About this opportunity

This solicitation seeks roadway construction and pavement preservation services within Point Reyes National Seashore in Marin County, California. Work includes resurfacing, restoring, rehabilitating, and reconstructing approximately 12.9 miles of roadway, as well as pavement preservation of approximately 20.9 additional miles. Key requirements include 45,000 tons of asphalt paving, 40,000 cubic yards of excavation and embankment, replacement of two culverts with a 56-foot bridge, and various drainage, parking area, and roadside improvements. Proposals will be evaluated based on technical qualifications, past performance, and price. Important dates include a pre-bid site visit on November 5, 2019, with questions due by December 4, 2019 and proposals due by December 17, 2019.

The solicitation utilizes no set-asides. Relevant NAICS codes include 237110 (Water and Sewer Line and Related Structures Construction) and 237990 (Other Heavy and Civil Engineering Construction). The current contractor is Hat Creek Construction. The budget range is over $30 million. Work must be completed within Point Reyes National Seashore by October 2021. The soliciting agency is the Department of Transportation Federal Highway Administration.

Notice text

3 versions

Update #3 · Latest ·

CA FLAP CR109(1) & FTNP PORE 10(4), 200(1), & 201(1) Sir Francis Drake Boulevard & Limantour, Lighthouse, and Chimney Rock Roads & Pavement Preservation

PROJECT DETAILS:

This project will consist of roadway resurfacing, restoration, rehabilitation, and reconstruction of approximately 12.9 miles of roadway and pavement preservation of approximately 20.9 miles of roadway within Point Reyes National Seashore (PRNS) in Marin County, California.  Rehabilitation and reconstruction is included on 12.0 miles of Sir Francis Drake Boulevard (SFDB) from Pierce Point Road to Chimney Rock/Lighthouse Roads (including bridge construction at Schooner Creek), and on 0.9 miles of Chimney Rock Road.  Pavement preservation is included on 7.5 miles of Limantour Road, 1.5 mile of Lighthouse Road and 11.9 miles of various roadways and parking areas within PRNS.  Also included is construction of a 2-acre wetland restoration site at the existing Drakes Beach parking lot.  The estimated price range is over $30,000,000. 

Principle work items include 45,000 tons of superpave hot asphalt concrete pavement, 40,000 cubic yards of roadway excavation and embankment, 13,000 cubic yards of subexcavation, 25,000 tons of roadway aggregate, 145,000 square yards of pulverizing, 260,000 square yards of asphalt surface treatment (chipseal), and 30,000 square yards of micro-surfacing.  Additional work includes replacement of the two existing 84-inch culverts at the Schooner Creek crossing of SFDB with a 56-foot-long prestressed concrete voided slab bridge including 80 cubic yards of structural concrete and 350 linear feet of 30-inch drilled shafts.  Additional drainage improvements including culvert cleaning, lining and replacement, reconstruction and rehabilitation of multiple parking areas, 20,000 linear feet of asphalt curb, 5,000 square yards of asphalt paved ditch, and 4,500 linear feet of concrete curb and gutter.  All of the work is occurring in cultural and natural resource sensitive areas.  Great attention to detail will be required in achieving customer satisfaction in areas of road construction, traffic control and timely completion of work.

This is a full and open solcitiation.

Update #2 ·

CA FLAP CR109(1) & FTNP PORE 10(4), 200(1), & 201(1) Sir Francis Drake Boulevard & Limantour, Lighthouse, and Chimney Rock Roads & Pavement Preservation  

PROJECT DETAILS:

This project will consist of roadway resurfacing, restoration, rehabilitation, and reconstruction of approximately 12.9 miles of roadway and pavement preservation of approximately 20.9 miles of roadway within Point Reyes National Seashore (PRNS) in Marin County, California. Rehabilitation and reconstruction is included on 12.0 miles of Sir Francis Drake Boulevard (SFDB) from Pierce Point Road to Chimney Rock/Lighthouse Roads (including bridge construction at Schooner Creek), and on 0.9 miles of Chimney Rock Road. Pavement preservation is included on 7.5 miles of Limantour Road, 1.5 mile of Lighthouse Road and 11.9 miles of various roadways and parking areas within PRNS. Also included is construction of a 2-acre wetland restoration site at the existing Drakes Beach parking lot.   The anticipated advertisement date for the project is November 2019 and the anticipated completion date is October 2021.

Principle work items include 45,000 tons of superpave hot asphalt concrete pavement, 40,000 cubic yards of roadway excavation and embankment, 13,000 cubic yards of subexcavation, 25,000 tons of roadway aggregate, 145,000 square yards of pulverizing, 260,000 square yards of asphalt surface treatment (chipseal), and 30,000 square yards of micro-surfacing. Additional work includes replacement of the two existing 84-inch culverts at the Schooner Creek crossing of SFDB with a 56-foot-long prestressed concrete voided slab bridge including 80 cubic yards of structural concrete and 350 linear feet of 30-inch drilled shafts. Additional drainage improvements including culvert cleaning, lining and replacement, reconstruction and rehabilitation of multiple parking areas, 20,000 linear feet of asphalt curb, 5,000 square yards of asphalt paved ditch, and 4,500 linear feet of concrete curb and gutter. All of the work is occurring in cultural and natural resource sensitive areas. Great attention to detail will be required in achieving customer satisfaction in areas of road construction, traffic control and timely completion of work.

The estimated price is over $30,000,000.

This will be solicited as a full and open competition.

Update #1 ·

THIS IS NOT A REQUEST FOR BID - PLANS AND SPECIFICATIONS ARE NOT AVAILABLE.
CA FLAP CR109(1) & FTNP PORE 10(4), 200(1), & 201(1) Sir Francis Drake Boulevard & Limantour, Lighthouse, and Chimney Rock Roads & Pavement Preservation
 

PROJECT DETAILS:

This project will consist of roadway resurfacing, restoration, rehabilitation, and reconstruction of approximately 12.9 miles of roadway and pavement preservation of approximately 20.9 miles of roadway within Point Reyes National Seashore (PRNS) in Marin County, California. Rehabilitation and reconstruction is included on 12.0 miles of Sir Francis Drake Boulevard (SFDB) from Pierce Point Road to Chimney Rock/Lighthouse Roads (including bridge construction at Schooner Creek), and on 0.9 miles of Chimney Rock Road. Pavement preservation is included on 7.5 miles of Limantour Road, 1.5 mile of Lighthouse Road and 11.9 miles of various roadways and parking areas within PRNS. Also included is construction of a 2-acre wetland restoration site at the existing Drakes Beach parking lot.   The anticipated advertisement date for the project is November 2019 and the anticipated completion date is October 2021.

Principle work items include 45,000 tons of superpave hot asphalt concrete pavement, 40,000 cubic yards of roadway excavation and embankment, 13,000 cubic yards of subexcavation, 25,000 tons of roadway aggregate, 145,000 square yards of pulverizing, 260,000 square yards of asphalt surface treatment (chipseal), and 30,000 square yards of micro-surfacing. Additional work includes replacement of the two existing 84-inch culverts at the Schooner Creek crossing of SFDB with a 56-foot-long prestressed concrete voided slab bridge including 80 cubic yards of structural concrete and 350 linear feet of 30-inch drilled shafts. Additional drainage improvements including culvert cleaning, lining and replacement, reconstruction and rehabilitation of multiple parking areas, 20,000 linear feet of asphalt curb, 5,000 square yards of asphalt paved ditch, and 4,500 linear feet of concrete curb and gutter. All of the work is occurring in cultural and natural resource sensitive areas. Great attention to detail will be required in achieving customer satisfaction in areas of road construction, traffic control and timely completion of work.

The estimated price is over $30,000,000.

This will be solicited as a full and open competition.

Files

Show all 26

Notice history

Notice Type Posted
CA FLAP CR 109(1), Sir Francis Drake Blvd. and Point Reyes Roads Award Award Notice
This notice Latest solicitation Solicitation

Similar open opportunities

Opportunity Agency Set-aside Responses due
NPS Repair or Alteration of Highways, Roads, Streets, Trails and Bridges Multip NAICS 237310 — No set-aside
Northeast Region Pavement and Bridge Preservation Construction - NP NER PMS BMS FY24(1) New York, United States · NAICS 237310 Federal Highway Administration Total Small Business
BRCA 310427 Southbound Shuttle Stop NAICS 237310 National Office No set-aside
UT NP ARCH 100(2) Bridges on Delicate Arch Road Moab, Utah 84532, United States · NAICS 237310 Federal Highway Administration No set-aside
Acadia National Park Maine, United States · NAICS 237310 Federal Highway Administration Total Small Business

On GovTribe

Work this opportunity

  • Track it in your pipeline
  • Find teaming partners
  • Similar opportunities
  • Ask GovTribe AI about this opportunity

GovTribe for Federal Contractors