Supplemental Price Breakdown to the Bidding Schedule.xlsx
XLSX spreadsheet 12 KB Posted
- Solicitation number
- W912WJ21R0003
About this file
This document contains a supplemental price breakdown spreadsheet and related federal contract opportunity notice for the replacement of two power transformers at the Fox Point Hurricane Barrier in Providence, Rhode Island. The U.S. Army Corps of Engineers, New England District is soliciting proposals to replace the original oil-filled power transformers designated as Transformers A and B, as well as the original manually operated disconnect switches at the transformer primary connections. The price breakdown spreadsheet provides unit pricing for individual work items associated with the removal of the existing transformers and installation of the new transformers. The contract opportunity notice specifies this is an unrestricted best value procurement with an estimated value between $1,000,000 and $5,000,000 and a period of performance of 540 calendar days. Proposals must be submitted through the System for Award Management website.
View the file
Other files
Show all 13
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Sheet1
| Supplemental Price Breakdown to the Bidding Schedule | |||||
| Replace Transformers A and B | |||||
| Fox Point Hurricane Barrier - Providence, Rhode Island | |||||
| UOM | Price | ||||
| Project Grand Total (Items 0001-0005) | LS | $0.00 | |||
| Item | UOM | Price | |||
| '0001 | Existing Transformer A - Siteprep, Shutdown, Disconnection and Removal | ||||
| 0001A | Shutdown Power Transformer A side and Disconnect exist. 5,v, 3000 amp Bus Duct. | LS | $0.00 | ||
| 0001B | Cable and Conduit Removal | LS | $0.00 | ||
| 0001C | Remove 15 kV, 1,200 A 3pole Disconnect and Space Heater w/branch wiring | LS | $0.00 | ||
| 0001D | Remove steel Busduct Enclosure | LS | $0.00 | ||
| 0001E | Disconnect 15 kV Potheads and Primary Connections from Transformer | LS | $0.00 | ||
| 0001F | Remove and Dispose of Transformer Oil | LS | $0.00 | ||
| 0001G | Remove and Dispose of Transformer A | LS | $0.00 | ||
| Item 0001 Total | $0.00 |
| Item | UOM | Price | |||
| '0002 | New Transformer A - New Installation and Cut-Over | ||||
| 0002A | Procure and Deliver New Unit Substation Tranformer | LS | $0.00 | ||
| 0002B | Seismic absorbers for transformer base | LS | $0.00 | ||
| 0002C | New Transformer Installation on prepared base | LS | $0.00 | ||
| 0002D | Prep and Fill New Transformer Oil Tank | LS | $0.00 | ||
| 0002E | Reconnect 15 kV Potheads and New Primary Conductors and All Conduit and Wiring | LS | $0.00 | ||
| 0002F | Install new 15kV, 1,200 Amp Disconnect, space heater, wiring | LS | $0.00 | ||
| 0002G | Install new Bus Duct Enclosure | LS | $0.00 | ||
| 0002H | Cutover Power to Transformer A side | LS | $0.00 | ||
| 0002I | Test and Commission | LS | $0.00 | ||
| Item 0002 Total | $0.00 | ||||
| Item | UOM | Price | |||
| '0003 | Existing Transformer B - Siteprep, Shutdown, Disconnection and Removal | ||||
| 0003A | Shutdown Power Transformer A side and Disconnect exist. 5,v, 3000 amp Bus Duct. | LS | $0.00 | ||
| 0003B | Cable and Conduit Removal | LS | $0.00 | ||
| 0003C | Remove 15 kV, 1,200 A 3pole Disconnect and Space Heater w/branch wiring | LS | $0.00 | ||
| 0003D | Remove steel Busduct Enclosure | LS | $0.00 | ||
| 0003E | Disconnect 15 kV Potheads and Primary Connections from Transformer | LS | $0.00 | ||
| 0003F | Remove and Dispose of Transformer Oil | LS | $0.00 | ||
| 0003G | Remove and Dispose of Transformer A | LS | $0.00 | ||
| Item 0003 Total | $0.00 |
| Item | UOM | Price | |||
| '0004 | New Transformer B - New Installation and Cut-Over | ||||
| 0004A | Procure and Deliver New Unit Substation Tranformer | LS | $0.00 | ||
| 0004B | Seismic absorbers for transformer base | LS | $0.00 | ||
| 0004C | New Transformer Installation on prepared base | LS | $0.00 | ||
| 0004D | Prep and Fill New Transformer Oil Tank | LS | $0.00 | ||
| 0004E | Reconnect 15 kV Potheads and New Primary Conductors and All Conduit and Wiring | LS | $0.00 | ||
| 0004F | Install new 15kV, 1,200 Amp Disconnect, space heater, wiring | LS | $0.00 | ||
| 0004G | Install new Bus Duct Enclosure | LS | $0.00 | ||
| 0004H | Cutover Power to Transformer A side | LS | $0.00 | ||
| 0004I | Test and Commission | LS | $0.00 | ||
| Item 0004 Total | $0.00 | ||||
| Item | UOM | Price | |||
| '0005 | Training, As-Builts,and Project Close-Out Submittals | LS | $0.00 | ||
| Item 0005 Total | $0.00 |