Addendum No. 4 for the Aircraft Parking Apron Expansion project is issued by the Umatilla Municipal Airport and AVCON, INC. as the Procurement Agent, dated April 11, 2025. The addendum addresses several key clarifications and modifications to the original solicitation, including project measurement and payment terms, construction material testing responsibilities, and specifications for Recycled Asphalt Pavement (RAP) usage. The document provides detailed responses to contractor questions about project quantities, material testing requirements, stockpile removal, work area limits, and as-built documentation requirements.
The addendum specifies that the bidder is responsible for construction material testing across multiple technical specification items, with a maximum of 20% RAP allowed in the P403 mix. Payment will be based on actual quantities of units incorporated into the work, as determined by the Engineer. The spoil area north of the berm will be cleared and grubbed, with spoiled material to be placed in compacted lifts. Work Area C has been removed from the project scope, and the contractor will be required to provide as-built documentation for various project elements including pavement edges, fenceline, tie-down anchors, and electrical infrastructure. Performance and payment bonds will cover the full contract amount.
View the file
Other files
Show all 16
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Umatilla Municipal Airport Page 1 of 2 ADDENDUM NO. 4 Aircraft Parking Apron Expansion Project No. 2023.352.02
Solicitation Addendum
Addendum No.: 4
Solicitation Title: Aircraft Parking Apron Expansion
Addendum Date: April 11, 2025
Procurement Agent: AVCON, INC.
THE FOLLOWING ITEMS ARE MADE AND HEREBY BECOME A PART OF THIS SOLICITATION AS PREPARED
BY PROCUREMENT:
Questions
1. Will all quantities on the project be field measured for payment? Will any of the quantities on the bid form be paid as a lump sum (example: Unclassified Excavation)?
a. When unit bid price items are included in the Contract Price, the quantities of various units contained in the Proposal are estimated and payment to the Contractor will be made only for the actual quantities of units that are incorporated in the Work or materials furnished in accordance with the plans and specifications, as determined by the Engineer in accordance with General Provisions Section 90, “Measurement and Payment”.
2. Which party is responsible for testing?
a. Bidder is responsible for construction material testing as detailed in the technical specifications.
Bidder’s responsibilities shall include, but not be limited to Items P-152, P-211, P-403, and electrical grounding and megger testing.
3. In Addendum 3, question/answer #22 allows RAP in the P403 mix. What is the maximum percentage of RAP allowed in the P403 mix?
a. 20%
4. The topo sheets provided in Addendum 3 do not show the existing stockpile in its entirety. Question/answer #6 state the contractor will be able to survey the site to confirm quantities. Question/answer #3 states we are to remove the existing stockpile in its entirety and will be spoiled on site. Does the existing stockpile extend beyond the clearing and grubbing limits shown on sheet C001?
a. No.
Umatilla Municipal Airport Page 2 of 2 ADDENDUM NO. 4 Aircraft Parking Apron Expansion Project No. 2023.352.02
5. If the excess soils are to be spoiled on site, on the north side of the berm, will the spoiled area be considered a stockpile or embankment? Will the area need to be stripped of any vegetation and/or sod before beginning spoiling operations? Will the spoiled material need to be compacted and tested per lift?
a. The area north of the berm is already being cleared, grubbed, and root raked. Spoiled material will be placed in lifts and compacted. Density testing in spoil area beyond the currently planned grading limits will not be required.
6. Sheet G003 does not show the Work Area C limits. Please issue a plan that shows the Work Area C limits.
a. Work Area C is no longer included in this project. Work Area C encompassed the portion of the project that previously included the Beacon replacement, which was removed and bid separately from this Contract. Work Area C references will be removed from the plans for the Conformed Construction Plans.
7. Sheet G002, General Note 13 calls for as-built plans. What items will need to be as-built?
a. Edges of Pavement, Fenceline, Tie Down Anchors, Paint Markings, Grading Features (break lines, top of bank, bottom of bank, pond bottom, swale centerlines, etc.), Apron Lighting Locations, and all new above ground electrical infrastructure.
8. Please provide the percentages required for payment and performance bonds.
a. Full Contract Amount.
Attachments None
End of Addendum
INSTRUCTIONS:
Respondent must acknowledge receipt of this Addendum as instructed in the solicitation document.
Failure to acknowledge receipt of this Addendum may result in the disqualification of Respondent’s response.