Question Response Form 11 Jun 24.pdf

PDF 81 KB Posted

Attached to
Access Control System
Solicitation number
FA527024QB007
Issued by

About this file

This document is a Memorandum for RFQ Interested Parties that provides responses to vendor questions regarding Solicitation FA527024QB007 for an Access Control System.

The key details are:

  • The solicitation is for the installation of a new access control system (ACS) and upgrade of the current ACS software, database conversion, site control units, and infrastructure.
  • The government confirmed that the existing communications wiring is expected to be reused unless deficiencies or compatibility issues are found.
  • The server for the new ACS will be located in Building 180, Room 115, and the workstation in Building 103, Room 104.
  • There are 39 existing Entrostar panels that will connect to the new server, along with 12 cameras and 66 card readers.
  • The new ACS will support only the buildings within the 1 SFG compound, not the entire base.

View the file

Other files

File Type Posted
RFQ 0005.pdf PDF
RFQ 0004.pdf PDF
Question Response Form 3 Jun 24.pdf PDF
Question Response Form 4 Jun 24.pdf PDF
RFQ 0003.pdf PDF
Question Response Form (2).pdf PDF
Question Reponse Form.pdf PDF
RFQ 0002.pdf PDF
RFQ.pdf PDF
Question Submission Form.docx DOCX document
SOW (17 May 24).pdf PDF
Show all 11

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

18 Jun 24

MEMORANDUM FOR RFQ INTERESTED PARTIES

FROM 18 CONS/PKB

SUBJECT: Receipt of Question(s) from Vendor Regarding RFQ FA527024QB007, Access Control System

The following are inquiries were submitted by a vendor on 11 Jun 24, for the subject requirement. The Government’s responses are recorded in blue:

1. Please confirm if the comms wiring to be replaced is:

i. OSP connection between each building?

ii. System communication line between workstation and Entrostar?

iii. Device communication line between Entrostar and devices?

iv. Or all of the above.

The current assumption is that all existing lines are within specification and standard. There are no existing plans to replace unless deficiencies or lack of compatibility with upgrades are found.

2. Please confirm where is the server for B180? and workstation to be located B103?

The server for B180 is in Rm. 115; the workstation for B103 will be in Rm. 104.

3. How many existing SCIF/RMS , RADC’s and other Entrostars will connect to the new server.

39 existing Entrostars.

4. Please list current equipment/system devices to be attached to the new server.

12 x Cameras

39 x Entrostar panels

66 x Card Readers

See SOW for full details.

5. Please confirm, if this server is for the whole base IDS/ACS or just buildings listed in PWS Bldg. 103 1F, Bldg. 140 1F, Bldg. 140 2F, Bldg141 2F, Bldg. 143 1F, Bldg. 146 2F,Bldg. 140 1F, Bldg. 140 2F.

Only the buildings within the 1 SFG compound.

//SIGNED//

18 CONS/PKB