make up the Key Personnel: Superintendent, Quality Control Manager, Site Safety and Health Officer, Project Manager and Master Electrician. The SOW further identifies several paragraphs within the specifications that should enumerate the qualifications and responsibilities (Superintendent, UFGS 01 30 00 paragraph 1.7.2 and Project Manager, UFGS 01 30 00 paragraph 1.7.3). There are no paragraphs 1.7.2 and 1.7.3. Furthermore, in the specification, it appears that the responsibilities of the Superintendent and the Project Manager have been merged. | It is acceptable for the Superintendent to dual hat and fulfill the role of the project manager as long as experience requirements are met for both positions. Experience required for the project manager as taken from UFS 01 30 00 paragraph 1.7.3.1: | ||
| "The Project Manager must have a minimum 10 years experience as a Project Manager or Superintendent on projects of similar size and complexity." | SOW/UFGS 01 30 00 |
Specifications-UFGS 01 30 00 para 1.6.2