Amendment W912WJ21R0003-0004.pdf

PDF 594 KB Posted

Attached to
Replacement of Transformers at the Fox Point Hurricane Barrier, Providence, RI
Solicitation number
W912WJ21R0003
Issued by

About this file

This amendment modifies a solicitation to replace two power transformers and disconnect switches at the Fox Point Hurricane Barrier in Providence, Rhode Island. The U.S. Army Corps of Engineers, New England District is seeking proposals for the transformer replacement project, estimated between $1,000,000 to $5,000,000, with a performance period of 540 calendar days extended to May 31, 2023. Interested parties must register in the System for Award Management to download the solicitation. Questions may be directed to the specified Contract Specialist by email. Revisions include responses to requests for information on transformer delivery and assembly, as well as changes to specifications regarding transformer foundations and connections.

View the file

Other files

File Type Posted
Amendment W912WJ21R0003-0005.pdf PDF
Revised 48 20 00.pdf PDF
Revised 48 19 23.pdf PDF
Amendment W912WJ21R0003-0003.pdf PDF
Amendment W912WJ21R0003-0002.pdf PDF
Appendix D.pdf PDF
Amendment W912WJ21R0003-0001.pdf PDF
Appendix H SBPD.pdf PDF
Fox Point 1141 1143 FDRS Schematic Wiring Diagram H-19998- 0.pdf PDF
Supplemental Price Breakdown to the Bidding Schedule.xlsx XLSX spreadsheet
W912WJ21R0003.pdf PDF
Plans.pdf PDF
Specs.pdf PDF
Show all 13

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print)

30-105-04EXCEPTION TO SF 30

APPROVED BY OIRM 11-84

STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA

FAR (48 CFR) 53.243

The above referenced solicitation is hereby amended to revise FAR Clause 52.211-10- Commencement, Prosecution and Completion of Work, to provide responses to Requests for Information, and to provide revised Specification Sections 48 19 23 and 48 20 00. All other terms and conditions remain unchanged.

1. CONTRACT ID CODE PAGE OF PAGES

1 3

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

16C. DATE SIGNED

BY 18-Feb-2021

16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR

(Signature of Contracting Officer)(Signature of person authorized to sign)

8. NAME AND ADDRESS OF CONTRACTOR (No., Street , County, State and Zip Code) X W912WJ21R0003

X 9B. DATED (SEE ITEM 11)

04-Jan-2021

10B. DATED (SEE ITEM 13)

9A. AMENDMENT OF SOLICITATION NO.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.

Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:

(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN

REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE

CONTRACT ORDER NO. IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

10A. MOD. OF CONTRACT/ORDER NO.

2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)

6. ISSUED BY

3. EFFECTIVE DATE

18-Feb-2021

CODE

U S ARMY ENGR DISTRICT, NEW ENGLAND

696 VIRGINIA RD

CONCORD MA 01742-2751

W912WJ 7. ADMINISTERED BY (If other than item 6)

4. REQUISITION/PURCHASE REQ. NO.

CODE

See Item 6

FACILITY CODECODE

EMAIL:TEL:

W912WJ21R0003

SECTION SF 30 BLOCK 14 CONTINUATION PAGE

SUMMARY OF CHANGES

SECTION SF 30 - BLOCK 14 CONTINUATION PAGE

The following have been added by full text:

REQUESTS FOR INFORMATION

1. Specification 48 20 00 Section 3.3.1 dictates that the transformers are to be delivered without oil. Manufacturer’s recommendation for a unit this size to ship fully assembled, oil filled. Please confirm it is acceptable to ship the transformers per manufacture's recommendations already oil filled and fully assembled.

RESPONSE: See revised Specification 48 20 00 Section 3.3.1.

2. It is typical of some manufacturers to deliver transformers of this size assembled and oil filled.

Specification 48 20 00 3.3.1 states the transformer shall be delivered without oil. Specification 48 19 23 3.6 states the transformer is to be re-assembled and oil filled if required. Can the transformers be delivered to the site oil filled?

RESPONSE: Please see the above response to RFI number 1.

3. Project duration specified in 52.211-10 of the RI_USACE Fox Point Barrier W912WJ21R0003

Solicitation Package page 52 states that the contract duration will be 540 days. This means the contract period will end during the 2022 hurricane restricted timeframe. Please confirm that the intent of USACE is to have the transformers replaced by 5/31/2022.

RESPONSE: Clause 52.211-10 has been replaced with Clause 52.211-10 Alt I, which extends the allowable period of perfomance for contract work to May 31, 2023.

4. Transformer manufacturers have been providing feedback that the steel supporting base as specified in Transformer Specification Section 48 19 23 2.7.6 will not be required/not provided by the manufacturer. These transformers are custom built to line up with the existing bus connections and feeders. Please confirm that this component can be omitted from the design and the transformers mounted directly to the concrete foundation. If this is not acceptable, please confirm that the steel foundation between the concrete slab and the bottom of the transformer can be a field bolted connection and not a field welded connection.

RESPONSE: Please see revised Specification 48 19 23 Section 2.7.6.

5. Please confirm if the existing bus to the transformers has bolted connections or welded connections.

RESPONSE: The existing bus to the transformers has bolted connections.

6. Price Breakdown items 0002B and 0004B refer to seismic absorbers for transformer base. We don't see a reference to seismic absorbers anywhere in the Drawings or Specifications. Please clarify what this price breakdown item refers to.

RESPONSE: Items 0002B and 0004B refer to anchorages specified in specification section 13 48 00 Seismic Restraint for Mechanical and Electrical Equipment. Any costs associated with inclusion of seismic anchorages of the transformers based on Section 13 48 00 should be paid for under those breakdown items.

SECTION 00010 - SOLICITATION CONTRACT FORM

The contractor period of performance end 540 has been deleted.

W912WJ21R0003

SECTION 00800 - SPECIAL CONTRACT REQUIREMENTS

The following have been added by full text:

52.211-10 COMMENCEMENT, PROSECUTION, AND COMPLETION OF WORK (APR 1984) -

ALTERNATE I (APR 1984)

The Contractor shall be required to (a) commence work under this contract within 15 calendar days after the date the Contractor receives the notice to proceed, (b) prosecute the work diligently, and (c) complete the entire work ready for use not later than May 31, 2023. * The time stated for completion shall include final cleanup of the premises.

*The Contracting Officer shall specify either a number of days after the date the contractor receives the notice to proceed, or a calendar date.

The completion date is based on the assumption that the successful offeror will receive the notice to proceed by 1 November 2021. The completion date will be extended by the number of calendar days after the above date that the Contractor receives the notice to proceed, except to the extent that the delay in issuance of the notice to proceed results from the failure of the Contractor to execute the contract and give the required performance and payment bonds within the time specified in the offer.

(End of clause)

The following have been deleted:

52.211-10 Commencement, Prosecution, and Completion of Work APR 1984

(End of Summary of Changes)