About this opportunity
The U.S. Department of Energy's Fermi National Accelerator Laboratory is seeking bids for a renovation project at the C0 Service Building. The scope of work includes removing and replacing the main entrance/exit double doors, two south side single doors, and 11 end-of-life windows, as well as re-epoxying approximately 500 square feet of concrete flooring, removing and replacing the restroom commode, sink, and mirror, and patching and painting walls in the hallway and two rooms. The contract will be awarded on a Lowest Price Technically Acceptable basis, and key qualifications include at least 5 years of carpentry, painting, and epoxying experience. The proposal is due by 5:00 PM CT on October 30, 2024.
This is a small business set-aside procurement with a NAICS code of 238350, Finish Carpentry Contractors. The place of performance is Batavia, Illinois. The estimated period of performance is from September 23, 2024 to August 29, 2025. The government has not provided a cost estimate or budget range for this project, and there is no information on potential incumbent contractors.
Notice text
3 versions
Update #3 · Latest ·
On October 22, 2024, Amendment 02 was issued.
This Amendment to the RFP is being issued to provide responses to questions from prospective offerors. Please see the attached Q&A document and epoxy flooring picture attachment.
On October 3, 2024, Amendment 01 was issued.
This Amendment to the RFP is being issued to include the following exhibits/documents on SAM.gov:
a. Exhibit J - Proposal Certifications, Form PUR-466, Rev. 1 (10/14/2021).
b. Exhibit K - Subcontractor Annual Representations & Certifications (SARC), Form SARC (Rev. 3) (04/08/2022).
c. Exhibit L - Construction Environmental, Safety & Health Certification (CESHC).
d. Business Visitor Registration Instructions & Directions
The Scope of Work for this project includes:
- Remove and replace main entrance/exit double doors with frame and all components. (Prime and Paint as well). Doors to be ENERGY STAR certified with a thermal break.
- Remove and replace (2) south side single doors with frame and all components. (Prime and Paint also). Doors to be ENERGY STAR certified with a thermal break.
- Remove and replace (11) EOL windows. Windows to be a minimum double-pane ENERGY STAR certified with a low-e coating.
- Re-Epoxy roughly 500 Sq Ft of concrete flooring.
- Remove and replace EOL commode, sink and mirror in restroom.
- Install a large new sink. (sink onsite already at C0)
- Patch and Paint Walls in the hallway and 2 rooms that were re done.
For more detailed information, please review the attached SOW titled, "Exhibit A SOW C0_Renovation."
Update #2 ·
On October 3, 2024, Amendment 01 was issued.
This Amendment to the RFP is being issued to include the following exhibits/documents on SAM.gov:
a. Exhibit J - Proposal Certifications, Form PUR-466, Rev. 1 (10/14/2021).
b. Exhibit K - Subcontractor Annual Representations & Certifications (SARC), Form SARC (Rev. 3) (04/08/2022).
c. Exhibit L - Construction Environmental, Safety & Health Certification (CESHC).
d. Business Visitor Registration Instructions & Directions
The Scope of Work for this project includes:
- Remove and replace main entrance/exit double doors with frame and all components. (Prime and Paint as well). Doors to be ENERGY STAR certified with a thermal break.
- Remove and replace (2) south side single doors with frame and all components. (Prime and Paint also). Doors to be ENERGY STAR certified with a thermal break.
- Remove and replace (11) EOL windows. Windows to be a minimum double-pane ENERGY STAR certified with a low-e coating.
- Re-Epoxy roughly 500 Sq Ft of concrete flooring.
- Remove and replace EOL commode, sink and mirror in restroom.
- Install a large new sink. (sink onsite already at C0)
- Patch and Paint Walls in the hallway and 2 rooms that were re done.
For more detailed information, please review the attached SOW titled, "Exhibit A SOW C0_Renovation."
Update #1 ·
The Scope of Work for this project includes:
- Remove and replace main entrance/exit double doors with frame and all components. (Prime and Paint as well). Doors to be ENERGY STAR certified with a thermal break.
- Remove and replace (2) south side single doors with frame and all components. (Prime and Paint also). Doors to be ENERGY STAR certified with a thermal break.
- Remove and replace (11) EOL windows. Windows to be a minimum double-pane ENERGY STAR certified with a low-e coating.
- Re-Epoxy roughly 500 Sq Ft of concrete flooring.
- Remove and replace EOL commode, sink and mirror in restroom.
- Install a large new sink. (sink onsite already at C0)
- Patch and Paint Walls in the hallway and 2 rooms that were re done.
For more detailed information, please review the attached SOW titled, "Exhibit A SOW C0_Renovation."
Files
Show all 24
Similar open opportunities
| Opportunity | Agency | Set-aside | Responses due |
|---|---|---|---|
| Central Utility Building Addition and Renovation Construction, UIP Subproject 1-CUB | Fermi National Accelerator Laboratory | No set-aside | |
| PIP-II f-37 building LWC pump room piping system installation | Fermi National Accelerator Laboratory | No set-aside | |
| RFP 7-B164-p-00002-00 (RR GC BPA FY27) | Office of Science | No set-aside | |
| Building 262 Renovation, FLETC Glynco, Georgia | Federal Law Enforcement Training Center | Total Small Business |
On GovTribe
Work this opportunity
- Track it in your pipeline
- Find teaming partners
- Similar opportunities
- Ask GovTribe AI about this opportunity