Attachment 2 SOW.pdf

PDF 308 KB Posted

Attached to
Comanche Park Campground Reconstruction Federal contract opportunity
Solicitation number
1240LT26Q0046
Issued by
Department of Agriculture Forest Service R2-Rocky Mountain Region

About this file

This is a Statement of Work (SOW) for the Comanche Park Campground Reconstruction project under the U.S. Department of Agriculture Forest Service, Black Hills National Forest, located 6.5 miles west of Custer, South Dakota on US Highway 16.

The project scope involves improving the campground from 20 sites to 34 sites, including road modifications with curve widening and drainage improvements, relocation and upgrade of host and volunteer sites with power, water, and wastewater infrastructure, replacement of five 1965 stick-built toilets with four new pre-cast vault toilets, and complete water system work including decommissioning the existing pumphouse, installing a new pre-cast concrete treatment building, replacing aboveground storage with a below-ground fiberglass tank, and replacing distribution piping and hydrants. Work must commence approximately 10 days after Notice to Proceed and be completed within 392 days. The campground operates seasonally from mid-May to mid-September. This is a Congressionally approved Great American Outdoors project that may include new trails connecting to nearby motorized trail systems.

Contractor requirements include demonstrated understanding of project requirements, strong communication skills, and experience in campground construction, general contracting, and road construction. Key personnel must include a company executive responsible for the project and an onsite superintendent at all times. Water system installers must meet South Dakota licensing requirements, and electricians must hold a South Dakota Electrical License with state inspection and approval required for all electrical work. The contractor bears all travel costs and is responsible for maintaining suitable barriers to protect the public, employees, and facilities. Deliverables include accident prevention plans, submittals, construction schedules, daily reports, permits and licenses, testing reports, operation and maintenance manuals, and project record documents, all due at specified intervals with delivery via email to the Contracting Officer.

View the file

Other files for this federal contract opportunity

Other files attached to Comanche Park Campground Reconstruction, newest first.
File Type Posted
Q and A.pdf PDF
Comanche Site Visit.pdf PDF
Q and A.pdf PDF
Attchment 3 Comanche_Specifications v2.pdf PDF
1240LT26Q0046 A0001.pdf PDF
Attachment 4 Maps and Drawaings.pdf PDF
1240LT26Q0046.pdf PDF
Attachment 1 SOI.pdf PDF
Attachment 3_Comanche_Specifications.pdf PDF
Attachment 5 Wage Determination.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

US Department of Agriculture (USDA)

United States Department of Agriculture

Forest Service

Black Hills National Forest

Black Hills Campground Reconstruction

Comanche Park Campground Statement of Work

Contents Project General Information

1.0 Scope of Work

2.0 Background

Contractor Requirements

3.0 Technical Requirements / Tasks

4.0 Government Furnished

5.0 Deliverables / Schedule

6.0 Travel

7.0 Contractor’s Key Personnel

8.0 Security Requirements

9.0 Data Rights

10.0 Section 508 – Electronic and Information Technology Standards

Project Comanche Park Campground Reconstruction

General Information

1.0 Scope of Work

Comanche Park Campground is located 6.5 miles west of Custer, SD on US16.

The Campground will be improved from 20 sites to 34 sites. The road will be modified with curve widening and shaping for drainage and new surfacing. The Host Site and Volunteer Site will be relocated and upgraded with power, water and wastewater vaults. 4 new pre-cast vault toilets will replace the five original 1965 stick-built toilets. The Water system work for this project consists of decommissioning the existing pumphouse, installing a new pre-cast concrete treatment building in a new location, with upgraded plumbing and controls, removing the existing aboveground water storage tank and installing a new below ground fiberglass water storage tank, replacing all the distribution piping and installing new hydrants. Work shall start approximately 10 days from the Notice to Proceed (NTP) and be completed 392 days from the

NTP.

2.0 Background

The Comanche Park Campground is a seasonal campground operating from approximately mid-May to mid-September annually. To access Comanche CG from downtown Custer, South Dakota, travel west on US Highway 16 for approximately 6.5 miles. Comanche Park Campground is on the left (south) side of the Highway. Comanche CG currently has 20 camping spurs inside the Campground gate and 2 sites outside the gate that are primitive and poorly defined.

There are currently five stick-built toilet buildings dating from 1965 at Comanche CG. These toilet buildings will be demolished. This is a Congressionally approved Great American Outdoors project that will include the design and reconstruction of Comanche Park Campground to accommodate modern recreational vehicle sites with modern design and amenities. Work will remove and replace leaking toilets and replace the water system and upgrade host sites.

Project may include new trails to connect Campground to nearby motorized trail system.

Contractor Requirements

3.0 Technical Requirements / Tasks

Contractors should demonstrate a thorough understanding of the project requirements and attention to detail is crucial for quality construction. Strong communication skills are essential for coordinating with clients, subcontractors and other stakeholders. Experience in campground construction, general contracting, and road construction is beneficial.

Contractors should have the capacity to handle the specific project requirements and deliver within the specified timeline.

A full copy of the Contract Specifications can be found with this solicitation.

A full copy of the Contract Construction Plans can be found with this solicitation.

4.0 Government Furnished

There are no Government Furnished Materials associated with this project.

5.0 Deliverables / Schedule

Key Deliverables Item No.

Deliverable / Item Title Description Frequency Reference

Delivery Format Due By

Accident Prevention Plan

Design the plan to address Federal, State, and Local Occupational Safety and Health requirements that apply to this project

Once Specifications General Requirements 2.2.A

Via email to

COR

10 days prior to on-site work beginning

Action Submittals

Written and graphic information that requires Contracting Officer’s(CO's) responsive action.

Prepare and submit Action Submittals required by individual Specification Sections.

Specifications General Requirements 3.4

Submit four copies of each submittal, unless otherwise indicated.

Before beginning work on individual item

Informational Submittals

Prepare and submit Informational Submittals required by other Specification Sections.

Prepare and submit Action Submittals required by individual Specification Sections.

Specifications General Requirements 3.5.A

Submit two copies of each submittal, unless otherwise indicated.

Before beginning work on individual item

Contractor's Construction Schedule

Provide a construction schedule that incorporates the full contract period.

Once Specifications General Requirements 3.5.B

Via email to

COR

10 days prior to on-site work beginning.

Monthly interval

Upcoming Work Summary

Prepare summary report indicating activities scheduled to occur or commence prior to submittal of next schedule update.

Monthly Specifications General Requirements 3.5.C

Via email to

COR

10 days prior to on-site work beginning.

Monthly interval

Construction Schedule Updating Report

At monthly intervals, update schedule to reflect actual construction progress and activities.

Submit with Applications for Payment

Specifications General Requirements 3.5.D

Via email to

COR

Monthly

Daily Construction Reports

Prepare a daily construction report recording information concerning events at Project site

Monthly Specifications General Requirements 3.5.E

Via email to

COR

Monthly

Item No.

Deliverable / Item Title Description Frequency Reference

Delivery Format Due By

Site Condition Reports

Report of differing site conditions

Submit at time of discovery of differing conditions.

Specifications General Requirements 3.5.F

Via email to

COR

Before continuation of work on individual item

Cost Breakdown Provide a cost breakdown schedule listing main types of work

Following Award Specifications General Requirements 3.5.G

Via email to

COR

Following Award

Project Record Documents

Record Drawings;

Record Specifications;

Record Product Data

Project Closeout Specifications General Requirements 5.5, 5.6, 5.7

Digital file Via email to COR

Project Closeout

Operation and Maintenance Manual furnish two complete sets of operation and maintenance (O&M) data

Before scheduling a final inspection

Specifications General Requirements 5.8

Digital file Via email to COR

Within 30 days following receipt of review comments

Testing Agency Qualifications proof of qualifications in the form of a recent report on the inspection of the testing agency by a recognized authority.

Once Specifications Quality Requirements 1.4.A

Digital file Via email to COR

Before beginning work on individual item

Permits, Licenses, and Certificates submit copies of permits, licenses, certifications, inspection reports, releases, jurisdictional settlements, notices, receipts for fee payments, judgments, correspondence, records, and similar documents established for compliance with standards and regulations bearing on performance of the Work.

Once Specifications Quality Requirements 1.4.B

Digital file Via email to COR

Before beginning work on individual item

Test and Inspection Reports

Prepare and submit certified written reports specified in other Sections

Prepare and submit test and inspection reports as required by individual Specification Sections.

Specifications Quality Requirements 1.5.A

Digital file Via email to COR

Submit test and inspection reports as required by individual Specification Sections.

Item No.

Deliverable / Item Title

Description Frequency Reference Delivery Format

Due By

Manufacturer's Technical Representative's Field Reports

Prepare written information documenting manufacturer's technical representative's tests and inspections specified in other Sections

Prepare written information documenting manufacturer's technical representative's tests and inspections specified in other Sections

Specifications Quality Requirements 1.5.B

Digital file Via email to COR

Prepare written information documenting manufacturer's technical representative's tests and inspections specified in other Sections

Factory- Authorized Service Representative's Reports

Prepare written information documenting manufacturer's factory-authorized service representative's tests and inspections specified in other Sections.

Prepare written information documenting manufacturer's factory-authorized service representative's tests and inspections specified in other Sections.

Specifications Quality Requirements 1.5.C

Digital file Via email to COR

Prepare written information documenting manufacturer's factory-authorized service representative's tests and inspections specified in other Sections.

Key Deliverables Item No.

Deliverable / Item Title Description Frequency Reference

Delivery Format Due By

Accident Prevention Plan

Design the plan to address Federal, State, and Local Occupational Safety and Health requirements that apply to this project

Once Specification s General Requirements 2.2.A

Via email to

COR

10 days prior to on-site work beginning

Action Submittals

Written and graphic information that requires Contracting Officer’s(CO's) responsive action.

Prepare and submit Action Submittals required by individual Specification Sections.

Specification s General Requirements 3.4

Submit four copies of each submittal, unless otherwise indicated.

Before beginning work on individual item

Informational Submittals

Prepare and submit Informational Submittals required by other Specification Sections.

Prepare and submit Action Submittals required by individual Specification Sections.

Specification s General Requirements 3.5.A

Submit two copies of each submittal, unless otherwise indicated.

Before beginning work on individual item

Contractor's Construction Schedule

Provide a construction schedule that incorporates the full contract period.

Once Specification s General Requirements 3.5.B

Via email to

COR

10 days prior to on-site work beginning.

Monthly interval

Upcoming Work Summary

Prepare summary report indicating activities scheduled to occur or commence prior to submittal of next schedule update.

Monthly Specification s General Requirements 3.5.C

Via email to

COR

10 days prior to on-site work beginning.

Monthly interval

Construction Schedule Updating Report

At monthly intervals, update schedule to reflect actual construction progress and activities.

Submit with Applications for Payment

Specification s General Requirements 3.5.D

Via email to

COR

Monthly

Daily Construction Reports

Prepare a daily construction report recording information concerning events at Project site

Monthly Specification s General Requirements 3.5.E

Via email to

COR

Monthly

Item No.

Deliverable / Item Title Description Frequency Reference

Delivery Format Due By

Site Condition Reports

Report of differing site conditions

Submit at time of discovery of differing conditions.

Specification s General Requirements 3.5.F

Via email to

COR

Before continuation of work on individual item

Cost Breakdown Provide a cost breakdown schedule listing main types of work

Following Award Specification s General Requirements 3.5.G

Via email to

COR

Following Award

Project Record Documents

Record Drawings; Record Specifications; Record Product Data

Project Closeout Specification s General Requirements 5.5, 5.6, 5.7

Digital file Via email to COR

Project Closeout

Operation and Maintenance Manual furnish two complete sets of operation and maintenance (O&M) data

Before scheduling a final inspection

Specification s General Requirements 5.8

Digital file Via email to COR

Within 30 days following receipt of review comments

Testing Agency Qualifications proof of qualifications in the form of a recent report on the inspection of the testing agency by a recognized authority.

Once Specification s Quality Requirements 1.4.A

Digital file Via email to COR

Before beginning work on individual item

Permits, Licenses, and Certificates submit copies of permits, licenses, certifications, inspection reports, releases, jurisdictional settlements, notices, receipts for fee payments, judgments, correspondence, records, and similar documents established for compliance with standards and regulations bearing on performance of the Work.

Once Specification s Quality Requirements 1.4.B

Digital file Via email to COR

Before beginning work on individual item

Test and Inspection Reports

Prepare and submit certified written reports specified in other Sections

Prepare and submit test and inspection reports as required by individual Specification Sections.

Specification s Quality Requirements 1.5.A

Digital file Via email to COR

Submit test and inspection reports as required by individual Specification Sections.

Item No.

Deliverable / Item Title

Description Frequency Reference Delivery Format

Due By

Manufacturer's Technical Representative's Field Reports

Prepare written information documenting manufacturer's technical representative's tests and inspections specified in other Sections

Prepare written information documenting manufacturer's technical representative's tests and inspections specified in other Sections

Specification s Quality Requirements 1.5.B

Digital file Via email to COR

Prepare written information documenting manufacturer's technical representative's tests and inspections specified in other Sections

Factory- Authorized Service Representative's Reports

Prepare written information documenting manufacturer's factory-authorized service representative's tests and inspections specified in other Sections.

Prepare written information documenting manufacturer's factory-authorized service representative's tests and inspections specified in other Sections.

Specification s Quality Requirements 1.5.C

Digital file Via email to COR

Prepare written information documenting manufacturer's factory-authorized service representative's tests and inspections specified in other Sections.

6.0 Travel

Travel is the responsibility of the contractor.

7.0 Contractor’s Key Personnel

The Contractor is to provide name, position title and contact information of company executive responsible for the project. Contractor is to provide an onsite superintendent at all times.

Water system installers must meet all State of South Dakota licensing requirements.

Electricians performing electrical installation must have a South Dakota Electrical License. State Electrical Inspection and approval is required on all electrical work.

8.0 Security Requirements

The Contractor is to install and maintain suitable barriers to ensure the protection of the public, employees, and facilities. Protect persons, motor vehicles, surrounding buildings, plants, and surrounding surfaces or buildings from harm resulting from Contractor’s work.

Site gate lockout procedures will be established if applicable.

9.0 Data Rights

Data will not be produced with this construction contract.

10.0 Section 508 – Electronic and Information Technology Standards Information technology will not be acquired with this construction contract.

Project
General Information
1.0 Scope of Work
2.0 Background
Contractor Requirements
3.0 Technical Requirements / Tasks
4.0 Government Furnished
5.0 Deliverables / Schedule
6.0 Travel
7.0 Contractor’s Key Personnel
8.0 Security Requirements
9.0 Data Rights
10.0 Section 508 – Electronic and Information Technology Standards