GAOA Tony Grove Dam Spillway Capacity & Seismic Mitigation, Uinta/Wasatch/Cache National Forest

Open Solicitation Posted

Solicitation number
1240BH27Q0002
Agency
Responses due
Set-aside
Total Small Business

Opportunity facts

Place of performance
Garden City, Utah, United States

Notice details come from SAM.gov. Updated .

About this opportunity

The Department of Agriculture Forest Service seeks construction services for the Tony Grove Dam Spillway Capacity & Seismic Mitigation project on the Uinta/Wasatch/Cache National Forest, with quotes due November 20, 2026. This is a total small business set-aside; the small business size standard is $45 million.

Place of performance is Garden City, Utah. The project runs from June 1, 2027 through October 1, 2027, with contractors required to commence work within 10 calendar days of receiving notice to proceed. Work includes reconstructing portions of the Tony Grove Dam, replacing outlet works, raising the dam crest, and adding embankment material. The NAICS code is 237990, Construction of Dams; PSC is Y1KA.

The estimated price range is $1 million to $5 million. A 20% bid guarantee (Standard Form 24) is required for quotes exceeding $150,000. Performance and payment bonds are required within 10 calendar days of award. Davis-Bacon Act prevailing wage requirements apply; the Department of Labor determination UT20260105 (modified May 18, 2026) establishes wage rates and fringe benefits for Cache County, Utah, including $13.65 minimum wage per Executive Order 13658 through December 31, 2026, and paid sick leave requirements under Executive Order 13706.

Award will be made on best value to the Government based on comparative evaluation of four factors: Technical and Project Management (technical approach, project management/oversight, and performance schedule); Experience (relevant projects completed within five years); Past Performance; and Price. Technical proposals must include detailed equipment descriptions, logistics, crew accommodations, subcontractor information, biobased products, organizational structure with key personnel resumes, and detailed project schedule. A mandatory site visit is scheduled for October 15, 2026 at 1:00 p.m. MDT. Questions are due October 20, 2026 at 5:00 p.m. MDT to Contract Specialist Judith Martin at PPS.proposals@usda.gov. Contractors must be registered in SAM.gov and submit unit pricing for all base and optional line items. The solicitation includes standard FAR and AGAR clauses applicable to commercial construction, including Buy American Act requirements for construction materials.

Notice text

2 versions

Update #2 · Latest ·

This is a combined synopsis/solicitation for commercial construction prepared in accordance with the format in FAR Part 12. This announcement constitutes the only solicitation; quotes are being requested, and a separate written solicitation will not be issued. 

Solicitation number 1240BH27Q0002 is issued as a Request for Quotation (RFQ) for the Tony Grove Dam Spillway Capacity & Seismic Mitigation on the Uinta/Wasatch/Cache National Forest.

This project consists of reconstructing portions of the Tony Grove Dam as shown in the drawings and described in the specifications. This also includes replacing outlet works and raising the dam crest along with the addition of embankment material.

This acquisition is set-aside for small business concerns. The applicable North American Industry Classification System Code is 237990. The small business size standard is $45 Million. This acquisition is a total Small Business set-aside.   All responsible sources may submit a quotation which will be considered by the agency. 

Amendment 01 - Summary: Extend quote due date to November 20, 2026.

Update #1 ·

This is a combined synopsis/solicitation for commercial construction prepared in accordance with the format in FAR Part 12. This announcement constitutes the only solicitation; quotes are being requested, and a separate written solicitation will not be issued. 

Solicitation number 1240BH27Q0002 is issued as a Request for Quotation (RFQ) for the Tony Grove Dam Spillway Capacity & Seismic Mitigation on the Uinta/Wasatch/Cache National Forest.

This project consists of reconstructing portions of the Tony Grove Dam as shown in the drawings and described in the specifications. This also includes replacing outlet works and raising the dam crest along with the addition of embankment material.

This acquisition is set-aside for small business concerns. The applicable North American Industry Classification System Code is 237990. The small business size standard is $45 Million. This acquisition is a total Small Business set-aside.   All responsible sources may submit a quotation which will be considered by the agency. 

Files

Similar open opportunities

Opportunity Agency Set-aside Responses due
Yellow Lake Disaster Relief Project – Watershed / Uinta-Wasatch-Cache NF Kamas, Utah 84036, United States · NAICS 115310 Forest Service Total Small Business
4 GAOA Flaming Gorge Water System Buckboard in Ashley NF, Wyoming Mc Kinnon, Wyoming 82935, United States · NAICS 237110 Forest Service Total Small Business
Camptonville Housing Decommissioning Nevada City, California 95959, United States · NAICS 238910 Forest Service Total Small Business
Ross Springs Waterline Replacement Utah 84078, United States · NAICS 237110 Forest Service Total Small Business
GAOA Brainard Lake Recreation Area Deferred Maintenance Ward, Colorado 80481, United States · NAICS 237310 Forest Service Total Small Business

On GovTribe

Work this opportunity

  • Track it in your pipeline
  • Find teaming partners
  • Similar opportunities
  • Ask GovTribe AI about this opportunity

GovTribe for Federal Contractors