CA ERFO FS LSPDR 2021-1(1) Nacimiento-Fergusson Road
Closed Solicitation Posted
This opportunity was awarded. See the award notice from .
- Solicitation number
- 6982AF23B000014
- Agency
-
Federal Highway Administration
Department of Transportation
- Responses due
- Set-aside
- Total Small Business
Opportunity facts
- NAICS code
- 237310 Highway, Street, and Bridge Construction
- Place of performance
- King City, California 93930, United States
Notice details come from SAM.gov. Updated .
About this opportunity
This solicitation seeks construction services for repairs to 13 damaged sites along 11 miles of the Nacimiento Fergusson Road within the Los Padres National Forest in Monterey County, California. The Department of Transportation Federal Highway Administration seeks to repair embankments, replace culverts from 24 to 72 inches in diameter, remove debris, grade the roadway, and repave the existing 16 to 24 foot wide pavement. Bids are due by May 18, 2023 with construction to be completed between May 2023 and December 2023. The contract will be awarded based on lowest price technically acceptable with consideration given to past performance and experience with similar projects.
This is a total small business set-aside solicitation. The primary NAICS code is 237110 with a secondary PSC code of D304. The engineer's estimate was $7,081,000 while the lowest bid of $4,939,384 was submitted by Herback General Engineering. Approximate quantities include 2,500 cubic yards of excavation, 2,200 square feet of retaining walls, and 650 tons of asphalt pavement. Place of performance will be along the 11 mile stretch of the Nacimiento Fergusson Road located approximately 33 miles southwest of King City, California within the Los Padres National Forest.
Notice text
THIS IS A REQUEST FOR BIDS. PLANS AND SPECIFICATION ARE AVAILABLE AT THIS TIME.
The project is located approximately 33 miles southwest of King City, CA on Forest Service Route 22S01 (Nacimiento Fergusson Road) within the Los Padres National Forest in Monterey, CA.
The project consists of repairing 13 sites, encompassing 11 miles along the route. Site repairs generally include embankment construction, retaining walls, and culvert replacements.
SCOPE OF THE WORK:
The purpose of the project is to repair 13 damaged sites along the Nacimiento Fergusson Road within the Los Padres National Forrest. 7 mechanically stabilized earth (MSE) walls and 8 drainage culverts are proposed as part of the repair design. Culverts range in size from 24-inch to 72-inch in diameter. Headwalls and wingwalls are proposed on the 72-inch culverts. Furthermore, as a result of the flood event, debris removal and grading are anticipated. Nacimiento Fergusson Road is currently paved and is proposed to be repaved with the existing pavement structural section within the repair sites.
Items worth noting:
*The terrain is mountainous with steep slopes.
*The roadway widths vary from 16-ft to 24-ft.
*The road is currently closed to the public. However, residents along the route do have access.
*The roadway serves as the primary route between King City and the Pacific Coast.
*Access for the residents will be maintained during construction.
*Shoring is anticipated for MSE wall excavations and to allow access.
PRINCIPAL WORK ITEMS:
Approximate quantities for major work items:
- 1 (LPSM) of Removal of Existing Structures and Obstructions
- 2,500 CUYD of Excavation/Embankment Construction
- 2,200 SQFT of Mechanically Stabilized Earth wall
- 220 CUYD of Riprap
- 700 TON of Roadway Aggregate
- 650 TON of Asphalt Pavement
- 3 EACH of Concrete Headwall
- 150 LNFT of 24-inch Culvert
- 80 LNFT of 36-inch Culvert
- 150 LNFT of 78-inch Culvert
- 110 LNFT of 72-inch Culvert
- 9 EACH End Section for Culverts
- 120 hours of Equipment Hours
- 1 (LPSM) Traffic Control
ANTICIPATED SCHEDULE:
Award: May 2023
Construction: May 2023 – December 2023
ESTIMATED COST RANGE:
The anticipated cost range is between $10,000,000 and $20,000,000.
Files
Show all 11
Notice history
| Notice | Type | Posted |
|---|---|---|
| CA ERFO FS LSPDR 2021-1(1), Nacimiento-Fergusson Road | Award Notice | |
| This notice | Solicitation | |
| CA ERFO FS LSPDR 2021-1(1) Nacimiento-Fergusson Road | Pre-Solicitation | |
| CA ERFO FS LSPDR 2021-1(1) Nacimiento-Fergusson Road | Pre-Solicitation |
Similar open opportunities
| Opportunity | Agency | Set-aside | Responses due |
|---|---|---|---|
| Custer Gallatin National Forest Ashland and Sioux Road Maintenance | Region 6 - Pacific Northwest Region | Total Small Business | |
| WA ERFO NPS OLYM 2022-1(3), OLYMPIC NPS ERFO REPAIRS 2022 Road 107 MP 0.3 TO 0.5 & MP 0.8 | Federal Highway Administration | No set-aside | |
| AZ BL COLO 7528(1) Burro Creek Road | Federal Highway Administration | Total Small Business | |
| GAOA Facilities, Barracks Inyo NF | Forest Service | Total Small Business | |
| Jake Rocks Road Reconstruction | Forest Service | Total Small Business |
On GovTribe
Work this opportunity
- Track it in your pipeline
- Find teaming partners
- Similar opportunities
- Ask GovTribe AI about this opportunity