Forward Hadronic Calorimeter Absorber Structures

Closed Solicitation Posted

Solicitation number
MB457842
Agency
Responses due
Set-aside
Woman-Owned Small Business

Opportunity facts

Place of performance
Upton, New York, United States

Notice details come from SAM.gov. Updated .

About this opportunity

The Department of Energy Office of Science, procuring through Brookhaven National Laboratory, seeks manufacturing and delivery of forward hadronic calorimeter absorber steel structures for the Electron-Ion Collider detector, with proposals due August 16, 2026. This procurement is restricted to Woman-Owned Small Business concerns.

Place of performance is Upton, New York. The base contract requires delivery of 845 production 8M modules plus five pre-production units within 78 weeks of award, with unilateral options for 216 additional 8M modules and 72 4M modules deliverable within 130 weeks. The modules are iron-scintillator sampling calorimeters comprising alternating 16 mm magnetic carbon steel (AISI 1020) plates and 4 mm scintillator plates, electron-beam or laser-beam welded and optionally nickel-plated for corrosion prevention. Each 8M module measures approximately 200 mm by 100 mm transverse size; 4M modules are 100 mm by 100 mm. The specification is NAICS 332999, All Other Miscellaneous Fabricated Metal Product Manufacturing, PSC 9640.

Distinctive technical requirements include ISO-9001 compliant quality assurance systems, material certifications with Certified Material Test Reports, magnetic permeability documentation per ASTM A773, laser or electron-beam welding compliance with AWS C7.4 standards, and dimensional acceptance testing at Oak Ridge National Laboratory within 90 days of receipt. Pre-production testing of five 8M modules at ORNL must complete within 16 weeks and receive written BSA approval before production authorization. Contractors must provide a program plan and manufacturing/inspection/test plan within four weeks of award and maintain records for three years post-completion.

Evaluation is best value with technical factors outweighing price: Design and Technical Capabilities (50 points), Prior Experience and Past Performance (25 points), Manufacturing Capabilities (15 points), and Quality Assurance (10 points). Offerors must achieve a minimum 60 percent overall technical score to be responsive. Proposals must remain firm for 120 days. Freight terms are FOB Oak Ridge National Laboratory, Oak Ridge, Tennessee (freight prepaid for North American shipments, DAP for foreign), with Net 10 payment terms from acceptance. All offerors must register in SAM.gov and provide three years of audited financial statements and minimum three customer references for comparable projects. Amendment 5, issued July 30, added an updated Questions and Answers document; prior amendments extended the deadline from the original March 11 date, reopened the RFP on July 10 with revised SOW, specification, and drawings, and updated Q&A documents on July 23 and 30.

Notice text

7 versions

Update #7 · Latest ·

Please thoroughly review all attachments to this solicitation for details. Failure to respond in accordance with the RFP's instructions may deem your proposal as unacceptable.

All questions shall be submitted in writing to the Contract Specialist via email.

Amendment 5 issued on 7/30/2026 is to add an updated Questions & Answers document.

Amendment 4 issued on 7/23/2026 is to add an updated Questions & Answers document based on the re-release of the RFP.

Amendment 3 issued on 7/10/2026 is to reopen the RFP with revised SOW, Spec, and Drawings.

Amendment 2 issued on 3/20/2026 is to extend the deadline to 4/1/2026 and update the Statement of Work and Specification documents.

Amendment 1 issued on 3/5/2026 is to extend the deadline to 3/20/2026. An updated Specification and SOW are forthcoming and will be posted when they are finalized. The RFP's question and answers document has also been added as an attachment.

Update #6 ·

Please thoroughly review all attachments to this solicitation for details. Failure to respond in accordance with the RFP's instructions may deem your proposal as unacceptable.

All questions shall be submitted in writing to the Contract Specialist via email.

Amendment 4 issued on 7/23/2026 is to add an updated Questions & Answers document based on the re-release of the RFP.

Amendment 3 issued on 7/10/2026 is to reopen the RFP with revised SOW, Spec, and Drawings.

Amendment 2 issued on 3/20/2026 is to extend the deadline to 4/1/2026 and update the Statement of Work and Specification documents.

Amendment 1 issued on 3/5/2026 is to extend the deadline to 3/20/2026. An updated Specification and SOW are forthcoming and will be posted when they are finalized. The RFP's question and answers document has also been added as an attachment.

Update #5 ·

Please thoroughly review all attachments to this solicitation for details. Failure to respond in accordance with the RFP's instructions may deem your proposal as unacceptable.

All questions shall be submitted in writing to the Contract Specialist via email.

Amendment 3 issued on 7/10/2026 is to reopen the RFP with revised SOW, Spec, and Drawings.

Amendment 2 issued on 3/20/2026 is to extend the deadline to 4/1/2026 and update the Statement of Work and Specification documents.

Amendment 1 issued on 3/5/2026 is to extend the deadline to 3/20/2026. An updated Specification and SOW are forthcoming and will be posted when they are finalized. The RFP's question and answers document has also been added as an attachment.

Update #4 ·

Please thoroughly review all attachments to this solicitation for details. Failure to respond in accordance with the RFP's instructions may deem your proposal as unacceptable.

All questions shall be submitted in writing to the Contract Specialist via email.

Amendment 2 issued on 3/20/2026 is to extend the deadline to 4/1/2026 and update the Statement of Work and Specification documents.

Amendment 1 issued on 3/5/2026 is to extend the deadline to 3/20/2026. An updated Specification and SOW are forthcoming and will be posted when they are finalized. The RFP's question and answers document has also been added as an attachment.

Update #3 ·

Please thoroughly review all attachments to this solicitation for details. Failure to respond in accordance with the RFP's instructions may deem your proposal as unacceptable.

All questions shall be submitted in writing to the Contract Specialist via email.

Amendment 1 issued on 3/5/2026 is to extend the deadline to 3/20/2026. An updated Specification and SOW are forthcoming and will be posted when they are finalized. The RFP's question and answers document has also been added as an attachment.

Update #2 ·

Please thoroughly review all attachments to this solicitation for details. Failure to respond in accordance with the RFP's instructions may deem your proposal as unacceptable.

All questions shall be submitted in writing to the Contract Specialist via email.

Amendment 1 issued on 3/5/2026 is to extend the deadline to 3/20/2026. An updated Specification and SOW are forthcoming and will be posted when they are finalized.

Update #1 ·

Please thoroughly review all attachments to this solicitation for details. Failure to respond in accordance with the RFP's instructions may deem your proposal as unacceptable.

All questions shall be submitted in writing to the Contract Specialist via email.

Files

File Type Posted
RFP 457842 Questions and Answers_73026.pdf PDF
RFP 457842 Questions Answers_72326.pdf PDF
B.1 Enclosure 1 - Contract 457842.pdf PDF
B.1 Enclosure 2 – AMS Form 050, Annual Representations and Certifications.pdf PDF
Attachment A - BSA General Terms and Conditions for Non-Commercial Items Rev 24 (April 2026).pdf PDF
Attachment F - BNL-QA-101.pdf PDF
B.1 Enclosure 3 – AMS Form 043, Proposal Pricing Sheet.pdf PDF
Attachment E - Drawing EPC-FWD-HCL-DET-ASM-200.pdf PDF
Attachment G - RFP 457842 Questions and Answers.pdf PDF
B.1 RFP 457842.pdf PDF
Attachment B - EIC-DET-SOW-026 Statement of Work for the Forward Hadronic Calorimeter Absorber Structure Rev. 7 dated 06-18-26.pdf PDF
Attachment C - Technical Specification EIC-DET-SPC-021 dated 6-18-26.pdf PDF
Attachment D - Drawing EPC-FWD-HCL-DET-ASM-100.pdf PDF
Attachment B - EIC-DET-SOW-026 Statement of Work for the Forward Hadronic Calorimeter Absorber Structure dated 03-09-26.pdf PDF
Attachment C - Technical Specification EIC-DET-SPC-021 dated 03.09.26.pdf PDF
RFP 457842 Questions and Answers.pdf PDF
Attachment A - BSA General Terms and Conditions for Non-Commercial Items Rev 23 (May 2025).pdf PDF
Attachment C - Technical Specification EIC-DET-SPC-021 dated 12-4-24.pdf PDF
Attachment E - Drawing EPC-FWD-HCL-DET-ASM-200.pdf PDF
B.1 Enclosure 1 - Contract 457842.pdf PDF
Attachment D - Drawing EPC-FWD-HCL-DET-ASM-100.pdf PDF
B.1 Enclosure 2 – AMS Form 050, Annual Representations and Certifications.pdf PDF
Attachment B - EIC-DET-SOW-026 Statement of Work for the Forward Hadronic Calorimeter Absorber Structure Rev. 5 dated 01-09-26.pdf PDF
B.1 RFP 457842.pdf PDF
B.1 Enclosure 3 – AMS Form 043, Proposal Pricing Sheet.pdf PDF
Attachment F - BNL-QA-101.pdf PDF
Show all 26

Notice history

Notice Type Posted
This notice Latest solicitation Solicitation
Forward Hadronic Calorimeter Absorber Structures Pre-Solicitation
Forward Hadronic Calorimeter Absorber Structures Original Pre-Solicitation

Similar open opportunities

Opportunity Agency Set-aside Responses due
CPMU - HRD Insertion Device Upton, New York, United States · NAICS 335999 Office of Science No set-aside
Fabrication Menlo Park, California 94025, United States · NAICS 3333 Office of Science No set-aside

On GovTribe

Work this opportunity

  • Track it in your pipeline
  • Find teaming partners
  • Similar opportunities