Lake fork erfo road repair
Closed Solicitation Posted
This opportunity was awarded. See the award notice from .
- Solicitation number
- 1122528
- Agency
- Forest Service Department of Agriculture
- Responses due
- Set-aside
- Total Small Business
Opportunity facts
- NAICS code
- 237310 Highway, Street, and Bridge Construction
- Place of performance
- Price, Utah 84501, United States
- Points of contact
-
- Lucas Dahlman lucas.dahlman@usda.gov (801) 625-5605
- Janice King janice.king@usda.gov (405) 571-3383
Notice details come from SAM.gov. Updated .
About this opportunity
The Department of Agriculture Forest Service is seeking contractors to repair damage to Forest Road 50070, also known as the Lake Fork Road, that was caused by 2021 monsoon storms. The work will involve culvert replacement, gravel fill, drainage grading, rock riprap placement, general roadway repair, and surface replacement. The intent is to provide for the complete construction of the project as described in the contract documents, including the Statement of Work and Schedule of Items. Proposals will be evaluated based on criteria such as past performance, experience/qualifications, and technical approach. Proposals are due by July 30, 2024, and the period of performance is estimated to be August 15, 2024 to September 30, 2025.
This solicitation is set aside for small businesses. The total estimated value of the base contract work is between $250,000 and $500,000, with an additional $1,000,000 to $5,000,000 in option items. The project is located approximately 19 miles from Spanish Fork City, Utah. The contractor will be responsible for providing all labor, materials, equipment, and transportation to complete the work in accordance with the FP-14 specifications and supplemental project documents.
Notice text
4 versions
Update #4 · Latest ·
UPDATED -7-18-2024 - Amendment 0003 - Q&A's and Incorporated Attendee's List from Site Visit.
UPDATED - 7-10-2024 - Amendment 0002 - Q&A
UPDATED - 7-4-2024 - Amendment 0001 - Update to sign requirement. See attachment 7
This project consists of repairing damage to Forest Road 50070, Lake Fork Road. The road was severely damaged during 2021 monsoon storms hitting a recent burn area above the roadway. The work will consist of culvert replacement, gravel fill, drainage grading, rock riprap placement, general roadway repair, surface replacement and function of the roadway. The intent of the contract is to provide for the complete construction of the project described in the contract. Unless otherwise provided, the contractor is to furnish all labor, materials, equipment, tools, transportation, and supplies and perform all work required to complete the project in reasonably close conformity with the drawings and specifications, and in accordance with the provisions of the contract. Payment for contract work will be made only for and under those pay items included in the Schedule of Items. All other work and materials will be considered as incidental to and included in the payment for the items shown in the Schedule. See the attached SOW and SOI for more details.
Update #3 ·
UPDATED - 7-10-2024 - Amendment 0002 - Q&A
UPDATED - 7-4-2024 - Amendment 0001 - Update to sign requirement. See attachment 7
This project consists of repairing damage to Forest Road 50070, Lake Fork Road. The road was severely damaged during 2021 monsoon storms hitting a recent burn area above the roadway. The work will consist of culvert replacement, gravel fill, drainage grading, rock riprap placement, general roadway repair, surface replacement and function of the roadway. The intent of the contract is to provide for the complete construction of the project described in the contract. Unless otherwise provided, the contractor is to furnish all labor, materials, equipment, tools, transportation, and supplies and perform all work required to complete the project in reasonably close conformity with the drawings and specifications, and in accordance with the provisions of the contract. Payment for contract work will be made only for and under those pay items included in the Schedule of Items. All other work and materials will be considered as incidental to and included in the payment for the items shown in the Schedule. See the attached SOW and SOI for more details.
Update #2 ·
UPDATED - 7-4-2024 - Amendment 0001 - Update to sign requirement. See attachment 7
This project consists of repairing damage to Forest Road 50070, Lake Fork Road. The road was severely damaged during 2021 monsoon storms hitting a recent burn area above the roadway. The work will consist of culvert replacement, gravel fill, drainage grading, rock riprap placement, general roadway repair, surface replacement and function of the roadway. The intent of the contract is to provide for the complete construction of the project described in the contract. Unless otherwise provided, the contractor is to furnish all labor, materials, equipment, tools, transportation, and supplies and perform all work required to complete the project in reasonably close conformity with the drawings and specifications, and in accordance with the provisions of the contract. Payment for contract work will be made only for and under those pay items included in the Schedule of Items. All other work and materials will be considered as incidental to and included in the payment for the items shown in the Schedule. See the attached SOW and SOI for more details.
Update #1 ·
This project consists of repairing damage to Forest Road 50070, Lake Fork Road. The road was severely damaged during 2021 monsoon storms hitting a recent burn area above the roadway. The work will consist of culvert replacement, gravel fill, drainage grading, rock riprap placement, general roadway repair, surface replacement and function of the roadway. The intent of the contract is to provide for the complete construction of the project described in the contract. Unless otherwise provided, the contractor is to furnish all labor, materials, equipment, tools, transportation, and supplies and perform all work required to complete the project in reasonably close conformity with the drawings and specifications, and in accordance with the provisions of the contract. Payment for contract work will be made only for and under those pay items included in the Schedule of Items. All other work and materials will be considered as incidental to and included in the payment for the items shown in the Schedule. See the attached SOW and SOI for more details.
Attachments
| File | Type | Posted |
|---|---|---|
| 1282B124R0024_A00003_LAKE FORK ERFO_S.pdf | ||
| 1282B124R0024_A0002_S.pdf | ||
| 1282B124R0024_A0001_S.pdf | ||
| Attachment 7 - Signs.pdf | ||
| 1282B124R0024_LAKE FORK.pdf | ||
| Attach 3 - Lake Fork ERFO Drawing Signed 06.07.2024_ Rev 1.pdf | ||
| Attach 5 - Wage Determination_UT20240109_Lake Fork ERFO Rd Repair.pdf | ||
| Attach 1 - SOW_Lake Fork ERFO 06.07.2024_REV 1.pdf | ||
| Attach 2 - SOI_Lake Fork _06.07.2024_REV1.xlsx | XLSX spreadsheet | |
| Attach 4 - FSSS_All_Supplementals_2403 (1) 06.07.2024.pdf | ||
| Attach 6- Location Map.pdf |
Show all 11
Notice history
| Notice | Type | Posted |
|---|---|---|
| Lake fork erfo road repair | Award Notice | |
| Lake fork erfo road repair | Solicitation | |
| Lake fork erfo road repair | Pre-Solicitation |
On GovTribe
Work this opportunity on GovTribe
- Track it in your pipeline
- Find teaming partners
- Similar opportunities
- Ask GovTribe AI about this opportunity