Access Control System

Closed Solicitation Posted

Solicitation number
FA527024QB007
Agency
Responses due
Set-aside
No set-aside

Opportunity facts

Place of performance
Yomitan Japan

Notice details come from SAM.gov. Updated .

About this opportunity

The U.S. Department of the Air Force Pacific Air Forces is seeking quotes for the installation of a new access control system (ACS) and upgrade of the current ACS software, database conversion, site control units, and infrastructure at a facility in Okinawa, Japan. The contractor must provide all necessary personnel, equipment, supplies, and services to meet the technical and performance requirements outlined in the Statement of Work. Quotes will be evaluated on a lowest price technically acceptable basis, and the contract will be awarded as a firm-fixed-price contract. Quotes are due by June 19, 2024, and a mandatory site visit is scheduled for May 31, 2024.

This opportunity is not set aside for any particular business type. The current system is proprietary technology of DAQ Electronics, LLC, but the new equipment and system must seamlessly integrate with the existing DAQ hardware and software. The contractor will be responsible for replacing existing ACS panels, installing a new ACS server, and replacing an existing workstation. The period of performance for the installation, integration, and training is 30 days, although this has been extended to 6 months to allow for a reasonable delivery schedule.

Notice text

7 versions

Update #7 · Latest ·

The mission partner requires all personnel, equipment, supplies, facilities, transportation, tools, materials, supervision, and other items and non-personal services necessary to perform the installation of a new access control system (ACS) and upgrade of the current ACS software, database conversion, site control units, and infrastructure, as defined in the Statement of Work (SOW).

AMENDMENT 0001: 

As of 21 May 24 (JST), the RFQ has been amended to add a term to Section E, Inspection and acceptance.

AMENDMENT 0002: 

As of 21 May 24 (JST), the RFQ has been amended to update the POC’s for the site visit in Section L, Instructions, conditions, and notices to offerors or respondents.

Q&A Response Form

As of 30 May 24 (JST), the Government's reponses have been made avaible regarding questions submitted 30 May 24. 

Q&A Response Form

As of 7 Jun 24 (JST), the Government's reponses have been made avaible regarding questions submitted 30 May 24 - 4 Jun 24. 

AMENDMENT 0003: 

As of 7 May 24 (JST), the RFQ has been amended to update the quote submission due date from 10 Jun 24, 0900 (JST) to 17 Jun 24, 0730 (JST). 

AMENDMENT 0004:

As of 15 Jun 25 (JST), the RFQ has been amended to update the quote submission due date from 17Jun 24, 0730(JST) to 20 Jun 24, 0830 (JST) to accomodate the provision of responses to questions subnmitted by the question submission due date.

The question submission date has passed. Questions after the due date may not receive a response if the contracting officer determines response time will further delay the acquisiton process. 

Vendors please ensure to recieve a reciept confirmation from the contract adminstrator or officer when submitting quotes. 

AMENDMENT 0005:

As of 18 Jun 25 (JST), the RFQ has been amended to update the quote submission due date from  21 Jun 24, 0830 (JST) to accomodate for updates to quotes from the questions answered on 18 Jun 24 (JST). No further questions will be accepted. 

Update #6 ·

The mission partner requires all personnel, equipment, supplies, facilities, transportation, tools, materials, supervision, and other items and non-personal services necessary to perform the installation of a new access control system (ACS) and upgrade of the current ACS software, database conversion, site control units, and infrastructure, as defined in the Statement of Work (SOW).

AMENDMENT 0001: 

As of 21 May 24 (JST), the RFQ has been amended to add a term to Section E, Inspection and acceptance.

AMENDMENT 0002: 

As of 21 May 24 (JST), the RFQ has been amended to update the POC’s for the site visit in Section L, Instructions, conditions, and notices to offerors or respondents.

Q&A Response Form

As of 30 May 24 (JST), the Government's reponses have been made avaible regarding questions submitted 30 May 24. 

Q&A Response Form

As of 7 Jun 24 (JST), the Government's reponses have been made avaible regarding questions submitted 30 May 24 - 4 Jun 24. 

AMENDMENT 0003: 

As of 7 May 24 (JST), the RFQ has been amended to update the quote submission due date from 10 Jun 24, 0900 (JST) to 17 Jun 24, 0730 (JST). 

AMENDMENT 0004:

As of 15 Jun 25 (JST), the RFQ has been amended to update the quote submission due date from 17Jun 24, 0730(JST) to 20 Jun 24, 0830 (JST) to accomodate the provision of responses to questions subnmitted by the question submission due date.

The question submission date has passed. Questions after the due date may not receive a response if the contracting officer determines response time will further delay the acquisiton process. 

Vendors please ensure to recieve a reciept confirmation from the contract adminstrator or officer when submitting quotes. 

Update #5 ·

The mission partner requires all personnel, equipment, supplies, facilities, transportation, tools, materials, supervision, and other items and non-personal services necessary to perform the installation of a new access control system (ACS) and upgrade of the current ACS software, database conversion, site control units, and infrastructure, as defined in the Statement of Work (SOW).

AMENDMENT 0001: 

As of 21 May 24 (JST), the RFQ has been amended to add a term to Section E, Inspection and acceptance.

AMENDMENT 0002: 

As of 21 May 24 (JST), the RFQ has been amended to update the POC’s for the site visit in Section L, Instructions, conditions, and notices to offerors or respondents.

Q&A Response Form

As of 30 May 24 (JST), the Government;s reponses have been made avaible regarding questions submitted 30 May 24. 

Q&A Response Form

As of 7 Jun 24 (JST), the Government;s reponses have been made avaible regarding questions submitted 30 May 24 - 4 Jun 24. 

AMENDMENT 0003: 

As of 7 May 24 (JST), the RFQ has been amended to update the quote submission due date from 10 Jun 24, 0900 (JST) to 17 Jun 24, 0730 (JST). 

Update #4 ·

The mission partner requires all personnel, equipment, supplies, facilities, transportation, tools, materials, supervision, and other items and non-personal services necessary to perform the installation of a new access control system (ACS) and upgrade of the current ACS software, database conversion, site control units, and infrastructure, as defined in the Statement of Work (SOW).

AMENDMENT 0001: 

As of 21 May 24 (JST), the RFQ has been amended to add a term to Section E, Inspection and acceptance.

AMENDMENT 0002: 

As of 21 May 24 (JST), the RFQ has been amended to update the POC’s for the site visit in Section L, Instructions, conditions, and notices to offerors or respondents.

Q&A Response Form

As of 30 May 24 (JST), the Government;s reponses have been made avaible regarding questions submitted 30 May 24. 

Update #3 ·

The mission partner requires all personnel, equipment, supplies, facilities, transportation, tools, materials, supervision, and other items and non-personal services necessary to perform the installation of a new access control system (ACS) and upgrade of the current ACS software, database conversion, site control units, and infrastructure, as defined in the Statement of Work (SOW).

AMENDMENT 0001: 

As of 21 May 24 (JST), the RFQ has been amended to add a term to Section E, Inspection and acceptance.

AMENDMENT 0002: 

As of 21 May 24 (JST), the RFQ has been amended to update the POC’s for the site visit in Section L, Instructions, conditions, and notices to offerors or respondents.

Update #2 ·

The mission partner requires all personnel, equipment, supplies, facilities, transportation, tools, materials, supervision, and other items and non-personal services necessary to perform the installation of a new access control system (ACS) and upgrade of the current ACS software, database conversion, site control units, and infrastructure, as defined in the Statement of Work (SOW).

AMENDMENT 0001: 

As of 21 May 24 (JST), this document has been amended to add a term to Section E, Inspection and acceptance.

Update #1 ·

The mission partner requires all personnel, equipment, supplies, facilities, transportation, tools, materials, supervision, and other items and non-personal services necessary to perform the installation of a new access control system (ACS) and upgrade of the current ACS software, database conversion, site control units, and infrastructure, as defined in the Statement of Work (SOW).

Files

File Type Posted
Question Response Form 11 Jun 24.pdf PDF
RFQ 0005.pdf PDF
RFQ 0004.pdf PDF
Question Response Form 3 Jun 24.pdf PDF
Question Response Form 4 Jun 24.pdf PDF
RFQ 0003.pdf PDF
Question Response Form (2).pdf PDF
Question Reponse Form.pdf PDF
RFQ 0002.pdf PDF
RFQ.pdf PDF
Question Submission Form.docx DOCX document
SOW (17 May 24).pdf PDF
Show all 12

On GovTribe

Work this opportunity

  • Track it in your pipeline
  • Find teaming partners
  • Similar opportunities
  • Ask GovTribe AI about this opportunity

GovTribe for Federal Contractors