This document is an amendment to a solicitation for the LAKE FORK ERFO ROAD REPAIR project. The purpose of this amendment is to provide a question and answer related to the project timeline, and indicate that an additional amendment may be posted after the question due date of July 18, 2024.
The project consists of repairing damage to Forest Road 50070, including culvert replacement, gravel fill, drainage grading, rock riprap placement, surface replacement, and other roadway repairs. The period of performance is from August 15, 2024 to September 30, 2025, but the Forest Service is offering flexibility for the contractor to complete the work in either the 2024 or 2025 field season, as long as the project is finished by the final date of September 30, 2025. All other terms and conditions of the solicitation remain unchanged.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| 1282B124R0024_A00003_LAKE FORK ERFO_S.pdf | ||
| 1282B124R0024_A0001_S.pdf | ||
| Attachment 7 - Signs.pdf | ||
| Attach 2 - SOI_Lake Fork _06.07.2024_REV1.xlsx | XLSX spreadsheet | |
| Attach 4 - FSSS_All_Supplementals_2403 (1) 06.07.2024.pdf | ||
| Attach 6- Location Map.pdf | ||
| 1282B124R0024_LAKE FORK.pdf | ||
| Attach 3 - Lake Fork ERFO Drawing Signed 06.07.2024_ Rev 1.pdf | ||
| Attach 5 - Wage Determination_UT20240109_Lake Fork ERFO Rd Repair.pdf | ||
| Attach 1 - SOW_Lake Fork ERFO 06.07.2024_REV 1.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
(x)
1282B124R0024 x x
1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted ; or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGEMENT TO BE
RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR
OFFER. If by virtue of this amendment you desire to change an offer already submitted , such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
x
82B1
WASHINGTON DC 20250-0001
1400 INDEPENDENCE AVE SW MS-1138
SPOC INTERMOUNTAIN
USDA FOREST SERVICE
07/10/20240002
13. THIS ITEM ONLY APPLIES TO MODIFICATION OF CONTRACTS/ORDERS. IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
12. ACCOUNTING AND APPROPRIATION DATA (If required) is not extended.is extended, Items 8 and 15, and returning
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended , by one of the following methods: (a) By completing
The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
FACILITY CODE CODE
10B. DATED (SEE ITEM 13)
10A. MODIFICATION OF CONTRACT/ORDER NO.
9B. DATED (SEE ITEM 11)
9A. AMENDMENT OF SOLICITATION NO.
CODE
8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State and ZIP Code)
7. ADMINISTERED BY (If other than Item 6)CODE 6. ISSUED BY
PAGE OF PAGES
4. REQUISITION/PURCHASE REQ. NO.3. EFFECTIVE DATE2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO. (If applicable)
1. CONTRACT ID CODE
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
06/20/2024
CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority) appropriation data, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
E. IMPORTANT: Contractor is not is required to sign this document and return __________________ copies to the issuing office.
ORDER NO. IN ITEM 10A.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
The purpose of this Amendment is to:
1. Provide a question and answer at this time.
2. An additional amendment will posted, as needed, after the question due date of July 18th, 2024.
3. See summary of changes
4. All other terms and conditions remain unchanged.
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)15A. NAME AND TITLE OF SIGNER (Type or print)
15C. DATE SIGNED 16B. UNITED STATES OF AMERICA 15B. CONTRACTOR/OFFEROR 16C. DATE SIGNED
(Signature of person authorized to sign) (Signature of Contracting Officer)
LUCAS J. DAHLMAN
STANDARD FORM 30 (REV. 11/2016)
Prescribed by GSA FAR (48 CFR) 53.243
Previous edition unusable
Except as provided herein, all terms and conditions of the document referenced in Item 9 A or 10A, as heretofore changed, remains unchanged and in full force and effect .
7-10-2024
Summary Of Changes
Question #1: According to the solicitation, the period of performance is from August 15, 2024, to
September 30, 2025. A contractor stated that it seemed feasible for his company to complete the project in approximately 45 days assuming a completion date by 9-30-2024. Given this, they were wondering if there are specific milestone dates or boundary times you would like each section of the project to be completed by, or if the timeline is more flexible as long as the project is finished by the final date of
September 30, 2025.”
Answer: The time frame on the project is to provide contractor flexibility to the field season that would work best for them, either 2024 or 2025. The Forest Service was not sure how late in the year it would take to get everything ready for a contractor this spring, so we are offering the flexibility to begin/complete in the 2025 season if necessary. The plan will be to close the road to the public for the project, so it is preferred that the project be started/completed in one season or the other weather permitting.