View the file

Other files

File Type Posted
Amendment 0010.pdf PDF
Amendment 0009.pdf PDF
Amendment 0008.pdf PDF
Amendment 0007_Plans - Revised.pdf PDF
Amendment 0007_Specification Appendices- Revised.pdf PDF
Amendment 0007_DMC Slug Tests - Revised.pdf PDF
Amendment 0007_Specs - Revised.pdf PDF
Amendment 0007.pdf PDF
Amendment 0006.pdf PDF
Amendment_0005_Sub_Cost_Detail_Template__Example_Only_.xlsx XLSX spreadsheet
Amendment_0005_Prime_Cost_Detail_Template__Example_Only_.xlsx XLSX spreadsheet
Amendment_0005_DMC_Slug_Tests.pdf PDF
Amendment_0005.pdf PDF
Amendment 0003_Fran Korn Consent Agreement for Excavation and remediation_Redacted.pdf PDF
Amendment 0003_215 Main St. - Access Requirements Oct 4 2022.pdf PDF
Amendment 0004.pdf PDF
Amendment 0003_215 Main St. - Access Requirements Oct 4 2022.pdf PDF
Amendment 0003_Fran Korn Consent Agreement for Excavation and remediation_Redacted.pdf PDF
Amendment_0002.pdf PDF
Amendment 0001.pdf PDF
Basis of Design.pdf PDF
Section 01 22 00 1_Sept 2022.pdf PDF
Past Performance Questionnaire.pdf PDF
W912WJ22R0014.pdf PDF
Specification Appendices.pdf PDF
Plans.pdf PDF
Specifications.pdf PDF
Joint Venture Requirements.pdf PDF
Show all 28

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

012345678910

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print)

30-105-04EXCEPTION TO SF 30

APPROVED BY OIRM 11-84

STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA

FAR (48 CFR) 53.243

This amendment is necessary to respond to RFIs. All other aspects remain unchanged.

1. CONTRACT ID CODE PAGE OF PAGES

1 12

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

16C. DATE SIGNED

BY 12-Oct-2022

16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR

(Signature of Contracting Officer)(Signature of person authorized to sign)

8. NAME AND ADDRESS OF CONTRACTOR (No., Street , County, State and Zip Code) X W912WJ22R0014

X 9B. DATED (SEE ITEM 11)

21-Sep-2022

10B. DATED (SEE ITEM 13)

9A. AMENDMENT OF SOLICITATION NO.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.

Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:

(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN

REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE

CONTRACT ORDER NO. IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

10A. MOD. OF CONTRACT/ORDER NO.

2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)

6. ISSUED BY

3. EFFECTIVE DATE

12-Oct-2022

CODE

U S ARMY ENGR DISTRICT, NEW ENGLAND

696 VIRGINIA RD

CONCORD MA 01742-2751

W912WJ 7. ADMINISTERED BY (If other than item 6)

4. REQUISITION/PURCHASE REQ. NO.

CODE

See Item 6

FACILITY CODECODE

EMAIL:TEL:

W912WJ22R0014

SECTION SF 30 BLOCK 14 CONTINUATION PAGE

SUMMARY OF CHANGES

SECTION SF 30 - BLOCK 14 CONTINUATION PAGE

The following have been added by full text:

AMENDMENT 0003

Requests for Information

1. We currently plan to submit a proposal for the subject contract and are looking for USACE support regarding the requirements specified in Section L, Factor 4 Cost Submission Requirements, d. Section 4 and e. Section 5 (page 53 of 64). We do not have a determination of adequacy from a cognizant federal agency official (CFAO) indicating that our current cost accounting system has been determined to be adequate for cost reimbursement contracts. We did have one for our prior system obtained for a USACE cost-reimbursable contract.

The solicitation Section L, Factor 4, heading Cost Accounting System (page 56 of 64) indicates that the Offeror should coordinate with the Contracting Officer to obtain an accounting system review prior to submitting a proposal.

Please provide additional details of the process and timing to obtain the review from a CFAO.

An approved cost accounting system as outlined in Section L of the subject solicitation is preferred. Offerors that do not have an approved cost accounting system will submit current audited financials as part of the responsibility determination prior to award.

Per DFARS 252.242-7006, an acceptable accounting system will provide reasonable assurance that:

Applicable laws and regulations are complied with;

The accounting system and cost data are reliable;

Risk of misallocations and mischarges are minimized; and Contract allocations and charges are consistent with billing procedures.

The Contractor’s accounting system shall provide for:

(1) A sound internal control environment, accounting framework, and organizational structure;

(2) Proper segregation of direct costs from indirect costs;

(3) Identification and accumulation of direct costs by contract;

(4) A logical and consistent method for the accumulation and allocation of indirect costs to intermediate and final cost objectives;

(5) Accumulation of costs under general ledger control;

(6) Reconciliation of subsidiary cost ledgers and cost objectives to general ledger;

(7) Approval and documentation of adjusting entries;

(8) Management reviews or internal audits of the system to ensure compliance with the Contractor’s established policies, procedures, and accounting practices;

(9) A timekeeping system that identifies employees’ labor by intermediate or final cost objectives;

(10) A labor distribution system that charges direct and indirect labor to the appropriate cost objectives;

(11) Interim (at least monthly) determination of costs charged to a contract through routine posting of books of account;

(12) Exclusion from costs charged to Government contracts of amounts which are not allowable in terms of Federal Acquisition Regulation (FAR) part 31, Contract Cost Principles and Procedures, and other contract provisions;

(13) Identification of costs by contract line item and by units (as if each unit or line item were a separate contract), if required by the contract;

(14) Segregation of preproduction costs from production costs, as applicable;

(15) Cost accounting information, as required—

(i) By contract clauses concerning limitation of cost (FAR 52.232-20), limitation of funds (FAR 52.232-22), or allowable cost and payment (FAR 52.216-7); and

(ii) To readily calculate indirect cost rates from the books of accounts;

(16) Billings that can be reconciled to the cost accounts for both current and cumulative amounts claimed and comply with contract terms;

(17) Adequate, reliable data for use in pricing follow-on acquisitions; and

(18) Accounting practices in accordance with standards promulgated by the Cost Accounting Standards Board, if applicable, otherwise, Generally Accepted Accounting Principles.

2. Plans indicate an above ground LPG tank on the property and a line from the tank to the building but the tank appears to have been removed in current aerial photos. Is the facility now connected to a Natural Gas service?

The above ground LPG tank was removed when DMC connected to the new gas line. There is still an active gas line between the buildings.

3. Eversource specifications are referenced but not provided. Can you please provide the most current technical specifications from Eversource for the electrical and duct bank installation?

Current technical specifications from Eversource are not currently available. They will be made available to the successful offeror.

4. Would you entertain a 2-week extension to the bid date to allow for receipt and review of all RFIs?

See Amendment 0002.

5. Please advise a date/time for an official RFP site visit, which is required to afford key subcontractors to view existing site conditions.

A pre-bid site visit was held on 16 September 2022. At this time, USACE New England does not intend to hold further site visits.

6. Access to the building (inside) for purposes of confirming/shutting off utilities will need to be coordinated with government and Durham Meadows. Please confirm government will allow limited access into the building during planning/construction.

Yes, the Government will facilitate access for the selected contractor to allow development of plans.

7. Please provide Design files in CADD for purposes of takeoffs/design.

The successful offeror will be provided CADD files. Design files are subject to waivers that will be completed for the successful offeror.

8. Bid Schedule – Please confirm which bid item to use for temporary utilities (water, communications, storm drain, gas, etc) other than electric which is covered under Bid Item 7.

These items should be placed in Bid item 3 – Temporary Facilities.

9. Will the large trees removed for Phase 01A excavation require replacement? If so, please clarify what replacement requirements in regard to trees.

Large trees will require replacement. The draft access agreement with property owner is attached to this amendment.

The current draft agreement indicates that any hardwood trees outside of the access boundary that are damaged will be replaced with mature sugar maple trees no less than 10 ft in height. All Trees removed or damaged along the property boundary shall be replaced with mature arborvitae trees at least 8 feet in height and spaced in a manner to provide a visual screen.

10. Have the trees been sampled for contaminants? Can removed trees be mulched for reuse?

Trees have not been sampled for contaminants. Trees can be mulched.

11. Reference C-16, “Restore Pavement” location notes. Is the pavement to be restored to a squared off area (further than the excavation limits)? Or just restored to the neat excavation limit? Please clarify and provide requirements.

Pavement to be restored to neat limits.

12. Reference Drawing C-16, Note 5, “Replace Curb and Bollards where necessary”. Should restoration be to replace all existing to pre-excavation conditions including entry gate and electric gate, etc.? Please clarity and provide requirements.

Restoration should bring the site back to pre-excavation conditions. Any removed or damaged gates, curbs, or bollards will be replaced.

13. Reference Plan Page C-12, “Temporary Shoring and Foundation Underpinning”. Is underpinning mandated to be required for this project in addition to shoring? Please clarify.

Underpinning is not mandated, but the Underpinning Program Work Plan must address building stabilization in a manner acceptable to Government.

14. Reference Drawing C-08. Please specify which utilities (i.e., water, gas, communications, drainage, etc.) must remain active and be temporarily relocated during execution of this project.

All utilities must remain active. The contractor is to determine which utilities must be relocated based on their work plan.

15. Reference Cross Sections on Drawing C-15. Please clarify whether Contractor is required to remove contaminated soil from beneath the existing building foundation, and hence the underpinning requirement?

The contractor is not required to remove contaminated soil from beneath the building. The goal is to remove soil as close as possible to the building foundation without going underneath.

16. QC Representative must be employed by Prime Contractor as per specifications. Please confirm whether the Site Superintendent and SSHO are required to be employed by the Prime Contractor as well.

The Site Superintendent and SSHO do not need to employed by the Prime Contractor.

17. The specification says the Contractor shall utilize sound enclosures for any generators used to power dewatering equipment. If a generator is used, it must be whisper quiet.

Please clarify if the Contractor is to provide a generator to operate the dewatering equipment or if the dewatering equipment can be connected to existing power at the DMC site.

Dewatering equipment cannot be connected to existing power at the DMC site. The contractor is to provide a generator if the contractor determines it is required to operate dewatering equipment.

18. In the Solicitation, it states that the schedule should be completed in Microsoft Project or a similar software, then in the Specs, it requires the use of Primavera P6. Which system is required?

Primavera P6 is required for the construction schedule. The schedule included in response to the solicitation as part of the proposal does not need to be at the same level of detail and can be in MS Project, P6 or any similar project.

19. In Section L, it states "Offeror should assume a Notice to Proceed date of 01 May 2023"; on Page 5, the RPF states "all work must be completed 365 days after notice of award", please clarify.

See FAR 52.211-8 ALT III in Amendment 0003. To allow scheduling for the purposes of proposal preparation, an estimated start date was set at 01 May 2023. Regardless of the actual start date, all work must be completed 365 days after Notice to Proceed.

20. The RFP states: “For Federal Government projects: provide the contract number, contract place of performance, and DUNS number”. As of April 2022, DUNS have been replaced with the UEI. Which identifier should be used?

As noted, DUNS numbers are no longer used in SAM.gov. Please provide the UEI number.

21. The solicitation states, “For non-Federal Government projects and commercial projects: The Offeror shall provide, at a minimum, a NAVFAC/USACE Past Performance Questionnaire (PPQ).” Should CPARS or PPQs be provided for Federal Government projects?

CPARS should be used for Federal Government Projects.

22. Can a site visit be scheduled to walk subcontractors around the site to ensure understanding for our team of the scope of work?

See response to Question 5.

23. Will an extension to the current due date be considered to allow time for a site visit?

At this time, USACE New England does not intend to extend the due date past the current date as indicated in Amendment 0002.

24. Can the drawings associated with the PDF labeled "Plans" be provided in AutoCAD to assist with project take-offs?

CAD plans will be made available to the successful contractor. Design files are subject to waivers that will be completed for the successful offeror.

25. Section 01 13 00, Permitter Air Monitoring and Emissions Control Plan, Part 3 Execution, 3.1 General Lists appropriate methods to minimize the generation of dust and odors. None of the methods included the use of foam to control odors. Although in the Basis of Design (AECOM-June 2022), Section 7.2 Dust and Emission Control (Page 7-1), the following language is provided, "The contractor will be required to mitigate odors that are released during excavation of impacted material. Odor suppressant foam has been successfully utilized on similar sites. It is presented in this plan as an option. Odor suppressant foam can provide immediate, localized control of VOC and odor emissions. Foam is a short term remedy and can be actively used to control VOC and odor emissions from active excavations/stockpiles, and during the loading of trucks". Please confirm if the contractor should provide foam pricing to control nuisance odors.

The contractor should determine their approach to odor control. One option is foam, but other methods may be acceptable.

26. Bid Schedule, Bid Item 11, lists a quantity of 1,152 tons of Non-Haz Debris. Please confirm the source and what this volume of debris consists of.

It is assumed that non-hazardous debris will be encountered/generated. No specific source is known at this time.

27. Has the local POTW been contacted to confirm allowable water treatment discharge rates and post treatment POTW acceptance criteria?

There is no local POTW. Contractor is responsible for determining how to address any water treatment discharge.

28. Please confirm that stockpiling of soils will be allowed to facilitate continued excavation production in the event of transportation scheduling issues.

Stockpiling is acceptable, but all air monitoring, health and safety, erosion/sediment control and other applicable standards must be addressed to ensure stockpiling does not cause environmental or Health and Safety issue.

29. A 365 day performance period may be unrealistic, particularly with start of field work not anticipated until May 2023 and given the surgical nature of the majority of excavations limiting overall production. Please consider an 18 month period of performance, wherein excavation of Phase 02 is completed in 2024.

The requirement remains unchanged.

30. Section 01 50 00, Temporary Construction Facilities and Controls, Section 3.6, Traffic Provisions and Traffic Control Plan states that the Contractor shall be responsible for the repair of any damage to roads caused by construction operations. To even the bidding playing field, please indicate what Contractors should include in their pricing costs (Road Bonding, or Road Repair Allowance, and which Bid Item should these costs be included?

Road bonding is not required. Offerors are advised that if they damage a road they will be required to repair this damage. The Government does not expect any road damage.

31. Section 01 50 00, Temporary Construction Facilities and Controls, Section 3.6, Traffic Provisions and Traffic Control Plan states that the Contractor shall be responsible for the repair of any damage to roads caused by construction operations. Please confirm if this statement also includes the pavement areas located on the DMC property that will be used for vehicular access to the areas of excavation. Please consider including an associated area (square feet) that is anticipated to be restored as part of this remedial activity in an attempt to balance the pricing for this effort. Please note that the site visit conducted on 16 September 2022 did not provide an escort to the southern limit of the site to observe the condition of the existing paved areas.

All pavement areas, including those inside the excavation area as well as those only used for vehicular travel, must be left in the same condition as documented in the pre-construction survey. If any pavement areas within DMC are affected by the construction work, the Contractor will be required to repair.

32. Section 02050, Demolition, Section 1.01, Scope of Work identifies that Contractor may encounter ACM, lead paint, and PCBs (contained in window caulk, frames, glass panels, and concrete window casing). Has a hazardous waste survey been performed on the Storage Building to identify other waste streams that will require off-site disposal prior to demolition?

No hazardous waste survey was completed on the Storage Building. Assume the building has ACM, lead paint, and PCBs.

33. Section 02050 Demolition states the contractor shall assume the building is painted in lead-based paint (LBP) and that window caulk, frames, glass panes, and a 1-inch layer of concrete adjacent to the window frames shall be assumed to contain PCBs at concentrations of greater than or equal to 50ppm and shall be disposed of as PCB bulk waste. However, the section also states that the contractor shall perform an ACM survey prior to building demolition. Will the government permit the contractor to perform sampling for LBP and PCBs in building materials in conjunction with the ACM survey? If building materials do not contain LBP and PCBs there may be a cost savings to the government.

Yes, the Government will allow the successful contractor to perform sampling for LBP and PCBS during the ACM survey.

34. Section 01 11 00, 1.3 – Please clarify the versions of the TEP required (ie. draft, draft final, final).

Official submittals will be draft and final. The number of review/comment cycles to move from Draft to Final is contingent upon the Contractor’s ability to address reviewer’s comments. The comment/review cycle will continue until the document is acceptable to the Government.

35. Please clarify the review times for government and regulator approval.

The standard review time is 30 calendar days. See Section 01 33 00, 1.9, 1.11.1, Review Notations - Contracting Officer review will be completed within 30 calendar days after date of submission.

36. Please clarify if the government will obtain access to private property or if this is the responsibility of the contractor.

The Government will provide access to the DMC property and the adjacent Francis Earle Korn property.

37. Are biweekly progress reports to be submitted via RMS?

Biweekly progress reports are to be submitted via RMS.

38. Please clarify if the Preconstruction Conference will be an in-person meeting at the Durham Manufacturing Company (DMC) site or if the meeting will be conducted via virtual meeting.

Assume meetings are all in-person, although hybrid meetings are acceptable. Note that major team members responsible for day-to-day work should be available for site meetings in-person.

39. Is the Perimeter Air Monitoring and Emissions Control Plan to be included in the TEP as an Appendix?

The Perimeter Air Monitoring and Emission Control Plan can either be referenced in the TEP or put into the TEP as an appendix.

40. If the Perimeter Air Monitoring and Emissions Control Plan is to be submitted as a stand-alone document, please specify the versions (draft, draft final, final) to be submitted and the review times for the government and regulators.

The plan can be either referenced in the TEP or put into the TEP as an appendix. Official submittals will be draft and final. Though the number of review/comment cycles to move from Draft to Final is contingent upon the Contractor’s ability to address reviewer’s comments. The comment/review cycle will continue until the document is acceptable to the Government.

41. Please clarify if the weekly air monitoring report is to be submitted via RMS.

Yes, the report is to be submitted via RMS.

42. Please clarify if the Preconstruction Meeting is to be an in-person meeting at DMC or will be held via virtual meeting.

Assume meetings are all in-person, although hybrid meetings are acceptable. Note that major team members responsible for day-to-day work should be available for site meetings in-person.

43. Please clarify if stakeholder meetings will be in-person or via virtual meeting.

Stakeholder meetings will be in-person.

44. Please clarify if all schedule submittals are to be submitted via RMS.

All schedule submittals are to be submitted via RMS.

45. Please clarify if NTP is assumed on the day of award. If not, please clarify when NTP will be provided by the government following the award date.

NTP is assumed on the day of award.

46. Please clarify if the contractor is to submit the project schedule, Narrative Report, and all required schedule reports via CD/DVD or if these submittals can be submitted electronically via email or RMS.

Project Schedule, Narrative Report, and all required schedule reports are to be submitted via RMS.

47. Please clarify if the monthly schedule meetings will be conducted via virtual meeting. Please clarify if the contractor should assume the monthly schedule meetings will be 8 hours.

The meeting will be in-person. The meeting duration is a function of the agenda items, although it should not be as long as 8 hours.

48. Please clarify if the weekly progress meetings are to be conducted via virtual meeting.

Assume meetings are all in-person, although hybrid meetings are acceptable. Note that major team members responsible for day-to-day work should be available for site meetings in-person.

49. The Technical Execution Plan referenced in Section 01 11 00 as a Preconstruction Submittal is not included in the list of Preconstruction Submittals. Should the TEP be included in this list?

The list in Section 01 33 00, 1.2.1 is not an all-inclusive list. Refer to submittal register for a complete list.

50. Please clarify if all the plans listed in this section are individual plans or will be included as appendices in the

TEP.

It can be an appendix or can be referenced in the TEP.

51. Please clarify the versions of the plans (ie. draft, draft final, final) and the review times required for government and regulators.

See response to Question 40.

52. Please clarify if the Contractor Quality Control (QC) Manager shall be full-time or if the Site Superintendent can also act as QC Manager.

The contractor Quality Control Manager shall be full-time and cannot also be the Site Superintendent.

53. Section 01 35 26, 1.9.1.8 discusses the contractor providing a qualified person to instruct a 40-hour safety awareness course including providing a written exam. Please clarify if this requirement is required, since all personnel working on the site will be required to already have completed the 40-hourOSHA HAZWOPER class.

The contractor will be required to submit a Site Safety and Health Plan that must adhere to EM 395-1-1. The contractor should determine what training is necessary to meet this requirement. The section referenced in this question is the general requirements for a Qualified Trainer and may not be applicable to this work.

54. Section 01 35 26, 1.9.2.2 references the Superintendent’s duties, but this section does not define the superintendent’s duties. Please provide a description of the superintendent’s duties.

See section 01 40 00, 3.1 General Requirements, for information on Superintendent’s duties.

55. Please clarify if all the submittals listed in this section are to be submitted to the government via RMS.

All submittals listed are to be submitted via RMS.

56. Please clarify if Daily Quality Control reports and the SSHO Daily Inspection logs are to be submitted to the government via RMS.

Daily Quality Control reports and the SSHO Daily Inspection logs are to be submitted via RMS.

57. Please clarify if vehicles and equipment used in the EZ can be decontaminated using dry brushing techniques or if the equipment must be pressure washed.

Decontamination methods should be determined by Contractor and approved by their Health and Safety system.

58. Please clarify if a professional photographer is needed for pre- and final completion construction photographs and that photograph must submit samples of their work or if site personnel will be allowed to use their cell phone cameras.

A professional photographer is not required. Per Section 01 39 00, Part 1, 1.3 Submittals – contractor shall submit work by proposed photographer. Details on format and camera resolution are provided in the same section.

59. Section 01 39 00, 1.3 says to submit photograph files within 3 days of taking photographs. Please clarify if the contractor must adhere to this requirement or if photographs will just be submitted with the final report.

The contractor must adhere to this requirement.

60. Section 01 39 00, 2.4 references development of photograph prints. Please clarify if the contractor is required to provide a developed hard copy of each photo or if digital images can be submitted.

Digital images can be submitted.

61. Please clarify that the on site CQC System Manager must be a full-time person and that the project superintendent cannot dual-hat in this role.

Contractor Quality Control Manager shall be full-time and cannot also be the Site Superintendent. See section 01 40 00, 3.4.2 CQC System Manager.

62. Please clarify if the Preconstruction Conference is to be held in person at DMC or via virtual meeting. Please clarify if the QC Coordination Meeting can be held on the same day as the Preconstruction Conference.

The preconstruction conference will be in-person, although some members may attend virtually. The QC Coordination meeting cannot be held on the same day of the Preconstruction Conference.

63. Please clarify if the QAPP/SAP is a stand-alone document. Please clarify the versions of the QAPP/SAP (ie.

draft, draft final, final) and the review times required for government and regulators.

The QAPP/SAP can be an appendix to the TEP or a separate document. Official submittals will be draft and final.

The number of review/comment cycles to move from Draft to Final is contingent upon the Contractor’s ability to address reviewer’s comments. The comment/review cycle will continue until the document is acceptable to the Government. The standard Government review time is 30 calendar days. See Section 01 33 00, 1.9, 1.11.1, Review Notations - Contracting Officer review will be completed within 30 calendar days after date of submission.

64. Please clarify if the contractor is to submit all documents (plans, reports, daily reports, schedule, lab data, etc.) to the government via RMS.

All listed documents are to be submitted via RMS.

65. Please clarify if a Project Pesticide Coordinator is required for this project.

A project pesticide coordinator is required. See Section 01 57 20, 3.10 Integrated Pest Management “In order to minimize impacts to existing fauna and flora, the Contractor, through the Contracting Officer, shall coordinate with the Project Pesticide Coordinator (PPC) at the earliest possible time prior to pesticide application, if pesticide treatment becomes necessary.”

66. Please clarify if the Environmental Protection Plan and Wood Turtle Protection Plan are stand-alone documents or appendices to a primary Work Plan. Please clarify the versions of the plans (ie. draft, draft final, final) and the review times required for government and regulators.

The Environmental Protection Plan and the Wood Turtle Protection Plan can be either a stand-alone documents or appendix. Official submittals will be draft and final. The number of review/comment cycles to move from Draft to Final is contingent upon the Contractor’s ability to address reviewer’s comments. The comment/review cycle will continue until the document is acceptable to the Government. The standard Government review time is 30 calendar days. See Section 01 33 00, 1.9, 1.11.1.

67. Please clarify if the contractor is required to conduct a field survey by a certified wetland biologist at any time during the field activities.

There is no requirement for the Contractor to conduct a field survey by a certified wetland biologist.

68. Please clarify if the preconstruction submittals are stand-alone documents or appendices to a primary Work Plan Please clarify the versions of the plans (ie. draft, draft final, final) and the review times required for government and regulators.

The preconstruction submittals can be either stand-alone documents or appendices as long as the required elements are covered. Official submittals will be draft and final. The number of review/comment cycles to move from Draft to Final is contingent upon the Contractor’s ability to address reviewer’s comments. The comment/review cycle will continue until the document is acceptable to the Government. The standard Government review time is 30 calendar days. See Section 01 33 00, 1.9, 1.11.1.

69. Please clarify if the DD1354 form is required for this contract.

It is not anticipated that the Government will provide any Real Property; therefore, it is unlikely that form DD1354 will be required.

70. Please clarify the versions (i.e., draft, draft final, final) of the construction drawings for the storage shed and the review times required for the government.

See response to Question 40.

71. Please clarify if the contractor is required to provide a uniformed police officer to direct traffic on Main Street.

See section 02120, 1.01 E. – “Contractor will employ a uniformed police officer to be at the site to direct traffic on Main Street.”

72. Please clarify if the contractor is required to clean local streets each day using a street sweeper.

The Contractor is required to keep debris and fluid from leaving the site. The Contractor shall determine the best manner of accomplishing this task.

73. Please clarify the versions (ie. draft, draft final, final) of the Excavation Support Plan and Construction Contingency Plan and the review times required for the government.

See response to Question 40 and 63.

74. Please clarify the versions (ie. draft, draft final, final) of the Underpinning Program Work Plan and the review times required for the government.

See response to Question 40 and 63.

75. Please clarify the versions (ie. draft, draft final, final) of the Excavation Plan and the review times required for the government.

See response to Question 40 and 63.

76. Please clarify if the contractor is required to complete the 3 phases in the order of 1A, 1B, then 2 or can the sequence be changed.

The sequence can be determined by Contractor.

77. “The contractor shall replace monitoring wells OW-3-08 and OW-8R-08.” Please clarify if the two new replacement wells are to be developed following installation.

Wells must be developed following installation.

78. “The contractor shall replace monitoring wells OW-3-08 and OW-8R-08.” Please clarify if the two new replacement wells are to be sampled. If the contractor is required to sample the new wells, please clarify the required laboratory analysis and if the sampling will be a one-time event.

Sampling is not required.

79. Please clarify if all Plans discussed throughout the Specifications are to be included as Appendices to the Technical Execution Plan.

The plan can be either referenced in the TEP or put into the TEP as an appendix.

80. Is the Contractor’s Health and Safety Manager, who will not be onsite full time per the specs, required to attend the Biweekly Health and Safety meeting in person or can they attend via virtual meeting?

The contractor’s Health and Safety Manager may attend virtually.

81. Section L, Factor 4, Direct Material: Please consider reducing the level of detail required for direct materials given the significant number of direct materials required for the project.

The requirement remains unchanged.

82. Section L, Factor 4, Subcontracts: Solicitation states that Major Subcontractors shall provide cost information equivalent to that of the Prime Offeror. If the Major Subcontractor will be a firm-fixed price subcontract, is the subcontractor required to provide details of overhead/indirect cost rates for labor, materials, and equipment?

Yes, if there are major subcontractors, cost information from those subcontractors is to be submitted equivalent to that of the prime.

SECTION F - DELIVERIES OR PERFORMANCE

The following have been modified:

52.211-8 TIME OF DELIVERY (JUN 1997)--ALTERNATE III (APR 1984)

(a) The Government requires delivery to be made according to the following schedule: REQUIRED DELIVERY

SCHEDULE:

ALL WORK MUST BE COMPLETED 365 DAYS AFTER NOTICE TO PROCEED.

The Government will evaluate equally, as regards time of delivery, offers that propose delivery of each quantity within the applicable delivery period specified above. Offers that propose delivery that will not clearly fall within the applicable required delivery period specified above, will be considered nonresponsive and rejected. The Government reserves the right to award under either the required delivery schedule or the proposed delivery schedule, when an offeror offers an earlier delivery schedule than required above. If the offeror proposes no other delivery schedule, the required delivery schedule above will apply.

OFFEROR'S PROPOSED DELIVERY SCHEDULE

WITHIN DAYS AFTER DATE OF RECEIPT OF:

ITEM NO. QUANTITY WRITTEN NOTICE OF AWARD

(End of clause)

(End of Summary of Changes)