This document is a Statement of Work (SOW) for a renovation project at the C0 Service Building on the Fermi National Accelerator Laboratory (Fermilab) campus. The project scope includes replacing the main entrance/exit double doors, two south side single doors, and eleven end-of-life (EOL) windows. The work also involves re-epoxying 500 square feet of concrete flooring, removing and replacing the restroom commode, sink, and mirror, and installing a new sink. Additionally, the walls in the hallway and two rooms will be patched and painted.
The estimated period of performance is from September 23, 2024 to August 29, 2025. The government will provide a large sink as government-furnished property. The SOW is associated with Solicitation Number ISD_362164_DA for the "C0 Service Building Renovation" project, issued by the Department of Energy's Fermi National Accelerator Laboratory.
View the file
Other files
Show all 23
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
SOW TEMPLATE 04.24.2023
SOW DATE: 8/19/2024
PROJECT TITLE: R164390 – C0 Minor Building Renovation FRA POINT OF CONTACT: Blake Hanauer – (43011N) COUNTY THAT WORK WILL BE COMPLETED IN: DuPage☒ Kane☐ Fermilab County Line
INTRODUCTION:
C0 has a new tenant moving in and some renovations will be needed to get the building in decent condition for the new tenants.
SCOPE OF WORK
1. Remove and replace main entrance/exit double doors with frame and all components. (Prime and
Paint as well). Doors to be ENERGY STAR certified with a thermal break.
2. Remove and replace (2) south side single doors with frame and all components. (Prime and Paint also). Doors to be ENERGY STAR certified with a thermal break.
3. Remove and replace (11) EOL windows. Windows to be a minimum double-pane ENERGY STAR certified with a low-e coating.
4. Re-Epoxy roughly 500 Sq Ft of concrete flooring.
5. Remove and replace EOL commode, sink and mirror in restroom.
6. Install a large new sink. (sink onsite already at C0)
7. Patch and Paint Walls in the hallway and 2 rooms that were re done.
GOVERNMENT FURNISHED PROPERTY
Large Sink
PLACE OF PERFORMANCE
C0 Service Building on Main Ring Road
ESTIMATED SCHEDULE/PERIOD OF PERFORMANCE
EST START DATE: 9/23/2024 EST END DATE: 8/29/2025
Statement of Work Infrastructure Services Division https://fermipoint.fnal.gov/org/os/FESS/web_docs/Shared%20Documents/Fermilab%20-%20with%20County%20Lines-compressed.pdf
File details come from the government source that posted it. Updated .