Site Visit QnA 11.5.2019.pdf

PDF 123 KB Posted

Attached to
CA FLAP CR 109(1), Sir Francis Drake Blvd. and Point Reyes Roads
Solicitation number
6982AF19B000023
Issued by

About this file

This document contains details of a federal contract opportunity for road construction and pavement preservation work within Point Reyes National Seashore in Marin County, California. The solicitation is for approximately 12.9 miles of roadway rehabilitation and reconstruction including work on Sir Francis Drake Boulevard and Chimney Rock Road, as well as pavement preservation on approximately 20.9 miles of additional roadways. Key work items include 45,000 tons of asphalt concrete pavement, 40,000 cubic yards of roadway excavation and embankment, replacement of two 84-inch culverts on Sir Francis Drake Boulevard with a 56-foot prestressed concrete bridge, and drainage, parking area, and roadway improvements. The estimated price for the contract is over $30 million. The advertisement date for the project is November 2019 with an anticipated completion date of October 2021. The soliciting agency is the Department of Transportation Federal Highway Administration.

View the file

Other files

Show all 25

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Questions and Answers during Pre-Bid Site Visit for

CA FLAP CR109(1), SIR FRANCIS DRAKE BLVD.

November 5, 2019

Questions Answers

1 What is the overall Engineer’s Estimate? The EE will not be disclosed until bid opening. The overall value is estimated to be over $30M.

2 Are hard copy bids required?

Original hard copy bids, to include bid bonds, are required. However, contractors may email or fax amended bid schedules up until the due date specified in the solicitation. See pages A-iii and A-iv.

3 Are there designated lay down areas?

See subsection 105.04 (page E-10) for staging and stockpile locations.

Staging areas are also available adjacent to the Home Ranch Ponds as shown on Option Z plan sheets A4, D7, and D8.

4 The frog ponds at home ranch: is there any public road or is it a walking trail only?

There is a 2 track ranch road that provides accesses near the sites as shown on Option Z plan sheet A4. See Option Z plan sheets D7, D8, E2, and E3 for access routes from the ranch road to the pond sites. There should be no restrictions on equipment size to access the pond sites.

5 Are the ponds wet or dry?

The work includes construction of 2 new ponds (no existing ponds) as shown on Option Z plan sheets D7-D10.

6 What are the expectations of the full time biologist monitor?

See Subsections 107.10(f) and 108.01 for biological monitoring requirements.

7 Work restrictions: The 51 consecutive day requirement – is that calculated using calendar days or work days (5 or 7)?

Chimney Rock Road and Parking Lot may be closed to public traffic for 51 consecutive calendar days. Daily access will need to be provided for the

PORE employee occupant of the residence located at the end of the

Chimney Rock road, and weekend access will need to be provided for authorized PORE staff. An amendment will be issued to clarify Subsection

156.06(k) requirements.

8 Is the Biological Opinion available for review? Yes, the Biological Opinion will be uploaded to Beta.SAM.gov.

9 Are asbestos surveys required for things to be removed? How will that be paid for?

As per Subsection 203.04 asbestos testing is required for the existing bridges (cattle under-crossings) at Stations 378+89 and 390+36, to be removed.

10 Can the limited operating period for spotted owls being explained?

As per Subsection 108.01 (page E-31) no construction work is allowed from February 1 to August 1 (Northern Spotted Owl nesting season) on

Limantour Road between Station 10+00 and 187+68, and on Mt. Vision

Road. An amendment will be issued clarifying requirements for getting approval for Schedule A tree removal and clearing and grubbing work outside the allowable time period of August 31 to October 15 (108.01, page

E-30).

11 Is water for construction available on site? Yes, see Subsection 105.02.

General comments from the Site Visit Meeting:

1) Part of the route (approximately 1/2 mile) was closed to the public due to an existing lighthouse construction project. The remainder of the project is open for the public to view.

2) The project was originally bid back around April 2019. There were minor changes in the SCR’s and contract documents but the scope is identical. The budget has been adjusted based on recent market trends in California.