Comanche Park Campground Reconstruction
Closed Solicitation Posted
This opportunity was awarded. See the award notice from .
- Solicitation number
- 1240LT26Q0046
- Agency
- Region 2 - Rocky Mountain Region Forest Service, Department of Agriculture
- Responses due
- Set-aside
- Total Small Business
Opportunity facts
- NAICS code
- 237110 Water and Sewer Line and Related Structures Construction
- Place of performance
- Custer, South Dakota 57730, United States
- Points of contact
-
- Erick Plamann erick.plamann@usda.gov (612) 315-9982
- Lucas Dahlman lucas.dahlman@usda.gov (801) 625-5605
Notice details come from SAM.gov. Updated .
About this opportunity
The USDA Forest Service, Region 2–Rocky Mountain Region seeks reconstruction and expansion of Comanche Park Campground from 20 to 34 base sites, with quotations due May 11, 2026 at 12:00 PM Central Time. This is a Total Small Business Set-Aside under NAICS 237110, with a $45 million size standard.
Place of performance is Custer, South Dakota, 6.5 miles west of Custer on US Highway 16. The scope includes road modification with curve widening, drainage shaping, and new surfacing; relocation and upgrade of Host Site and Volunteer Site with power, water, and wastewater infrastructure; replacement of five 1965 stick-built toilets with four new pre-cast vault toilets; decommissioning the existing pumphouse and installing a new pre-cast concrete treatment building with upgraded plumbing and controls; removing the existing aboveground water storage tank and installing a new 3,000-gallon below-ground fiberglass water storage tank; replacing all distribution piping and installing new hydrants. The contractor furnishes all labor, materials, and equipment.
Estimated construction magnitude is between $1,000,000 and $5,000,000. Performance period is 392 days from Notice to Proceed, with work to commence approximately September 15, 2025, and complete by November 13, 2026. Water system installers must meet South Dakota licensing requirements; electricians must hold a South Dakota Electrical License with state inspection and approval required for all electrical work. Contractor must provide an Accident Prevention Plan, daily reports, permits and licenses, and operation and maintenance manuals.
An organized site visit is scheduled for April 17, 2026 at 9:00 AM Mountain Time; technical questions were due April 22, 2026. Amendment A0001, effective April 28, 2026, added Q&A documentation and revised specifications (v2). Evaluation criteria are experience and past performance, technical approach with construction schedule, and pricing. Single firm fixed-price award. Performance and payment bonds required within 10 calendar days after award. Pricing firm for 90 days from May 11. Contractors must comply with Davis-Bacon prevailing wage requirements, Buy American materials provisions, and FAR and AGAR clauses including anti-discrimination and DEI compliance certifications.
Notice text
2 versions
Update #2 · Latest ·
POC Erick Plamann, Contract Specialist, erick.plamann@usda.gov
Comanche Park Campground Reconstruction
The contractor will provide all labor, materials, and equipment for the campground improvement of 20 sites to 34 sites to include a road modification with curve widening and shaping for drainage and new surfacing. The Host Site and Volunteer Site will be relocated and upgraded with power, water and wastewater vaults. 4 new pre-cast vault toilets will replace the five original 1965 stick-built toilets. The Water system work for this project consists of decommissioning the existing pumphouse, installing a new pre-cast concrete treatment building in a new location, with upgraded plumbing and controls, removing the existing aboveground water storage tank and installing a new below ground fiberglass water storage tank, replacing all the distribution piping and installing new hydrants IAW with SOW, Specifications and Drawings
Magnitude of Construction is between $1,000,000 and $5,000,000
NAICS 237110 - Water and Sewer Line and Related Structures Construction
Organized Site Visit
Name: Richard Zacher
Address: Comanche Park Campground is located 6.5 miles west of Custer, SD on US16
Date and Time: April 17, 2026, 9:00 AM Mountain
Telephone: 605-673-9222 Email: richard.zacher@usda.gov
Questions and Answers updated
Update #1 ·
POC Erick Plamann, Contract Specialist, erick.plamann@usda.gov
Comanche Park Campground Reconstruction
The contractor will provide all labor, materials, and equipment for the campground improvement of 20 sites to 34 sites to include a road modification with curve widening and shaping for drainage and new surfacing. The Host Site and Volunteer Site will be relocated and upgraded with power, water and wastewater vaults. 4 new pre-cast vault toilets will replace the five original 1965 stick-built toilets. The Water system work for this project consists of decommissioning the existing pumphouse, installing a new pre-cast concrete treatment building in a new location, with upgraded plumbing and controls, removing the existing aboveground water storage tank and installing a new below ground fiberglass water storage tank, replacing all the distribution piping and installing new hydrants IAW with SOW, Specifications and Drawings
Magnitude of Construction is between $1,000,000 and $5,000,000
NAICS 237110 - Water and Sewer Line and Related Structures Construction
Organized Site Visit
Name: Richard Zacher
Address: Comanche Park Campground is located 6.5 miles west of Custer, SD on US16
Date and Time: April 17, 2026, 9:00 AM Mountain
Telephone: 605-673-9222 Email: richard.zacher@usda.gov
Attachments
| File | Type | Posted |
|---|---|---|
| Q and A.pdf | ||
| Comanche Site Visit.pdf | ||
| 1240LT26Q0046 A0001.pdf | ||
| Q and A.pdf | ||
| Attchment 3 Comanche_Specifications v2.pdf | ||
| Attachment 4 Maps and Drawaings.pdf | ||
| 1240LT26Q0046.pdf | ||
| Attachment 1 SOI.pdf | ||
| Attachment 2 SOW.pdf | ||
| Attachment 3_Comanche_Specifications.pdf | ||
| Attachment 5 Wage Determination.pdf |
Show all 11
Notice history
| Notice | Type | Posted |
|---|---|---|
| Comanche Park Campground Reconstruction | Award Notice | |
| Comanche Park Campground Reconstruction | Solicitation |
On GovTribe
Work this opportunity on GovTribe
- Track it in your pipeline
- Find teaming partners
- Similar opportunities
- Ask GovTribe AI about this opportunity