Amend 002 - IIJA LIT ATCT, HVAC, Replace Boiler, Controls System
Closed Solicitation Posted
- Solicitation number
- 6973GH-25-R-00125
- Agency
- Franchise Acquisition Servies Federal Aviation Administration, Department of Transportation
- Responses due
- Set-aside
- No set-aside
Opportunity facts
- NAICS code
- 238220 Plumbing, Heating, and Air-Conditioning Contractors
- Place of performance
- Little Rock, Arkansas 72202, United States
- Points of contact
-
- Jason Perry jason.m.perry@faa.gov (405) 954-3141
Notice details come from SAM.gov. Updated .
About this opportunity
The Federal Aviation Administration (FAA) is seeking a small business contractor to comprehensively replace HVAC systems, boiler, and control infrastructure at the Bill and Hillary Clinton National Airport's Air Traffic Control Tower in Little Rock, Arkansas. The solicitation requires replacing three 15-ton split computer room HVAC systems, two 5-ton split HVACs for the Power Conditioning System, and the facility's existing boiler with a new Peerless 500,000 BTU unit. The project mandates installing a Schneider Electric Ecostruxure control system, creating new graphic pages, implementing a new computer interface/control workstation with Enterprise Server software, and installing CAT6 cable with ring topology networking. Proposals are due by June 10, 2025, with a site visit originally scheduled for May 7, 2025. Contractors must demonstrate prior experience with commercial HVAC units, Schneider Electric Ecostruxure controls, and boiler replacement through submission of organizational experience forms.
The contract is specifically designated as a small business set-aside with an estimated value between $850,000 and $1,500,000. The project performance period is 180 days following the notice to proceed, with work to be performed at 2601 David Grundfest Jr. Dr, Little Rock, AR 72202. Contractors must maintain continuous facility cooling during construction, coordinate with the FAA Contracting Officer's Representative, and potentially undergo background checks for on-site personnel. Only one HVAC unit may be worked on simultaneously, and contractors must submit a detailed written plan outlining construction sequencing and methods to ensure operational air conditioning throughout the project. Additional requirements include removing and replacing the under-floor leak detection system, creating new control schematics, and ensuring all new systems have the capacity to manage and potentially expand control of HVAC systems throughout the facility.
Notice text
4 versions
Update #4 · Latest ·
Amendment 002:
The purpose of this amendment is to attach revision 01 to attachment 16 Att 03 230900 SF.
------------------------------------------------------------------------------------------------
Amendment 001:
The purpose of this amendment is to extend the SIR closing date.
------------------------------------------------------------------------------------------------
Questions and Answers are hereby posted in the Attachments (17 Questions and Answers)
------------------------------------------------------------------------------------------------
BRAND NAME: Schneider Electric Ecostruxure System
******This requirement will be a Competed Small Business Setaside.*****
The Federal Aviation Administration’s, Bill and Hillary Clinton National Airport, Little Rock Air Traffic Control Tower (LIT ATCT) has three (3), 15-ton split computer room system HVACs that shall be replaced. The two 5 ton split computer room HVACs for the Power Conditioning System (PCS) in the Environmental Support Unit Building (ESU) shall also be replaced. The boiler for the facility shall be removed and replaced. Additionally, all controls shall be replaced. The system, controls, and computer shall replace all existing controls on the current HVAC equipment, and have the capacity to manage and expand to control all HVAC systems throughout the facility. The initial installation shall replace all field components and sensors associated with the Liebert Units that provide the equipment room cooling in the main building and the two Liebert units in the detached Environmental Support Building. The new system shall include all components and field wiring to make the new system fully operational when complete, including a new computer interface/control work station, with Enterprise Server software installed. Contractor shall create new EBO graphic page, and create new control schematic layout. Contractor shall provide and install all new CAT6 cable and ring topology network as required for a fully operational system. Contractor shall remove and replace the under floor leak detection system. The contractor shall furnish necessary equipment, materials, labor and supervision to perform the following work at the LIT ATCT located at 2601 David Grundfest Jr. Dr, Little Rock, AR 72202. Work within this area requires escort, and might include background checks for all onsite personnel, and must be coordinated with the FAA Contracting Officer’s Representative (COR) in advance. Adequate cooling must be maintained within the facility during the construction. Only one unit may be worked on at a time. The Contractor must submit a written plan/sequence of construction detailing the methods, equipment, points of connection, etc. that will be utilized to provide an operational air conditioning system at all times and adhere to the sequence of work proposed for removal and replacement of the HVAC units and controls.
Update #3 ·
Amendment 001:
The purpose of this amendment is to extend the SIR closing date.
------------------------------------------------------------------------------------------------
Questions and Answers are hereby posted in the Attachments (17 Questions and Answers)
------------------------------------------------------------------------------------------------
BRAND NAME: Schneider Electric Ecostruxure System
******This requirement will be a Competed Small Business Setaside.*****
The Federal Aviation Administration’s, Bill and Hillary Clinton National Airport, Little Rock Air Traffic Control Tower (LIT ATCT) has three (3), 15-ton split computer room system HVACs that shall be replaced. The two 5 ton split computer room HVACs for the Power Conditioning System (PCS) in the Environmental Support Unit Building (ESU) shall also be replaced. The boiler for the facility shall be removed and replaced. Additionally, all controls shall be replaced. The system, controls, and computer shall replace all existing controls on the current HVAC equipment, and have the capacity to manage and expand to control all HVAC systems throughout the facility. The initial installation shall replace all field components and sensors associated with the Liebert Units that provide the equipment room cooling in the main building and the two Liebert units in the detached Environmental Support Building. The new system shall include all components and field wiring to make the new system fully operational when complete, including a new computer interface/control work station, with Enterprise Server software installed. Contractor shall create new EBO graphic page, and create new control schematic layout. Contractor shall provide and install all new CAT6 cable and ring topology network as required for a fully operational system. Contractor shall remove and replace the under floor leak detection system. The contractor shall furnish necessary equipment, materials, labor and supervision to perform the following work at the LIT ATCT located at 2601 David Grundfest Jr. Dr, Little Rock, AR 72202. Work within this area requires escort, and might include background checks for all onsite personnel, and must be coordinated with the FAA Contracting Officer’s Representative (COR) in advance. Adequate cooling must be maintained within the facility during the construction. Only one unit may be worked on at a time. The Contractor must submit a written plan/sequence of construction detailing the methods, equipment, points of connection, etc. that will be utilized to provide an operational air conditioning system at all times and adhere to the sequence of work proposed for removal and replacement of the HVAC units and controls.
Update #2 ·
Questions and Answers are hereby posted in the Attachments (17 Questions and Answers)
------------------------------------------------------------------------------------------------
BRAND NAME: Schneider Electric Ecostruxure System
******This requirement will be a Competed Small Business Setaside.*****
The Federal Aviation Administration’s, Bill and Hillary Clinton National Airport, Little Rock Air Traffic Control Tower (LIT ATCT) has three (3), 15-ton split computer room system HVACs that shall be replaced. The two 5 ton split computer room HVACs for the Power Conditioning System (PCS) in the Environmental Support Unit Building (ESU) shall also be replaced. The boiler for the facility shall be removed and replaced. Additionally, all controls shall be replaced. The system, controls, and computer shall replace all existing controls on the current HVAC equipment, and have the capacity to manage and expand to control all HVAC systems throughout the facility. The initial installation shall replace all field components and sensors associated with the Liebert Units that provide the equipment room cooling in the main building and the two Liebert units in the detached Environmental Support Building. The new system shall include all components and field wiring to make the new system fully operational when complete, including a new computer interface/control work station, with Enterprise Server software installed. Contractor shall create new EBO graphic page, and create new control schematic layout. Contractor shall provide and install all new CAT6 cable and ring topology network as required for a fully operational system. Contractor shall remove and replace the under floor leak detection system. The contractor shall furnish necessary equipment, materials, labor and supervision to perform the following work at the LIT ATCT located at 2601 David Grundfest Jr. Dr, Little Rock, AR 72202. Work within this area requires escort, and might include background checks for all onsite personnel, and must be coordinated with the FAA Contracting Officer’s Representative (COR) in advance. Adequate cooling must be maintained within the facility during the construction. Only one unit may be worked on at a time. The Contractor must submit a written plan/sequence of construction detailing the methods, equipment, points of connection, etc. that will be utilized to provide an operational air conditioning system at all times and adhere to the sequence of work proposed for removal and replacement of the HVAC units and controls.
Update #1 ·
BRAND NAME: Schneider Electric Ecostruxure System
******This requirement will be a Competed Small Business Setaside.*****
The Federal Aviation Administration’s, Bill and Hillary Clinton National Airport, Little Rock Air Traffic Control Tower (LIT ATCT) has three (3), 15-ton split computer room system HVACs that shall be replaced. The two 5 ton split computer room HVACs for the Power Conditioning System (PCS) in the Environmental Support Unit Building (ESU) shall also be replaced. The boiler for the facility shall be removed and replaced. Additionally, all controls shall be replaced. The system, controls, and computer shall replace all existing controls on the current HVAC equipment, and have the capacity to manage and expand to control all HVAC systems throughout the facility. The initial installation shall replace all field components and sensors associated with the Liebert Units that provide the equipment room cooling in the main building and the two Liebert units in the detached Environmental Support Building. The new system shall include all components and field wiring to make the new system fully operational when complete, including a new computer interface/control work station, with Enterprise Server software installed. Contractor shall create new EBO graphic page, and create new control schematic layout. Contractor shall provide and install all new CAT6 cable and ring topology network as required for a fully operational system. Contractor shall remove and replace the under floor leak detection system. The contractor shall furnish necessary equipment, materials, labor and supervision to perform the following work at the LIT ATCT located at 2601 David Grundfest Jr. Dr, Little Rock, AR 72202. Work within this area requires escort, and might include background checks for all onsite personnel, and must be coordinated with the FAA Contracting Officer’s Representative (COR) in advance. Adequate cooling must be maintained within the facility during the construction. Only one unit may be worked on at a time. The Contractor must submit a written plan/sequence of construction detailing the methods, equipment, points of connection, etc. that will be utilized to provide an operational air conditioning system at all times and adhere to the sequence of work proposed for removal and replacement of the HVAC units and controls.