About this opportunity

The Department of the Treasury Bureau of Engraving and Printing seeks development of design-build bridging documents for modernization of seventeen electric elevators (twelve passenger and five freight) at its Washington, DC facility, with proposals due July 28, 2026, with questions due June 30, 2026. This procurement is a total small business set-aside, and the most recent amendment (0003) extended the original July 21 deadline by seven days.

Place of performance is the Bureau's facility at 14th and C Streets S.W., Washington, DC 20228. The contractor shall deliver a survey report, basis of design documentation, and a 35% design submission with architectural, structural, mechanical, and electrical plans and specifications within 230 calendar days of notice to proceed, with intermediate milestones at 90, 135, and 185 days. Deliverables must address code compliance per DC Building Codes, IBC, NFPA, ANSI/ASME A17.1, and other applicable standards; include MEP systems upgrades, ACM abatement and PCB removal surveys, and structural alterations to machine rooms and hoistways; and integrate new elevator controllers with the Bureau's existing SCADA system. The contractor must also develop a draft commissioning plan, construction phasing plan, and preliminary cost and schedule estimates. Hazmat testing and reporting are required during this phase.

The NAICS code is 541330, Engineering Services. PSC code is C215, Architect and Engineering—General: Production Engineering. Evaluation criteria weight technical capability and past performance on similar Federal, State, Local, Commercial, or Foreign contracts within the last five years; price competitiveness also applies. Offerors must demonstrate experience with vertical transportation systems design, historical building work, and building control systems integration and must submit three relevant contract references. All contractor personnel require background security clearances, identification badges, non-disclosure agreements for sensitive but unclassified information, and compliance with BEP's physical security protocols. Proposals are submitted in three volumes: technical capability (10-page limit), past performance (10-page limit), and firm-fixed pricing with no page limit. An optional site visit was held June 24, 2026; Amendment 0002 (July 6, 2026) posted responses to clarifications and updated the Statement of Work.

Notice text

3 versions

Update #3 · Latest ·

16 July 2026 - Amendment 0003 to extend proposal due date.

6 July 2026 - Issue amendment 0002 to 

     1. Post Responses to questions. 

     2. Update Attachment 1 - SOW. 

     3. Update Section L.  

     4. Attach document 2e. 

     5. Attach Site Visit Sign-in sheet. 

18 June 2026 - Issue amendment 0001 to update Attachment 1 - Site Visit Information.

The Contractor shall develop bridging documents, consisting of conceptual design, technical specifications, and performance criteria for the complete repair of seventeen electric elevators (12 passenger and 5 freight as identified in the 2024 Elevator Assessment) replacing all components that are obsolete and/or have reached end-of-life, including MEP systems upgrades, ACM abatement, PCBs removal, structural and architectural alterations to bring the existing machine rooms and hoistways up to code. New elevator controllers shall be integrated with BEP’s existing Supervisory Control and Data Acquisition (SCADA) system.

The bridging documents should provide enough detail to allow successful solicitation of a design-build construction contract addressing complete alteration of the elevators.

The Contractor shall ensure compliance with all federal, state, and local regulations, minimize disruption to building operations during installation and achieve targeted energy savings and sustainability goals.

Update #2 ·

6 July 2026 - Issue amendment 0002 to 

     1. Post Responses to questions. 

     2. Update Attachment 1 - SOW. 

     3. Update Section L.  

     4. Attach document 2e. 

     5. Attach Site Visit Sign-in sheet. 

18 June 2026 - Issue amendment 0001 to update Attachment 1 - Site Visit Information.

The Contractor shall develop bridging documents, consisting of conceptual design, technical specifications, and performance criteria for the complete repair of seventeen electric elevators (12 passenger and 5 freight as identified in the 2024 Elevator Assessment) replacing all components that are obsolete and/or have reached end-of-life, including MEP systems upgrades, ACM abatement, PCBs removal, structural and architectural alterations to bring the existing machine rooms and hoistways up to code. New elevator controllers shall be integrated with BEP’s existing Supervisory Control and Data Acquisition (SCADA) system.

The bridging documents should provide enough detail to allow successful solicitation of a design-build construction contract addressing complete alteration of the elevators.

The Contractor shall ensure compliance with all federal, state, and local regulations, minimize disruption to building operations during installation and achieve targeted energy savings and sustainability goals.

Update #1 ·

18 June 2026 - Issue amendment 0001 to update Attachment 1 - Site Visit Information.

The Contractor shall develop bridging documents, consisting of conceptual design, technical specifications, and performance criteria for the complete repair of seventeen electric elevators (12 passenger and 5 freight as identified in the 2024 Elevator Assessment) replacing all components that are obsolete and/or have reached end-of-life, including MEP systems upgrades, ACM abatement, PCBs removal, structural and architectural alterations to bring the existing machine rooms and hoistways up to code. New elevator controllers shall be integrated with BEP’s existing Supervisory Control and Data Acquisition (SCADA) system.

The bridging documents should provide enough detail to allow successful solicitation of a design-build construction contract addressing complete alteration of the elevators.

The Contractor shall ensure compliance with all federal, state, and local regulations, minimize disruption to building operations during installation and achieve targeted energy savings and sustainability goals.

Files

Show all 18

Similar open opportunities

Opportunity Agency Set-aside Responses due
Cooling Tower, Roofing, and Structural Construction District of Columbia 20024, United States · NAICS 236220 Bureau of Engraving and Printing Total Small Business
Replace Elevators at FDC Miami Miami, Florida 33132, United States · NAICS 238290 BOP Field Acquisition Office Total Small Business
General Construction Services for Elevator Modernization at the Thurgood Marshall U. S. Courthouse, New York, NY New York, New York 10007, United States · NAICS 236220 — No set-aside
Maintenance Service for Portable Fire Extinguishers Washington, District of Columbia, United States · NAICS 541990 Bureau of Engraving and Printing Total Small Business
Elevator Maintenance Services - Potter Stewart US Courthouse, John Weld Peck Federal Building, and FDA-NFCC (Cincinnati, OH) Cincinnati, Ohio 45202, United States · NAICS 238290 — No set-aside

On GovTribe

Work this opportunity

  • Track it in your pipeline
  • Find teaming partners
  • Similar opportunities
  • Ask GovTribe AI about this opportunity