This solicitation package includes specifications and drawings for the construction of the Human Engineering Lab - Soldier Squad Performance Research Institute at Natick Soldier Systems Center in Natick, Massachusetts. Key requirements include construction of temporary facilities and controls, interior signage, and stair signage. The specifications provide product and installation requirements for standard room signs, changeable message strip signs, stair signage, and protective site fencing. The contractor must attend an organized site visit on March 18, 2020 and submit any requests for information by March 25, 2020. The solicitation number is W912WJ20B0001 and was issued by the Department of the Army Corps of Engineers Engineering District New England.
View the file
Other files
Show all 29
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
SECTION 01 50 00
TEMPORARY CONSTRUCTION FACILITIES AND CONTROLS
05/1804/23/2020
PART 1 GENERAL
1.1 REFERENCES
The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.
AMERICAN SOCIETY OF HEATING, REFRIGERATING AND AIR-CONDITIONING
ENGINEERS (ASHRAE)
ASHRAE 189.1 (2014) Standard for the Design of High-Performance Green Buildings Except Low-Rise Residential Buildings
AMERICAN WATER WORKS ASSOCIATION (AWWA)
AWWA C511 (2017) Reduced-Pressure Principle Backflow Prevention Assembly
FOUNDATION FOR CROSS-CONNECTION CONTROL AND HYDRAULIC RESEARCH
(FCCCHR)
FCCCHR List (continuously updated) List of Approved Backflow Prevention Assemblies
FCCCHR Manual (10th Edition) Manual of Cross-Connection Control
NATIONAL FIRE PROTECTION ASSOCIATION (NFPA)
NFPA 241 (2013; Errata 2015) Standard for Safeguarding Construction, Alteration, and Demolition Operations
NFPA 70 (2017; ERTA 1-2 2017; TIA 17-1; TIA 17-2;
TIA 17-3; TIA 17-4; TIA 17-5; TIA 17-6;
TIA 17-7; TIA 17-8; TIA 17-9; TIA 17-10;
TIA 17-11; TIA 17-12; TIA 17-13; TIA
17-14; TIA 17-15; TIA 17-16; TIA 17-17 )
National Electrical Code
U.S. ARMY CORPS OF ENGINEERS (USACE)
EM 385-1-1 (2014) Safety and Health Requirements Manual
U.S. DEPARTMENT OF DEFENSE (DOD)
UFC 1-200-02 (2016, with Change 1) High Performance and Sustainable Building Requirements
U.S. FEDERAL AVIATION ADMINISTRATION (FAA)
FAA AC 70/7460-1 (2015; Rev L) Obstruction Marking and Lighting
U.S. FEDERAL HIGHWAY ADMINISTRATION (FHWA)
MUTCD (2015) Manual on Uniform Traffic Control Devices
1.2 SUBMITTALS
Government approval is required for submittals with a "G" designation;
submittals not having a "G" designation are for information only. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government. Submittals with an "S" are for inclusion in the Sustainability eNotebook, in conformance to Section 01 33 29 SUSTAINABILITY REPORTING. Submit the following in accordance with Section 01 33 00 SUBMITTAL PROCEDURES:
SD-01 Preconstruction Submittals
Construction Site Plan; G, RO
Traffic Control Plan; G
Haul Road Plan; G, RO
SD-06 Test Reports
Backflow Preventer Tests; G, RO
SD-07 Certificates
Backflow Tester Certification; G, RO
Backflow Preventers Certificate of Full Approval
1.3 CONSTRUCTION SITE PLAN
Prior to the start of work, submit a site plan showing the locations and dimensions of temporary facilities (including layouts and details, equipment and material storage area (onsite and offsite), and access and haul routes, avenues of ingress/egress to the fenced area and details of the fence installation. Identify any areas which may have to be graveled to prevent the tracking of mud. Indicate if the use of a supplemental or other staging area is desired. Show locations of safety and construction fences, site trailers, construction entrances, trash dumpsters, temporary sanitary facilities, and worker parking areas.
1.4 BACKFLOW PREVENTERS CERTIFICATE
Certificate of Full Approval from FCCCHR List, University of Southern California, attesting that the design, size and make of each backflow preventer has satisfactorily passed the complete sequence of performance testing and evaluation for the respective level of approval. Certificate of Provisional Approval will not be acceptable.
1.4.1 Backflow Tester Certificate
Prior to testing, submit to the Contracting Officer certification issued by the State or local regulatory agency attesting that the backflow tester has successfully completed a certification course sponsored by the regulatory agency. Tester must not be affiliated with any company participating in any other phase of this Contract.
1.4.2 Backflow Prevention Training Certificate
Submit a certificate recognized by the State or local authority that states the Contractor has completed at least 10 hours of training in backflow preventer installations. The certificate must be current.
PART 2 PRODUCTS
2.1 TEMPORARY SIGNAGE
2.1.1 Bulletin Board
Within one calendar day of mobilization on site and prior to the commencement of work activities, provide a clear weatherproof covered bulletin board not less than 36 by 48 inches in size for displaying the Equal Employment Opportunity poster, a copy of the wage decision contained in the contract, Wage Rate Information poster, Safety and Health Information as required by EM 385-1-1 Section 01 and other information approved by the Contracting Officer. Coordinate requirements herein with
01 35 26 GOVERNMENTAL SAFETY REQUIREMENTS.
2.1.2 Project Identification Signs
The requirements for the signs, their content, and location are as specified in Section 01 58 00 PROJECT IDENTIFICATION. Erect signs within 15 days after receipt of the notice to proceed. Correct the data required by the safety sign daily, with light colored metallic or non-metallic numerals.
2.1.3 Warning Signs
Post temporary signs, tags, and labels to give workers and the public adequate warning and caution of construction hazards according to the EM 385-1-1 Section 04. Attach signs to the perimeter fencing every 150 feet warning the public of the presence of contruction hazards. Signs must require unauthorized persons to keep out of the construction site. Correct the data required by safety signs daily.
2.2 TEMPORARY TRAFFIC CONTROL
2.2.1 Haul Roads
Construct access and haul roads necessary for proper prosecution of the work under this contract in accordance with EM 385-1-1 Section 04.
Construct with suitable grades and widths; sharp curves, blind corners, and dangerous cross traffic are be avoided. Submit haul road plan for approval. Provide necessary lighting, signs, barricades, and distinctive markings for the safe movement of traffic. The method of dust control, although optional, must be adequate to ensure safe operation at all times.
Location, grade, width, and alignment of construction and hauling roads are subject to approval by the Contracting Officer. Lighting must be adequate to assure full and clear visibility for full width of haul road and work areas during any night work operations.
2.2.2 Barricades
Erect and maintain temporary barricades to limit public access to hazardous areas. Whenever safe public access to paved areas such as roads, parking areas or sidewalks is prevented by construction activities or as otherwise necessary to ensure the safety of both pedestrian and vehicular traffic barricades will be required. Securely place barricades clearly visible with adequate illumination to provide sufficient visual warning of the hazard during both day and night.
2.3 FENCING
Provide fencing along the construction site and at all open excavations and tunnels to control access by unauthorized personnel. Safety fencing must be highly visible to be seen by pedestrians and vehicular traffic.
Specific fencing requirements are as described herein. All fencing will meet the requirements of EM 385-1-1.
2.3.1 Polyethylene Mesh Safety Fencing
Temporary safety fencing must be a high visibility orange colored, high density polyethylene grid, a minimum of 48 inches high and maximum mesh size of 2 inches. Fencing must extend from the grade to a minimum of 48 inches above the grade and be tightly secured to T-posts spaced as necessary t maintain a rigid and taut fence. Fencing must remain rigid and taut with a minimum of 200 pounds of force exerted on it from any direction with less than 4 inches of deflection.
2.3.2 Not UsedChain Link Panel Fencing
Temporary panel fencing must be galvanized steel chain link panels 6 feet high. Multiple fencing panels may be linked together at the bases toform long spens as needed. Each panel base must be weighted down using sand bags or other suitable materials in order ofr the fencing to withstand anticipated winds while remaining upright. Fencing must remain rigid and taut with a minimum of 200 pounds of force exerted on it from any direction with less than 4 inches of deflection.
2.3.3 Post-Driven Chain Link Fencing
Temporary post-driven fencing must be galvanized chain link fencing constructed as shown on Sheet C-501 of the contract drawings and6 feet high supported by by an tightly secured to galvanized steel posts driven below grade. Fence posts must be located on minimuma maximum of 10 foot on center
s. Posts may be set in various sufaces such as sand, soil, ashpalt or concrete as necessary. Chain link fencing must remain rigid and taut with a minimum of 200 pounds of force exerted on it from any direction with less than 4 inches of deflection. Include either plastic strip inserts within the chain link fabric or attach construction grade fence screening to the inside of the fabric (85% vision blockage minimum), colored green, so that visibility through the fence is obstructed. Screening shall be securely attached and shall be replaced if any tears or defects occur. Fencing and posts must be completely removed at the completion of construction and any surfaces disturbed or damaged must be restored to its original condition.
Underground utilities must be located and identified prior to setting fence posts. Fence must be equipped with a lockable gate as shown. Gate must remain locked when construction personnel are not present.
2.4 TEMPORARY WIRING
Provide temporary wiring in accordance with EM 385-1-1 Section 11, NFPA 241 and NFPA 70. Include monthly inspection and testing of all equipment and apparatus.
2.5 BACKFLOW PREVENTERS
Reduced pressure principle type conforming to the applicable requirements AWWA C511. Provide backflow preventers complete with 150 pound flanged cast iron, mounted gate valve and strainer, 304 stainless steel or bronze, internal parts. After installation conduct Backflow Preventer Tests and provide test reports verifying that the installation meets the FCCCHR Manual Standards.
PART 3 EXECUTION
3.1 EMPLOYEE PARKING
Construction contract employees will park privately owned vehicles in an area designated by the Contracting Officer. This area will be within reasonable walking distance of the construction site. Employee parking must not interfere with existing and established parking requirements of the government installation.
3.2 TEMPORARY BULLETIN BOARD
Locate the bulletin board at the project site in a conspicuous place easily accessible to all employees, as approved by the Contracting Officer.
3.3 AVAILABILITY AND USE OF UTILITY SERVICES
3.3.1 Temporary Utilities
Provide temporary utilities required for construction. Materials may be new or used, must be adequate for the required usage, not create unsafe conditions, and not violate applicable codes and standards.
3.3.2 Payment for Utility Services
a. The Government will make all reasonably required utilities available from existing outlets and supplies, as specified in the contract.
Unless otherwise provided in the contract, the amount of each utility service consumed will be charged to or paid at prevailing rates charged to the Government or, where the utility is produced by the Government, at reasonable rates determined by the Contracting Officer. Carefully conserve any utilities furnished without charge.
b. Reasonable amounts of the following utilities will be made available without charge.
c. The point at which the Government will deliver such utilities or services and the quantity available is as indicated. Pay all costs incurred in connecting, converting, and transferring the utilities to the work. Make connections, including providing backflow-preventing devices on connections to domestic water lines; providing meters; and providing transformers; and make disconnections.
3.3.3 Meters and Temporary Connections
Provide and maintain necessary temporary connections, distribution lines, and meter bases (Government will provide meters) required to measure the amount of each utility used for the purpose of determining charges. Notify the Contracting Officer, in writing, 5 working days before final electrical connection is desired so that a utilities contract can be established. The Government will provide a meter and make the final hot connection after inspection and approval of the Contractor's temporary wiring installation.
Do not make the final electrical connection.
3.3.4 Advance Deposit
An advance deposit for utilities consisting of an estimated month's usage or a minimum of $50.00 will be required. The last monthly bills for the fiscal year will normally be offset by the deposit and adjustments will be billed or returned as appropriate. Services to be rendered for the next fiscal year, beginning 1 October, will require a new deposit. Notification of the due date for this deposit will be mailed prior to the end of the current fiscal year.
3.3.5 Final Meter Reading
Before completion of the work and final acceptance of the work by the Government, notify the Contracting Officer, in writing, 5 working days before termination is desired. The Government will take a final meter reading, disconnect service, and remove the meters. Then remove all the temporary distribution lines, meter bases, and associated paraphernalia.
Pay all outstanding utility bills before final acceptance of the work by the Government.
3.3.6 Sanitation
a. Provide and maintain within the construction area minimum field-type sanitary facilities approved by the Contracting Officer and periodically empty wastes into a municipal, district, or station sanitary sewage system, or remove waste to a commercial facility.
Obtain approval from the system owner prior to discharge into any municipal, district, or commercial sanitary sewer system. Any penalties or fines associated with improper discharge will be the responsibility of the Contractor. Coordinate with the Contracting Officer and follow station regulations and procedures when discharging into the station sanitary sewer system. Maintain these conveniences at all times. Include provisions for pest control and elimination of odors. Government toilet facilities will not be available to Contractor's personnel.
3.3.7 Telephone
Make arrangements and pay all costs for telephone facilities desired.
3.3.8 Obstruction Lighting of Cranes
Provide a minimum of 2 aviation red or high intensity white obstruction lights on temporary structures (including cranes) over 100 feet above ground level. Light construction and installation must comply with FAA AC 70/7460-1. Lights must be operational during periods of reduced visibility, darkness, and as directed by the Contracting Officer.
3.3.9 Fire Protection
Provide temporary fire protection equipment for the protection of personnel and property during construction. Remove debris and flammable materials daily to minimize potential hazards.
3.4 TRAFFIC PROVISIONS
3.4.1 Maintenance of Traffic
a. Conduct operations in a manner that will not close any thoroughfare or interfere in any way with traffic on railways or highways except with written permission of the Contracting Officer at least 15 calendar days prior to the proposed modification date, and provide a Traffic Control Plan detailing the proposed controls to traffic movement for approval.
The plan must be in accordance with State and local regulations and the MUTCD, Part VI. Make all notifications and obtain any permits required for modification to traffic movements outside Station's jurisdiction..
Contractor may move oversized and slow-moving vehicles to the worksite provided requirements of the highway authority have been met.
b. Conduct work so as to minimize obstruction of traffic, and maintain traffic on at least half of the roadway width at all times. Obtain approval from the Contracting Officer prior to starting any activity that will obstruct traffic.
c. Provide, erect, and maintain, at contractors expense, lights, barriers, signals, passageways, detours, and other items, that may be required by the Life Safety Signage, overhead protection authority having jurisdiction.
3.4.2 Protection of Traffic
Maintain and protect traffic on all affected roads during the construction period except as otherwise specifically directed by the Contracting Officer. Measures for the protection and diversion of traffic, including the provision of watchmen and flagmen, erection of barricades, placing of lights around and in front of equipment the work, and the erection and maintenance of adequate warning, danger, and direction signs, will be as required by the State and local authorities having jurisdiction. Protect the traveling public from damage to person and property. Minimize the interference with public traffic on roads selected for hauling material to and from the site. Investigate the adequacy of existing roads and their allowable load limit. Contractor is responsible for the repair of any damage to roads caused by construction operations.
3.4.3 Rush Hour Restrictions
Do not interfere with the peak traffic flows preceding and during normal operations for construction without notification to and approval by the Contracting Officer.
3.4.4 Dust Control
Dust control methods and procedures must be approved by the Contracting Officer. Coordinate dust control methods with 01 57 19 TEMPORARY
ENVIRONMENTAL CONTROLS.
3.5 CONTRACTOR'S TEMPORARY FACILITIES
3.5.1 Quality Control Manager Records and Field Office
Provide on the jobsite an office with approximately 200 square feet of useful floor area for the exclusive use of the QC Manager. Provide a weathertight structure with adequate heating and cooling, toilet facilities, lighting, ventilation, a 4 by 8 foot plan table, a standard size office desk and chair, computer station, and working communications facilities. Provide a door with a cylinder lock and windows with locking hardware. Make utility connections. Locate as directed. File quality control records in the office and make available at all times to the Government. After completion of the work, remove the entire structure from the site.
3.5.2 Safety Systems
Protect the integrity of any installed safety systems or personnel safety devices. Obtain prior approval from Contracting Officer if entrance into systems serving safety devices is required. If it is temporarily necessary to remove or disable personnel safety devices in order to accomplish contract requirements, provide alternative means of protection prior to removing or disabling any permanently installed safety devices or equipment and obtain approval from the Contracting Officer.
3.5.3 Administrative Field Offices
Provide and maintain administrative field office facilities within the construction area at the designated site. Government office and warehouse facilities will not be available to the Contractor's personnel.
3.5.4 Storage Area
Construct a temporary 6 foot high chain link fence as shown on Sheet C-501 of the contract drawings around trailers and materials which are located outside the temporary construction fence installed along the limit of work.
Include plastic strip inserts within the chain link fabric or attach construction grade fence screening to the inside of the fabric (85% vision blockage minimum), colored green, so that visibility through the fence is obstructed. Screening shall be securely attached and shall be replaced if any tears or defects occur. Fence posts may be driven, in lieu of concrete bases, where soil conditions permit. Do not place or store trailers, materials, or equipment outside the fenced area unless such trailers, materials, or equipment are assigned a separate and distinct storage area by the Contracting Officer away from the vicinity of the construction site but within the installation boundaries. Trailers, equipment, or materials must not be open to public view with the exception of those items which are in support of ongoing work on any given day. Do not stockpile materials outside the fence in preparation for the next day's work. Park mobile equipment, such as tractors, wheeled lifting equipment, cranes, trucks, and like equipment within the fenced area at the end of each work day.
3.5.5 Not UsedSupplemental Storage Area
Upon request, and pending availability, the Contracting Officer will designate another or supplemental area for the use and storage of trailers, equipment, and materials. This area may not be in close proximity of the construction site but will be within the installation boundaries. The area will be maintained in an clean and orderly fashion and secured if needed to protect supplies and equipment. All materials to be stored in compliance with UFC 1-200-02 and ASHRAE 189.1-2017, as well as the LEEDv4 BD+C and TPC requirements for indoor air quality practices. Utilities will not be provided to this area by the Government.
3.5.6 Trailers and/or Storage Containers
a. Trailers or Storage Containers which are rusted, have peeling paint or are otherwise in need of repair will not be allowed on Installation property. Trailers must present a clean and neat exterior appearance and be in a state of good repair.
b. Maintain the temporary facilities. Failure to do so will be sufficient reason to require their removal.
3.5.7 Maintenance of Storage Area
a. Keep fencing in a state of good repair and proper alignment. Grassed or unpaved areas, which are not established roadways, and will be traversed with construction equipment or other vehicles, will be covered with a layer of gravel as necessary to prevent rutting and the tracking of mud onto paved or established roadways, should the Contractor elect to traverse them with construction equipment or other vehicles. Mow and maintain grass located within the boundaries of the construction site for the duration of the project. Grass and vegetation along fences, buildings, under trailers, and in areas not accessible to mowers will be edged or trimmed neatly.
3.5.8 Security Provisions
Provide adequate outside security lighting at the temporary facilities.
The Contractor will be responsible for the security of its own equipment.
3.5.9 Weather Protection of Temporary Facilities and Stored Materials
Take necessary precautions to ensure that roof openings and other critical openings in the building are monitored carefully. Take immediate actions required to seal off such openings when rain or other detrimental weather is imminent, and at the end of each workday. Ensure that the openings are completely sealed off to protect materials and equipment in the building from damage. All materials to be stored in compliance with UFC 1-200-02 and ASHRAE 189.1-2017, as well as the LEEDv4 BD+C and TPC requirements for indoor air quality practices.
3.5.9.1 Building and Site Storm Protection
When a warning of gale force winds is issued, take precautions to minimize danger to persons, and protect the work and nearby Government property.
Precautions must include, but are not limited to, closing openings;
removing loose materials, tools and equipment from exposed locations; and removing or securing scaffolding and other temporary work. Close openings in the work when storms of lesser intensity pose a threat to the work or any nearby Government property.
3.6 GOVERNMENT FIELD OFFICE
3.6.1 Resident Engineer's Office
Resident Engineer's Office Adjacent to the contractor's office facilities, the contractor shall provide a separate, securable, 12' x 65' office, with lights, communications, heat, AC and an operable restroom for exclusive use by the government. Within the office area there shall be 2 separate small offices (approximately 12 foot by 12 foot) at each end with a small separate storage area with metal shelving along the walls. Also, the following shall be provided: 4 each, desks with drawers and desk chairs on casters, 6 each, 4 drawer filing cabinets with locks, 1 each, plan table 3 each, four shelf shelving units (other than shelves in storage area).
Power and data sufficient for 6 computer workstations. 1 copier station with data and power (contractor to provide copier, Canon Super G3 high speed Image Runner 3320G with scan and e-mail capability, or equal). 1 water cooler with bottled water service. For the government office, for communications systems, the contractor is to provide wireless internet.
There will be no separate payment for any of the work included in this entire government office item. The contractor will not have access to the wireless internet provided under this requirement. The contractor is responsible for all costs associated with this item to include any monthly cost for the wireless internet, the copier/scanner/fax (and any servicing to the piece of equipment) or the water service. The contractor shall provide cleaning service of the trailer once per week. In addition to and separate from the above, for mutual use between the government and the contractor, a conference room shall be provided equipped with a conference table and seating to accommodate up to 15 people. Utility Services. The Contractor shall arrange for and pay all costs for water, electricity, liquefied petroleum or fuel oil, and other utilities as necessary for the field office. Clean and service equipment on an as needed basis. No separate payment will be made for maintaining the facilities and furnishing these utilities and costs in connection therewith shall be included in other items authorized for payment. Remove the buildings and facilities upon completion of the contract.
3.7 PLANT COMMUNICATIONS
Whenever the individual elements of the plant are located so that operation by normal voice between these elements is not satisfactory, install a satisfactory means of communication, such as telephone or other suitable devices and make available for use by Government personnel.
3.8 TEMPORARY PROJECT SAFETY FENCING
As soon as practicable, but not later than 15 days after the date established for commencement of work, furnish and erect temporary project safety fencing at the work site. Maintain the safety fencing during the life of the contract and, upon completion and acceptance of the work, removefrom the work site.
3.9 CLEANUP
Remove construction debris, waste materials, packaging material and the like from the work site daily. Any dirt or mud which is tracked onto paved or surfaced roadways must be cleaned away. Store any salvageable materials resulting from demolition activities within the fenced area described above or at the supplemental storage area. Neatly stack stored materials not in trailers, whether new or salvaged.
3.10 RESTORATION OF STORAGE AREA
Upon completion of the project remove the bulletin board, signs, barricades, haul roads, and any other temporary products from the site.
After removal of trailers, materials, and equipment from within the fenced area, remove the fence. Restore areas used during the performance of the contract to the original or better condition. Remove gravel used to traverse grassed areas and restore the area to its original condition, including top soil and seeding as necessary.
-- End of Section --
S2PRINT S2PRINT
SECTION 10 14 00.20
INTERIOR SIGNAGE
08/1704/23/2020
PART 1 GENERAL
This specification Section identifies Contractor sustainability requirements and procedures necessary to meet federally mandated High Performance and Sustainable Building (HPSB) goals and Guiding Principles (GP) Third Party Certification. In addition, this Project will submit for LEED v4 BD+C Silver Certification. Certification requirements include meeting UFC 1-200-02 requirements, LEED v4 BD+C Silver Certification requirements and all requirements of specification Section 01 33 29 - Sustainability Reporting, including maintaining and submitting the "LEED v4 materials attribute form" located in Section 01 33 29.
1.1 REFERENCES
The publications listed below form a part of this specification to the extent referenced. The publications are referred to in the text by basic designation only.
INTERNATIONAL CODE COUNCIL (ICC)
ICC A117.1 COMM (2017) Standard And Commentary Accessible and Usable Buildings and Facilities
NATIONAL FIRE PROTECTION ASSOCIATION (NFPA)
NFPA 101 (2018; TIA 18-1; TIA 18-2; TIA 18-3) Life Safety Code
U.S. DEPARTMENT OF DEFENSE (DOD)
UFC 1-200-02 (2016, with Change 1) High Performance and Sustainable Building Requirements
U.S. GREEN BUILDING COUNCIL (USGBC)
LEED v4 LEED, Leadership in Energy and Environmental Design
LEED v4 BD+C GBCI - Silver Certification Review
U.S. NATIONAL ARCHIVES AND RECORDS ADMINISTRATION (NARA)
36 CFR 1191 Americans with Disabilities Act (ADA) Accessibility Guidelines for Buildings and Facilities; Architectural Barriers Act (ABA) Accessibility Guidelines
1.2 SUBMITTALS
Government approval is required for submittals with a "G" designation;
submittals not having a "G" designation are for Contractor Quality Control approval. Submittals with an "S" are for inclusion in the Sustainability
SECTION 10 14 00.20 Page 1 eNotebook, in conformance to Section 01 33 29 SUSTAINABILITY REPORTING.
Submit the following in accordance with Section 01 33 00 SUBMITTAL
PROCEDURES:
SD-02 Shop Drawings
Detail Drawings; G, AE
SD-03 Product Data
Installation; G, RO
Warranty; G, RO
SD-04 Samples
Interior Signage; G, AE
Software; G, RO
SD-10 Operation and Maintenance Data
Approved Manufacturer's Instructions; G, RO
Protection and Cleaning; G, RO
1.3 EXTRA MATERIALS
Provide 10 extra frames and extra stock of the following: blank plates of each color and size for sign types S2 - Typical Permanent Room Sign.
Changeable message strips for sign type S1 - Typical Office Sign. Provide 100 paper inserts and one copy of the software for user produced signs and inserts after project completion and equipment necessary for removal of signage parts and pieces.
1.4 QUALITY ASSURANCE
1.4.1 Samples
Submit interior signage samples of each of the following sign types showing typical quality, workmanship and color: Typical Room Sign,Typical Office Sign (interchangeable), and Typical Stair Landing Sign (raised letter / braille). The samples may be installed in the work, provided each sample is identified and location recorded.
1.4.2 Detail Drawings
Submit detail drawings showing elevations of each type of sign, dimensions, details and methods of mounting or anchoring, mounting height, shape and thickness of materials, and details of construction. Include a schedule showing the location, each sign type, and message.
1.5 DELIVERY, STORAGE, AND HANDLING
Materials must be packaged to prevent damage and deterioration during shipment, handling, storage and installation. Product must be delivered to the jobsite in manufacturer's original packaging and stored in a clean, dry area in accordance with manufacturer's instructions.
SECTION 10 14 00.20 Page 2
1.6 WARRANTY
Warrant the interior signage for a period of 2 years against defective workmanship and material. Warranties must be signed by the authorized representative of the manufacturer. Submit warranty accompanied by the document authenticating the signer as an authorized representative of the guarantor. Guarantee that the signage products and the installation are free from any defects in material and workmanship from the date of delivery.
PART 2 PRODUCTS
2.1 STANDARD PRODUCTS
Signs, plaques, directories, and dimensional letters must be the standard product of a manufacturer regularly engaged in the manufacture of such products that essentially duplicate signs that have been in satisfactory use at least 2 years prior to bid opening. Obtain signage from a single manufacturer with edges and corners of finished letterforms and graphics true and clean.
2.2 STANDARD ROOM SIGNAGE, DIRECTIONAL SIGNAGE, AND BUILDING DIRECTORYROOM
IDENTIFICATION/DIRECTIONAL SIGNAGE SYSTEM
2.2.1 Standard Room Signs
Signs must consist of frameless laminated thermosetting Type MP plastic (three-ply melamine plastic laminate with phenolic core) and must conform to the following:
a. Display rails must be brushed aluminum (clear satin finish) with square
- edge beveled style corners.
b. Units must be frameless. Corners of signs must be squared - edge beveled.
2.2.2 Changeable Message Strip Signs
Changeable message strip signs must be of same construction as standard room signs to include a clear sleeve that will accept a paper or plastic insert identifying changeable text. The insert must be prepared typeset message mounted on paper card stock. Provide software for creating text and symbols for computers identified by owner for Owner production of paper inserts after project completion.
2.2.3 Type of Mounting For Signs
Provide extruded aluminum brackets for hanging, projecting, and double-sided signs. Mounting for framed, hanging, and projecting signs must be by mechanical fasteners. Surface mounted signs must be mounted with 1/16 inch thick closed cell vinyl foam with adhesive backing.
Adhesive must be transparent, long aging, high tech formulation on two sides of the vinyl foam. fabricated from materials that are not corrosive to sign material and mounting surface.
2.2.4 Graphics
Signage graphics for modular signs must conform to the following:
SECTION 10 14 00.20 Page 3
2.2.4.1 First Surface Copy Direct Print or Silkscreened (With Bonded Tactile Overlay Copy)
Message may be applied to panel using the silkscreen process. Silkscreened images must be executed with photo screens prepared from original art.
Handcut screens will not be accepted. Original art is defined as artwork that is a first generation reproduction of the specified art. Edges and corners must be clean.
2.2.4.2 Surface Applied Photopolymer
Integral graphics and Braille achieved by photomechanical stratification processes. Photopolymer used for ADA compliant graphics must be of the type that has a minimum durometer reading of 90. Tactile graphics must be raised 1/32 inch from the first surface of plaque by photomechanical stratification process.
2.2.5 Character Proportions and Heights
Letters and numbers on signs conform to 36 CFR 1191.
2.2.6 Tactile Letters, Symbols and Braille
Raised letters and numbers on signs must conform to 36 CFR 1191.
2.3 STAIR SIGNAGE: Types; SXX1, SXX2
Provide signs on stairs serving three or more stories with special signage within the enclosure at each floor landing conforming to NFPA 101.
Indicate the floor level, the terminus of the top and bottom of the stair enclosure, and the identification of the stair enclosure. Also, state the floor level of, and the direction to, exit discharge. Locate the signage inside the enclosure in a position that is visible when the door is in the open or closed position and install in conformance with 36 CFR 1191. The floor level designation must also be tactile in accordance with
ICC A117.1 COMM.
2.4 NOT USEDBUILDING DIRECTORIES
2.4.1 Electronic Directory System
Provide interactive electronic directory. Electronic directory system must be a complete turnkey system consisting of digital display, hardware, software connected through the local area network (LAN) to a server.
Electrical equipment must be UL listed and must comply with NFPA 70. Unit must be wall mounted.
2.5 COLOR, FINISH, AND CONTRAST
Color must be as indicated. Finish of all signs must be matte, or other non-glare finish as required in handicapped-accessible buildings.
2.6 TYPEFACE
ADA-ABA compliant font for Room Signs.
SECTION 10 14 00.20 Page 4
PART 3 EXECUTION
3.1 INSTALLATION
Signs must be installed plumb and true and in accordance with approved manufacturer's instructions at locations shown on the Contract Drawings;
see A-940 Series drawings. Submit six copies of operating instructions outlining the step-by-step procedures required for sign installation, upgrade and maintenance.. The instructions must include simplified diagrams for the system as installed, the manufacturer's name, model number, service manual, parts list, and brief description of all equipment. Mounting height and mounting location must conform to 36 CFR 1191. Required blocking must be installed. Signs on doors or other surfaces must not be installed until finishes on such surfaces have been installed. Signs installed on glass surfaces must be installed with matching blank back-up plates in accordance with manufacturer's instructions.
Do not install items that show visual evidence of biological growth.
3.1.1 Anchorage
Anchorage must be in accordance with approved manufacturer's instructions.
a. Signs mounted to painted gypsum board surfaces must be removable for painting maintenance.
b. Install signs mounted on fabric surfaces with hook and loop tape or pin mount.
3.1.2 Protection and Cleaning
Protect the work against damage during construction. Hardware and electrical equipment must be adjusted for proper operation. Glass, frames, and other sign surfaces must be cleaned at completion of sign installation in accordance with the manufacturer's approved instructions and the requirements of Section 01 78 23 OPERATION AND MAINTENANCE DATA, Package 1.
-- End of Section --