W912QR26RA016_Specs_Vol2-0000.pdf
PDF 4 MB Posted
- Solicitation number
- W912QR26RA016
About this file
This document is Volume 2 of 3 of the Certified Final Design Specifications for the Unaccompanied Enlisted Personnel Housing (UEPH) project at Fort Campbell, Kentucky, covering Divisions 02-22 of the construction specifications. The specifications establish comprehensive technical requirements for a Design-Bid-Build construction project involving demolition of existing structures and construction of new barracks to house 260 unaccompanied enlisted personnel.
The specifications detail requirements across multiple construction disciplines including demolition (Section 02), concrete work (Section 03), masonry (Section 04), structural and miscellaneous metals (Sections 05), wood and composites (Section 06), and thermal/moisture protection including insulation, air barriers, and flashing (Sections 07). Key technical specifications include concrete compressive strength minimums of 4,000 psi, structural steel fabrication by AISC-certified shops, spray foam insulation with R-value requirements, self-adhering and fluid-applied air barrier systems meeting ASTM E2357 standards, and spray-applied fireproofing. Materials specified include reinforced concrete, structural steel, brick and masonry units, gypsum board, rigid board insulation with recycled content requirements, stainless steel and galvanized metal flashing, and various roofing components. Quality assurance requirements mandate third-party inspection, field testing protocols, air barrier commissioning per ASTM standards, and manufacturer certifications for critical systems including welding, concrete testing, and thermal barrier installations. The specifications incorporate sustainability requirements including recycled material content minimums, energy efficiency standards per UFC 1-200-02, and compliance with DoD Minimum Antiterrorism standards for building construction.
View the file
Other files
Show all 13
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Solicitation For
UNACCOMPANIED ENLISTED
PERSONNEL HOUSING (UEPH)
FORT CAMPBELL, KY
P2: 511686
Design-Bid-Build
Specifications - Vol 2 of 3 (Div 02-22) Certified Final Design
13 March 2026
W912QR26RA016
RRS-A: 200A Disposition: Maintain for 15 yrs after construction.
W912QR26RA016_Specs_Vol2-0000
P2 511686 UEPH
Fort Campbell, KY
PROJECT TABLE OF CONTENTS
DIVISION 00 - PROCUREMENT AND CONTRACTING REQUIREMENTS
00 80 00.00 06 04/21, CHG 1: 06/23 SPECIAL PROVISIONS
DIVISION 01 - GENERAL REQUIREMENTS
01 11 00 02/24, CHG 1: 05/25 SUMMARY OF WORK
01 32 01.00 06 10/23 PROJECT SCHEDULE
01 33 00 08/18, CHG 4: 02/21 SUBMITTAL PROCEDURES
01 33 29.00 06 11/17 SUSTAINABILITY REPORTING
01 35 26.00 06 05/24 CHG 1: 10/24 GOVERNMENT SAFETY REQUIREMENTS
01 42 00 05/24 SOURCES FOR REFERENCE PUBLICATIONS
01 45 00.15 10 11/23 RESIDENT MANAGEMENT SYSTEM CONTRACTOR
MODE (RMS CM)
01 45 04.10 06 05/25 CONTRACTOR QUALITY CONTROL
01 45 35 05/24 SPECIAL INSPECTIONS
01 50 00 11/20, CHG 3: 08/24 TEMPORARY CONSTRUCTION FACILITIES AND
CONTROLS
01 57 19.00 06 04/20 TEMPORARY ENVIRONMENTAL CONTROLS AND
PERMITS
01 74 19 02/19, CHG 3: 11/21 CONSTRUCTION WASTE MANAGEMENT AND
DISPOSAL
01 78 23 05/23, CHG 1: 05/25 OPERATION AND MAINTENANCE DATA
01 91 00.15 05/23, CHG 3: 08/24 BUILDING COMMISSIONING
01 91 19 05/2023 BUILDING ENCLOSURE COMMISSIONING
DIVISION 02 - EXISTING CONDITIONS
02 41 00 08/22 DEMOLITION
DIVISION 03 - CONCRETE
03 30 00 02/19, CHG 8: 05/24 CAST-IN-PLACE CONCRETE
DIVISION 04 - MASONRY
04 20 00 11/15, CHG 2: 05/19 UNIT MASONRY
DIVISION 05 - METALS
05 05 20 05/22 POST-INSTALLED CONCRETE AND MASONRY
ANCHORS
05 05 23.16 08/18 STRUCTURAL WELDING
05 12 00 08/18, CHG 2: 05/21 STRUCTURAL STEEL
05 30 00 05/15, CHG 2: 08/18 STEEL DECKS
05 40 00 05/15, CHG 1: 08/18 COLD-FORMED METAL FRAMING
05 50 13 05/17, CHG 1: 08/18 MISCELLANEOUS METAL FABRICATIONS
05 51 00 02/17, CHG 1: 05/17 METAL STAIRS
05 51 33 02/16, CHG 2: 02/18 METAL LADDERS
05 52 00 02/18, CHG 1: 02/20 METAL RAILINGS
DIVISION 06 - WOOD, PLASTICS, AND COMPOSITES
06 10 00 08/16, CHG 3: 05/25 ROUGH CARPENTRY
06 41 16.00 10 08/25 PLASTIC-LAMINATE-CLAD ARCHITECTURAL
CABINETS
06 61 16 08/20 SOLID SURFACING FABRICATIONS
PROJECT TABLE OF CONTENTS Page 1
CERTIFIED FINAL
SPECIFICATIONS VOLUME 1 OF 3
SPECIFICATIONS VOLUME 2 OF 3
DIVISION 07 - THERMAL AND MOISTURE PROTECTION
07 21 13 08/23 BOARD INSULATION
07 22 00 08/23 ROOF AND DECK INSULATION
07 27 10 08/23 BUILDING AIR BARRIER SYSTEM
07 27 19.01 08/23, CHG 1: 08/24 SELF-ADHERING AIR BARRIERS
07 27 26 08/23 FLUID-APPLIED MEMBRANE AIR BARRIERS
07 27 36 08/23 SPRAY FOAM INSULATION
07 60 00 08/23 FLASHING AND SHEET METAL
07 61 14.00 20 08/16, CHG 1: 08/18 STEEL STANDING SEAM ROOFING
07 84 00 05/10, CHG 1: 08/13 FIRESTOPPING
07 92 00 08/23 JOINT SEALANTS
DIVISION 08 - OPENINGS
08 11 13 08/20 STEEL DOORS AND FRAMES
08 11 16 05/17, CHG 2: 11/18 ALUMINUM DOORS AND FRAMES
08 14 00 08/16, CHG 1: 08/18 WOOD DOORS
08 31 00 05/17, CHG 1: 08/18 ACCESS DOORS AND PANELS
08 41 13 08/18, CHG 1: 08/18 ALUMINUM-FRAMED ENTRANCES AND
STOREFRONTS
08 44 00 05/19 CURTAIN WALL AND GLAZED ASSEMBLIES
08 51 13 05/19 ALUMINUM WINDOWS
08 71 00 02/16, CHG 4: 02/22 DOOR HARDWARE
08 81 00 05/19 GLAZING
DIVISION 09 - FINISHES
09 22 00 02/10, CHG 2: 08/18 SUPPORTS FOR GYPSUM BOARD
09 29 00 08/16, CHG 4: 02/20 GYPSUM BOARD
09 30 10 08/20 CERAMIC, QUARRY, AND GLASS TILING
09 51 00 08/20 ACOUSTICAL CEILINGS
09 62 38 08/17, CHG 1: 08/18 STATIC-CONTROL FLOORING
09 65 00 11/24 RESILIENT FLOORING
09 65 66 08/16, CHG 1: 08/18 RESILIENT ATHLETIC FLOORING
09 90 00 02/21 PAINTS AND COATINGS
DIVISION 10 - SPECIALTIES
10 14 00.10 08/17, CHG 1: 11/18 EXTERIOR SIGNAGE
10 14 00.20 08/20 INTERIOR SIGNAGE
10 26 00 08/20 WALL AND DOOR PROTECTION
10 28 13 08/20 TOILET ACCESSORIES
10 44 16 11/19 FIRE EXTINGUISHERS
DIVISION 12 - FURNISHINGS
12 21 00 08/17, CHG 2: 11/18 WINDOW BLINDS
12 48 13 08/23 ENTRANCE FLOOR MATS AND FRAMES
DIVISION 13 - SPECIAL CONSTRUCTION
13 48 73 05/25 SEISMIC CONTROL FOR NONSTRUCTURAL
COMPONENTS
DIVISION 14 - CONVEYING EQUIPMENT
14 21 23 05/16, CHG 1: 05/18 ELECTRIC TRACTION PASSENGER ELEVATORS
PROJECT TABLE OF CONTENTS Page 2
CERTIFIED FINAL
DIVISION 21 - FIRE SUPPRESSION
21 12 00 05/11 STANDPIPE SYSTEMS
21 13 13 08/20 WET PIPE SPRINKLER SYSTEMS, FIRE
PROTECTION
21 30 00 04/08, CHG 1: 08/13 FIRE PUMPS
DIVISION 22 - PLUMBING
22 00 00 05/24 PLUMBING, GENERAL PURPOSE
22 31 03 05/25 DOMESTIC WATER SOFTENERS AND WATER
CONDITIONERS
DIVISION 23 - HEATING, VENTILATING, AND AIR CONDITIONING (HVAC)
23 03 00 11/25 BASIC MECHANICAL MATERIALS AND METHODS
23 05 48.19 05/18, CHG 2: 08/20 SEISMIC BRACING FOR HVAC
23 05 93 05/25 TESTING, ADJUSTING, AND BALANCING FOR
HVAC
23 07 00 08/24 THERMAL INSULATION FOR MECHANICAL
SYSTEMS
23 08 00 05/23, CHG 1: 08/24 COMMISSIONING OF MECHANICAL AND
PLUMBING SYSTEMS
23 09 00 08/24 INSTRUMENTATION AND CONTROL FOR HVAC
23 09 13 11/15 INSTRUMENTATION AND CONTROL DEVICES
FOR HVAC
23 09 23.02 08/24 BACNET DIRECT DIGITAL CONTROL FOR HVAC
AND OTHER BUILDING CONTROL SYSTEMS
23 21 23 05/25 HYDRONIC PUMPS
23 30 00 02/25 HVAC AIR DISTRIBUTION
23 64 10 05/25 WATER CHILLERS, VAPOR COMPRESSION TYPE
23 64 26 08/09, CHG 5: 11/19 CHILLED, CHILLED-HOT, AND CONDENSER
WATER PIPING SYSTEMS
23 74 33 05/24 DEDICATED OUTDOOR AIR SYSTEMS (DOAS)
DIVISION 25 - INTEGRATED AUTOMATION
25 05 11.01 08/24 CYBERSECURITY FOR FACILITY-RELATED
CONTROL SYSTEMS - FIRE ALARM
25 05 11.02 05/21 CYBERSECURITY FOR FACILITY-RELATED
CONTROL SYSTEMS - HVAC
25 08 10 05/21 UTILITY MONITORING AND CONTROL SYSTEM
TESTING
25 10 10 02/19, CHG 1: 05/21 UTILITY MONITORING AND CONTROL SYSTEM
(UMCS) FRONT END AND INTEGRATION
DIVISION 26 - ELECTRICAL
26 05 48.00 10 10/07 SEISMIC PROTECTION FOR ELECTRICAL
EQUIPMENT
26 05 73 08/23 POWER SYSTEM STUDIES
26 08 00 11/22 APPARATUS INSPECTION AND TESTING
26 20 00 08/23 INTERIOR DISTRIBUTION SYSTEM
26 23 00 05/15, CHG 2: 11/19 LOW-VOLTAGE SWITCHGEAR
26 24 13 08/21 SWITCHBOARDS
26 28 01.00 10 08/21 COORDINATED POWER SYSTEM PROTECTION
26 29 23 02/20, CHG 1: 05/21 ADJUSTABLE SPEED DRIVE (ASD) SYSTEMS
UNDER 600 VOLTS
PROJECT TABLE OF CONTENTS Page 3
CERTIFIED FINAL
SPECIFICATIONS VOLUME 3 OF 3
26 41 00 08/23 LIGHTNING PROTECTION SYSTEM
26 51 00 05/20, CHG 2: 11/21 INTERIOR LIGHTING
26 56 00 08/21 EXTERIOR LIGHTING
DIVISION 27 - COMMUNICATIONS
27 10 00 08/11 BUILDING TELECOMMUNICATIONS CABLING
SYSTEM
DIVISION 28 - ELECTRONIC SAFETY AND SECURITY
28 31 76 08/20 INTERIOR FIRE ALARM AND MASS
NOTIFICATION SYSTEM, ADDRESSABLE
DIVISION 31 - EARTHWORK
31 00 00.00 06 05/24 EARTHWORK
31 05 19.13 06 05/24 GEOTEXTILES FOR EARTHWORK
31 21 13 11/18 RADON MITIGATION
31 63 26.00 06 08/25 DRILLED SHAFTS
DIVISION 32 - EXTERIOR IMPROVEMENTS
32 01 19.61 11/19 SEALING OF JOINTS IN RIGID PAVEMENT
32 11 23 05/22 AGGREGATE BASE COURSE
32 11 23.23 08/22 BASE COURSE DRAINAGE LAYERS
32 13 13.06 06 06/18 PORTLAND CEMENT CONCRETE PAVEMENT FOR
ROADS AND SITE FACILITIES
32 16 19 05/18 CONCRETE CURBS, GUTTERS AND SIDEWALKS
32 17 23 08/16, CHG 5: 11/18 PAVEMENT MARKINGS
32 92 19 08/17, CHG 1: 08/21 SEEDING
32 93 00 08/17, CHG 1: 08/21 EXTERIOR PLANTS
DIVISION 33 - UTILITIES
33 11 00 02/18, CHG 2: 11/23 WATER UTILITY DISTRIBUTION PIPING
33 30 00 05/18 SANITARY SEWERAGE
33 40 00 11/21 STORMWATER UTILITIES
33 46 16 05/18 SUBDRAINAGE PIPING
33 71 02 08/21 UNDERGROUND ELECTRICAL DISTRIBUTION
33 82 00 04/06 TELECOMMUNICATIONS OUTSIDE PLANT (OSP)
-- End of Project Table of Contents --
PROJECT TABLE OF CONTENTS Page 4
SECTION TABLE OF CONTENTS
DIVISION 02 - EXISTING CONDITIONS
SECTION 02 41 00
DEMOLITION
08/22
PART 1 GENERAL
1.1 REFERENCES
1.2 PROJECT DESCRIPTION
1.2.1 Definitions
1.2.1.1 Demolition
1.2.1.2 Deconstruction
1.2.1.3 Demolition Plan
1.2.1.4 Deconstruction Plan
1.2.2 Demolition/Deconstruction Plan
1.2.3 General Requirements
1.3 ITEMS TO REMAIN IN PLACE
1.3.1 Existing Construction Limits and Protection
1.3.2 Weather Protection
1.3.3 Utility Service
1.3.4 Facilities
1.4 BURNING
1.5 SUBMITTALS
1.6 QUALITY ASSURANCE
1.6.1 Dust and Debris Control
1.7 PROTECTION
1.7.1 Traffic Control Signs
1.7.2 Protection of Personnel
1.8 EXISTING CONDITIONS
PART 2 PRODUCTS
2.1 FILL MATERIAL
PART 3 EXECUTION
3.1 EXISTING FACILITIES TO BE REMOVED
3.1.1 Structures
3.1.2 Utilities and Related Equipment
3.1.2.1 General Requirements
3.1.2.2 Disconnecting Existing Utilities
3.1.3 Paving and Slabs
3.1.4 Concrete
3.1.5 Structural Steel
3.1.6 Miscellaneous Metal
3.1.7 Carpentry
3.1.8 Carpet
3.1.9 Acoustic Ceiling Tile
3.1.10 Patching
3.1.11 Cylinders and Canisters
3.1.12 Locksets on Swinging Doors
SECTION 02 41 00 Page 1
3.1.13 Mechanical Equipment and Fixtures
3.1.13.1 Preparation for Storage
3.1.13.2 Piping
3.1.13.3 Ducts
3.1.13.4 Fixtures, Motors and Machines
3.1.14 Electrical Equipment and Fixtures
3.1.14.1 Fixtures
3.1.14.2 Electrical Devices
3.1.14.3 Wiring Ducts or Troughs
3.1.14.4 Conduit and Miscellaneous Items
3.1.15 Elevators and Hoists
3.2 CONCURRENT EARTH-MOVING OPERATIONS
3.3 DISPOSITION OF MATERIAL
3.3.1 Title to Materials
3.3.2 Reuse of Materials and Equipment
3.3.3 Disposal of Ozone Depleting Substance (ODS)
3.3.3.1 Special Instructions
3.3.3.2 Fire Suppression Containers
3.3.4 Transportation Guidance
3.3.5 Unsalvageable and Non-Recyclable Material
3.4 CLEANUP
3.5 DISPOSAL OF REMOVED MATERIALS
3.5.1 Regulation of Removed Materials
3.5.2 Burning on Government Property
3.5.3 Removal to Spoil Areas on Government Property
3.5.4 Removal from Government Property
3.6 REUSE OF SALVAGED ITEMS
-- End of Section Table of Contents --
SECTION 02 41 00 Page 2
SECTION 02 41 00
DEMOLITION
08/22
PART 1 GENERAL
1.1 REFERENCES
The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.
AIR-CONDITIONING, HEATING AND REFRIGERATION INSTITUTE (AHRI)
AHRI Guideline K (2009) Guideline for Containers for Recovered Non-Flammable Fluorocarbon Refrigerants
AMERICAN ASSOCIATION OF STATE HIGHWAY AND TRANSPORTATION OFFICIALS
(AASHTO)
AASHTO M 145 (1991; R 2012) Standard Specification for Classification of Soils and Soil-Aggregate Mixtures for Highway Construction Purposes
AASHTO T 180 (2017) Standard Method of Test for Moisture-Density Relations of Soils Using a 4.54-kg (10-lb) Rammer and a 457-mm (18-in.) Drop
AMERICAN SOCIETY OF SAFETY PROFESSIONALS (ASSP)
ASSP A10.6 (2006) Safety & Health Program Requirements for Demolition Operations - American National Standard for Construction and Demolition Operations
ASTM INTERNATIONAL (ASTM)
ASTM D2487 (2017; E 2020) Standard Practice for Classification of Soils for Engineering Purposes (Unified Soil Classification System)
CARPET AND RUG INSTITUTE (CRI)
CRI 104 (2015) Carpet Installation Standard for Commercial Carpet
CRI 105 (2015) Carpet Installation Standard for Residential Carpet
U.S. ARMY CORPS OF ENGINEERS (USACE)
EM 385-1-1 (2014) Safety -- Safety and Health Requirements Manual
SECTION 02 41 00 Page 3
U.S. DEFENSE LOGISTICS AGENCY (DLA)
DLA 4145.25 (Jun 2000; Reaffirmed Oct 2010) Storage and Handling of Liquefied and Gaseous Compressed Gases and Their Full and Empty Cylinders;
https://www.dla.mil/Portals/104/Documents/DispositionServices /ddsr/docs/cylinderjointpub.pdf
U.S. DEPARTMENT OF DEFENSE (DOD)
DOD 4000.25-1-M (2006) MILSTRIP - Military Standard Requisitioning and Issue Procedures
MIL-STD-129 (2014; Rev R; Change 1 2018; Change 2 2019) Military Marking for Shipment and Storage
U.S. FEDERAL AVIATION ADMINISTRATION (FAA)
FAA AC 70/7460-1 (2016; Rev L; Change 2) Obstruction Marking and Lighting
U.S. NATIONAL ARCHIVES AND RECORDS ADMINISTRATION (NARA)
40 CFR 61 National Emission Standards for Hazardous Air Pollutants
40 CFR 82 Protection of Stratospheric Ozone
49 CFR 173.301 Shipment of Compressed Gases in Cylinders and Spherical Pressure Vessels
1.2 PROJECT DESCRIPTION
1.2.1 Definitions
1.2.1.1 Demolition
Demolition is the process of tearing apart and removing any feature of a facility together with any related handling and disposal operations.
1.2.1.2 Deconstruction
Deconstruction is the process of taking apart a facility with the primary goal of preserving the value of all useful building materials.
1.2.1.3 Demolition Plan
Demolition Plan is the planned steps and processes for managing demolition activities and identifying the required sequencing activities and disposal mechanisms.
1.2.1.4 Deconstruction Plan
Deconstruction Plan is the planned steps and processes for dismantling all or portions of a structure or assembly, to include managing sequencing activities, storage, re-installation activities, salvage and disposal
SECTION 02 41 00 Page 4 mechanisms.
1.2.2 Demolition/Deconstruction Plan
Prepare a Demolition Plan and submit proposed demolition and removal procedures for approval before work is started. Include in the plan procedures for careful removal and disposition of materials specified to be salvaged, coordination with other work in progress, a disconnection schedule of utility services with a detailed description of methods and equipment to be used for each operation and of the sequence of operations.
Coordinate with Waste Management Plan in accordance with Section 01 74 19 CONSTRUCTION WASTE MANAGEMENT AND DISPOSAL. Include statements affirming Contractor inspection of the existing roof deck and its suitability to perform as a safe working platform or if inspection reveals a safety hazard to workers, state provisions for securing the safety of the workers throughout the performance of the work. Provide procedures for safe conduct of the work in accordance with EM 385-1-1 . Plan must be approved by Structural PE prior to work beginning. Contractor to coordinate with the COR prior to demolishing arms vault structures from site to confirm all arms / munitions have been removed from the vaults.
1.2.3 General Requirements
Do not begin demolition or deconstruction until authorization is received from the Contracting Officer. Remove rubbish and debris from the project site; do not allow accumulations inside or outside the buildings. The work includes demolition, and removal of resulting rubbish and debris. Remove rubbish and debris from Government property daily, unless otherwise directed. Store materials that cannot be removed daily in areas specified by the Contracting Officer. In the interest of occupational safety and health, perform the work in accordance with EM 385-1-1 , Section 23, Demolition, and other applicable Sections.
1.3 ITEMS TO REMAIN IN PLACE
Comply with FAR 52.236-9 to protect existing vegetation, structures, equipment, utilities, and improvements. Coordinate the work of this section with all other work indicated. Construct and maintain shoring, bracing, and supports as required. Ensure that structural elements are not overloaded. Increase structural supports or add new supports as may be required as a result of any cutting, removal, deconstruction, or demolition work performed under this contract. Do not overload structural elements and/or pavements to remain. Repairs, reinforcement, or structural replacement require approval by the Contracting Officer prior to performing such work.
1.3.1 Existing Construction Limits and Protection
Do not disturb existing construction beyond the extent indicated or necessary for installation of new construction. Provide temporary shoring and bracing for support of building components to prevent settlement or other movement. Provide protective measures to control accumulation and migration of dust and dirt in all work areas. Remove snow, dust, dirt, and debris from work areas daily.
1.3.2 Weather Protection
For portions of the building to remain, protect building interior and materials and equipment from the weather at all times. Where removal of
SECTION 02 41 00 Page 5 existing roofing is necessary to accomplish work, have materials and workmen ready to provide adequate and temporary covering of exposed areas.
1.3.3 Utility Service
Maintain existing utilities indicated to stay in service and protect against damage during demolition and deconstruction operations. Prior to start of work, the Contractor must coordinate utility work with the COR and Utility provider. There are existing water mains and sanitary sewer gravity and force mains that run through the site. Jacobs (water and sewer utility provider) is to construct the new water and sanitary sewer force and gravity mains that traverse the site and connect all proposed utilities to the existing mains along with demolishing existing utilities to be taken out of service.
1.3.4 Facilities
Protect electrical and mechanical services and utilities. Where removal of existing utilities and pavement is specified or indicated, provide approved barricades, temporary covering of exposed areas, and temporary services or connections for electrical and mechanical utilities. Floors, roofs, walls, columns, pilasters, and other structural components that are designed and constructed to stand without lateral support or shoring, and are determined to be in stable condition, must remain standing without additional bracing, shoring, or lateral support until demolished or deconstructed, unless directed otherwise by the Contracting Officer.
Ensure that no elements determined to be unstable are left unsupported and place and secure bracing, shoring, or lateral supports as may be required as a result of any cutting, removal, deconstruction, or demolition work performed under this contract.
1.4 BURNING
The use of burning at the project site for the disposal of refuse and debris will not be permitted.
1.5 SUBMITTALS
Government approval is required for submittals with a "G" or "S" classification. Submittals not having a "G" or "S" classification are for information only. When used, a code following the "G" classification identifies the office that will review the submittal for the Government.
Submit the following in accordance with Section 01 33 00 SUBMITTAL
PROCEDURES:
SD-01 Preconstruction Submittals
Demolition Plan; G , RO
Existing Conditions
SD-07 Certificates
Notification; G , RO
SD-11 Closeout Submittals
SECTION 02 41 00 Page 6
Receipts
1.6 QUALITY ASSURANCE
Submit timely notification of demolition projects to Federal, State, regional, and local authorities in accordance with 40 CFR 61 , Subpart M.
Notify the State's environmental protection agency and the Contracting Officer in writing 10 working days prior to the commencement of work in accordance with 40 CFR 61 , Subpart M. Comply with federal, state, and local hauling and disposal regulations. In addition to the requirements of the "Contract Clauses," conform to the safety requirements contained in ASSP A10.6 . Comply with the Environmental Protection Agency requirements specified. Use of explosives will not be permitted.
1.6.1 Dust and Debris Control
Prevent the spread of dust and debris and avoid the creation of a nuisance or hazard in the surrounding area. Do not use water if it results in hazardous or objectionable conditions such as, but not limited to, ice, flooding, or pollution. Sweep pavements as often as necessary to control the spread of debris that may result in foreign object damage potential to vehicles or personnel in the area.
1.7 PROTECTION
1.7.1 Traffic Control Signs
a. Where pedestrian and driver safety is endangered in the area of removal work, use traffic barricades with flashing lights. Anchor barricades in a manner to prevent displacement by wind. Notify the Contracting Officer prior to beginning such work.
Provide a minimum of 2 FAA type L-810 steady burning red obstruction lights on temporary structures (including cranes) over 100 feet, but less than 200 ft, above ground level. The use of LED based obstruction lights are not permitted. For temporary structures (including cranes) over 200 ft above ground level provide obstruction lighting in accordance with FAA AC 70/7460-1 . Perform light construction and installation in compliance with FAA AC 70/7460-1 .
Lights must be operational during periods of reduced visibility, darkness, and as directed by the Contracting Officer. Maintain the temporary services during the period of construction and remove only after permanent services have been installed and tested and are in operation.
1.7.2 Protection of Personnel
Before, during and after the demolition work continuously evaluate the condition of the site specific features and structures being demolished and take immediate action to protect all personnel working in and around the project site. No area, section, or component of floors, roofs, walls, columns, pilasters, or other structural element will be allowed to be left standing without sufficient bracing, shoring, or lateral support to prevent collapse or failure while workmen remove debris or perform other work in the immediate area.
SECTION 02 41 00 Page 7
1.8 EXISTING CONDITIONS
Before beginning any demolition or deconstruction work, survey the site and examine the drawings and specifications to determine the extent of the work. Record existing conditions in the presence of the Contracting Officer or the Contracting Officer's Representative showing the condition of structures and other facilities adjacent to areas of alteration or removal. Photographs or electronic images with a minimum resolution of 3072 x 2304 pixels, capable of a print resolution of 300 dpi, will be acceptable as a record of existing conditions. Include in the record the elevation of the top of foundation walls, finish floor elevations, possible conflicting electrical conduits, plumbing lines, alarms systems, the location and extent of existing cracks and other damage and description of surface conditions that exist prior to starting work. It is the Contractor's responsibility to verify and document all required outages which will be required during the course of work, and to note these outages on the record document. Submit survey results to the Contracting Officer or the Contracting Officer's Representative.
PART 2 PRODUCTS
2.1 FILL MATERIAL
a. Comply with excavating, backfilling, and compacting procedures for soils used as backfill material to fill basements, voids, depressions or excavations resulting from demolition or deconstruction of structures.
b. Provide fill material conforming to the definition of satisfactory soil material as defined in ASTM D2487 and AASHTO M 145, Soil Classification Groups A-1, A-2-4, A-2-5 and A-3. In addition, fill material must be free from roots and other organic matter, trash, debris, frozen materials, and stones larger than 2 inches in any dimension.
c. Proposed fill material must be sampled and tested by an approved soil testing laboratory, as follows:
Soil classification AASHTO M 145
Moisture-density relations AASHTO T 180 , Method B or D
PART 3 EXECUTION
3.1 EXISTING FACILITIES TO BE REMOVED
Inspect and evaluate existing structures onsite for reuse. Disassemble existing construction scheduled to be removed for reuse. Dismantled and removed materials are to be separated, set aside, and prepared as specified, and stored or delivered to a collection point for reuse, remanufacture, recycling, or other disposal, as specified. Designate materials for reuse onsite whenever possible.
3.1.1 Structures
a. Remove existing structures indicated to be removed including foundations. Contractor must fill foundation holes to provide positive
SECTION 02 41 00 Page 8 drainage to sediment basins and other erosion control measures.
Remove pavements, sidewalks, curbs, gutters and street light bases as indicated.
b. Demolish structures in a systematic manner from the top of the structure to the ground. Complete demolition work above each tier or floor before the supporting members on the lower level are disturbed.
Demolish concrete and masonry walls in small sections. Remove structural framing members and lower to ground by means of derricks, platforms hoists, or other suitable methods as approved by the Contracting Officer.
c. Locate demolition and deconstruction equipment throughout the structure and remove materials so as to not impose excessive loads to supporting walls, floors, or framing.
d. Building, or the remaining portions thereof, not exceeding 80 feet in height may be demolished by the mechanical method of demolition.
3.1.2 Utilities and Related Equipment
3.1.2.1 General Requirements
Do not interrupt existing utilities serving occupied or used facilities, except when authorized in writing by the Contracting Officer. Do not interrupt existing utilities serving facilities occupied and used by the Government except when approved in writing and then only after temporary utility services have been approved and provided. Do not begin demolition or deconstruction work until all utility disconnections have been made.
Shut off and cap utilities for future use, as indicated.
3.1.2.2 Disconnecting Existing Utilities
Remove existing utilities , as indicated or uncovered by work and terminate in a manner conforming to the nationally recognized code covering the specific utility and approved by the Contracting Officer. Do not remove existing utilities that are to be demolished by the utility provider unless expressly ordered to do so by the utility provider. When utility lines are encountered but are not indicated on the drawings, notify the Contracting Officer prior to further work in that area. Remove meters and related equipment and deliver to a location in accordance with instructions of the Contracting Officer.
3.1.3 Paving and Slabs
Remove concrete and asphaltic concrete paving and slabs including aggregate base as indicated to a depth of 8 inches below existing adjacent grade. Provide neat sawcuts at limits of pavement removal as indicated.
Remove pavement and slabs not to be used in this project from the installation at Contractor's expense.
3.1.4 Concrete
Saw concrete along straight lines to a depth of a minimum 2 inch. Make each cut in walls perpendicular to the face and in alignment with the cut in the opposite face. Break out the remainder of the concrete provided that the broken area is concealed in the finished work, and the remaining concrete is sound. At locations where the broken face cannot be concealed, grind smooth or saw cut entirely through the concrete. Sawcuts
SECTION 02 41 00 Page 9 in existing concrete sidewalk must be at the nearest existing expansion joint or weakened plane joint and at full depth.
3.1.5 Structural Steel
Dismantle structural steel at field connections and in a manner that will prevent bending or damage. Salvage for recycle structural steel, steel joists, girders, angles, plates, columns and shapes. Flame-cutting torches are permitted when other methods of dismantling are not practical.
Transport steel joists and girders as whole units and not dismantled.
Transport structural steel shapes to a designated area as directed by the Contracting Officer, stacked according to size, type of member and length, and stored off the ground, protected from the weather.
3.1.6 Miscellaneous Metal
Salvage shop-fabricated items such as access doors and frames, steel gratings, metal ladders, wire mesh partitions, metal railings, metal windows and similar items as whole units. Salvage light-gage and cold-formed metal framing, such as steel studs, steel trusses, metal gutters, roofing and siding, metal toilet partitions, toilet accessories and similar items. Scrap metal is the Contractor's property. Recycle scrap metal as part of demolition and deconstruction operations. Provide separate containers to collect scrap metal and transport to a scrap metal collection or recycling facility, in accordance with the Waste Management Plan.
3.1.7 Carpentry
Salvage for recycle lumber, millwork items, and finished boards, and sort by type and size. windows, doors, frames, and cabinets, and similar items as whole units, complete with trim and accessories. Brace the open end of door frames to prevent damage.
3.1.8 Carpet
Remove existing carpet for reclamation in accordance with manufacturer recommendations and as follows. Remove used carpet in large pieces, roll tightly, and pack neatly in a container. Remove adhesive according to recommendations of the Carpet and Rug Institute (CRI). Provide adhesive removal solvents in compliance with CRI 104 / CRI 105 . Recycle removed carpet cushion.
3.1.9 Acoustic Ceiling Tile
Remove, neatly stack, and recycle acoustic ceiling tiles. Recycling may be available with manufacturer. Otherwise, give priority to a local recycling organization. Recycling is not required if the tiles contain or may have been exposed to asbestos material.
3.1.10 Patching
Where removals leave holes and damaged surfaces exposed in the finished work, patch and repair these holes and damaged surfaces to match adjacent finished surfaces, using on-site materials when available. Where new work is to be applied to existing surfaces, perform removals and patching in a manner to produce surfaces suitable for receiving new work. Make finished surfaces of patched area flush with the adjacent existing surface and match the existing adjacent surface as closely as possible to texture and
SECTION 02 41 00 Page 10 finish. Provide patching as specified and indicated, and include the following:
a. Concrete and Masonry: Completely fill holes and depressions, left as a result of removals in existing masonry walls to remain, with an approved masonry patching material, applied in accordance with the manufacturer's printed instructions.
b. Where existing partitions have been removed leaving damaged or missing resilient tile flooring, patch to match the existing floor tile.
c. Patch acoustic lay-in ceiling where partitions have been removed. Make the transition between the different ceiling heights by continuing the higher ceiling level over to the first runner on the lower ceiling and closing the vertical opening with a painted sheet metal strip.
3.1.11 Cylinders and Canisters
Remove all fire suppression system cylinders and canisters and dispose of in accordance with the paragraph entitled "Disposal of Ozone Depleting Substance (ODS)."
3.1.12 Locksets on Swinging Doors
Remove all locksets from all swinging doors indicated to be removed and disposed of. Deliver the locksets and related items to a designated location for receipt by the Contracting Officer after removal.
3.1.13 Mechanical Equipment and Fixtures
Disconnect mechanical hardware at the nearest connection to existing services to remain, unless otherwise noted. Disconnect mechanical equipment and fixtures at fittings. Remove service valves attached to the unit. Salvage each item of equipment and fixtures as a whole unit;
listed, indexed, tagged, and stored. Salvage each unit with its normal operating auxiliary equipment. Transport salvaged equipment and fixtures, including motors and machines, to a designated storage area as directed by the Contracting Officer. Do not remove equipment until approved. Do not offer low-efficiency equipment for reuse; provide to recycling service for disassembly and recycling of parts.
3.1.13.1 Preparation for Storage
Remove water, dirt, dust, and foreign matter from units; drain tanks, piping and fixtures; if previously used to store flammable, explosive, or other dangerous liquids, steam clean interiors. Seal openings with caps, plates, or plugs. Secure motors attached by flexible connections to the unit. Change lubricating systems with the proper oil or grease.
3.1.13.2 Piping
Disconnect piping at unions, flanges and valves, and fittings as required to reduce the pipe into straight lengths for practical storage. Store salvaged piping according to size and type. If the piping that remains can become pressurized due to upstream valve failure, attach end caps, blind flanges, or other types of plugs or fittings with a pressure gage and bleed valve to the open end of the pipe to ensure positive leak control. Carefully dismantle piping that previously contained gas, gasoline, oil, or other dangerous fluids, with precautions taken to
SECTION 02 41 00 Page 11 prevent injury to persons and property. Store piping outdoors until all fumes and residues are removed. Box prefabricated supports, hangers, plates, valves, and specialty items according to size and type. Wrap sprinkler heads individually in plastic bags before boxing. Classify piping not designated for salvage, or not reusable, as scrap metal.
3.1.13.3 Ducts
Classify removed duct work as scrap metal.
3.1.13.4 Fixtures, Motors and Machines
Remove and salvage fixtures, motors and machines associated with plumbing, heating, air conditioning, refrigeration, and other mechanical system installations. Salvage, box and store auxiliary units and accessories with the main motor and machines. Tag salvaged items for identification, storage, and protection from damage. Classify broken, damaged, or otherwise unserviceable units and not caused to be broken, damaged, or otherwise unserviceable as debris to be disposed of by the Contractor.
3.1.14 Electrical Equipment and Fixtures
Salvage motors, motor controllers, and operating and control equipment that are attached to the driven equipment. Salvage wiring systems and components. Box loose items and tag for identification. Disconnect primary, secondary, control, communication, and signal circuits at the point of attachment to their distribution system.
3.1.14.1 Fixtures
Remove and salvage electrical fixtures. Salvage unprotected glassware from the fixture and salvage separately. Salvage incandescent, mercury-vapor, and fluorescent lamps and fluorescent ballasts manufactured prior to 1978, boxed and tagged for identification, and protected from breakage.
3.1.14.2 Electrical Devices
Remove and salvage switches, switchgear, transformers, conductors including wire and nonmetallic sheathed and flexible armored cable, regulators, meters, instruments, plates, circuit breakers, panelboards, outlet boxes, and similar items. Box and tag these items for identification according to type and size.
3.1.14.3 Wiring Ducts or Troughs
Remove and salvage wiring ducts or troughs. Dismantle plug-in ducts and wiring troughs into unit lengths. Remove plug-in or disconnecting devices from the busway and store separately.
3.1.14.4 Conduit and Miscellaneous Items
Salvage conduit except where embedded in concrete or masonry. Consider corroded, bent, or damaged conduit as scrap metal. Sort straight and undamaged lengths of conduit according to size and type. Classify supports, knobs, tubes, cleats, and straps as debris to be removed and disposed.
SECTION 02 41 00 Page 12
3.1.15 Elevators and Hoists
Remove elevators, hoists, and similar conveying equipment and salvage as whole units, to the most practical extent. Remove and prepare items for salvage without damage to any of the various parts. Salvage and store rails for structural steel with the equipment as an integral part of the unit.
3.2 CONCURRENT EARTH-MOVING OPERATIONS
Do not begin excavation, filling, and other earth-moving operations that are sequential to demolition or deconstruction work in areas occupied by structures to be demolished or deconstructed until all demolition and deconstruction in the area has been completed and debris removed. Fill holes, open basements and other hazardous openings.
3.3 DISPOSITION OF MATERIAL
3.3.1 Title to Materials
Except for salvaged items specified in related Sections, and for materials or equipment scheduled for salvage, all materials and equipment removed and not reused or salvaged, become the property of the Contractor and must be removed from Government property. Materials approved for storage by the Contracting Officer must be removed before completion of the contract. Title to materials resulting from demolition and deconstruction, and materials and equipment to be removed, is vested in the Contractor upon approval by the Contracting Officer. The Government will not be responsible for the condition or loss of, or damage to, such property after contract award. Showing for sale or selling materials and equipment on site is prohibited.
3.3.2 Reuse of Materials and Equipment
Remove and store materials and equipment listed in the Demolition Plan to be reused or relocated to prevent damage, and reinstall as the work progresses. Coordinate the re-use of materials and equipment with the re-use requirements in accordance with Section 01 74 19 CONSTRUCTION WASTE MANAGEMENT AND DISPOSAL. Capture re-use of materials in the diversion calculations for the project.
3.3.3 Disposal of Ozone Depleting Substance (ODS)
Class I and Class II ODS are defined in Section, 602(a) and (b), of The Clean Air Act. Prevent discharge of Class I and Class II ODS to the atmosphere. Place recovered ODS in cylinders meeting AHRI Guideline K suitable for the type ODS (filled to no more than 80 percent capacity) and provide appropriate labeling. Recovered ODS must be Remove recovered ODS from Government property and dispose of in accordance with 40 CFR 82 .
Dispose products, equipment and appliances containing ODS in a sealed, self-contained system (e.g. residential refrigerators and window air conditioners) in accordance with 40 CFR 82 . Submit Receipts or bills of lading, as specified. Submit a shipping receipt or bill of lading for all containers of ozone depleting substance (ODS) shipped to the Defense Depot, Richmond, Virginia.
3.3.3.1 Special Instructions
No more than one type of ODS is permitted in each container. Apply a
SECTION 02 41 00 Page 13 warning/hazardous label to the containers in accordance with Department of Transportation regulations. Provide a tag with the following information on all cylinders including but not limited to fire extinguishers, spheres, or canisters containing an ODS:
a. Activity name and unit identification code
b. Activity point of contact and phone number
c. Type of ODS and pounds of ODS contained
d. Date of shipment
e. National stock number (for information, call (804) 279-4525).
3.3.3.2 Fire Suppression Containers
Deactivate fire suppression system cylinders and canisters with electrical charges or initiators prior to shipment. Also, safety caps must be used to cover exposed actuation mechanisms and discharge ports on these special cylinders.
3.3.4 Transportation Guidance
Ship all ODS containers in accordance with MIL-STD-129 , DLA 4145.25 (also referenced one of the following: Army Regulation 700-68, Naval Supply Instruction 4440.128C, Marine Corps Order 10330.2C, and Air Force Regulation 67-12), 49 CFR 173.301 , and DOD 4000.25-1-M .
3.3.5 Unsalvageable and Non-Recyclable Material
Dispose of unsalvageable and non-recyclable noncombustible material in the disposal area located by COR. Maintain the fill in the disposal area below elevation and after disposal is completed, uniformly grade the disposal area to drain. Dispose of unsalvageable and non-recyclable combustible material off the site .
3.4 CLEANUP
Remove debris and rubbish from project site and similar excavations.
Remove and transport the debris in a manner that prevents spillage on streets or adjacent areas. Apply local regulations regarding hauling and disposal.
3.5 DISPOSAL OF REMOVED MATERIALS
3.5.1 Regulation of Removed Materials
Dispose of debris, rubbish, scrap, and other nonsalvageable materials resulting from removal operations with all applicable federal, state and local regulations as contractually specified in the Waste Management Plan.
Storage of removed materials on the project site is prohibited.
3.5.2 Burning on Government Property
Burning of materials removed from demolished and deconstructed structures will not be permitted on Government property.
SECTION 02 41 00 Page 14
3.5.3 Removal to Spoil Areas on Government Property
Transport noncombustible materials removed from demolition and deconstruction structures to designated spoil areas on Government property.
3.5.4 Removal from Government Property
Transport waste materials removed from demolished and deconstructed structures, except waste soil, from Government property for legal disposal. Dispose of waste soil as directed per Section 01 57 19.00 06
TEMPORARY ENVIRONMENTAL CONTROLS.
3.6 REUSE OF SALVAGED ITEMS
Recondition salvaged materials and equipment designated for reuse before installation. Replace items damaged during removal and salvage operations or restore them as necessary to usable condition.
-- End of Section --
SECTION 02 41 00 Page 15
SECTION TABLE OF CONTENTS
DIVISION 03 - CONCRETE
SECTION 03 30 00
CAST-IN-PLACE CONCRETE
02/19, CHG 8: 05/24
PART 1 GENERAL
1.1 REFERENCES
1.2 DEFINITIONS
1.3 SUBMITTALS
1.4 MODIFICATION OF REFERENCES
1.5 DELIVERY, STORAGE, AND HANDLING
1.5.1 Reinforcement
1.5.1.1 Epoxy Coated Reinforcing Steel
1.6 QUALITY ASSURANCE
1.6.1 Design Data
1.6.1.1 Concrete Mix Design
1.6.2 Shop Drawings
1.6.2.1 Formwork
1.6.2.2 Reinforcing Steel
1.6.3 Control Submittals
1.6.3.1 Concrete Curing Plan
1.6.3.2 Pumping Concrete
1.6.3.3 Silica Fume Manufacturer's Representative
1.6.3.4 Finishing Plan
1.6.3.5 VOC Content for form release agents, curing compounds, and concrete penetrating sealers
1.6.3.6 Safety Data Sheets
1.6.4 Test Reports
1.6.4.1 Fly Ash and Pozzolan
1.6.4.2 Slag Cement
1.6.4.3 Aggregates
1.6.5 Field Samples
1.6.5.1 Slab Finish Sample
1.6.6 Quality Control Program
1.6.7 Quality Control Personnel Certifications
1.6.7.1 Quality Manager Qualifications
1.6.7.2 Field Testing Technician and Testing Agency
1.6.8 Laboratory Qualifications for Concrete Qualification Testing
1.6.9 Laboratory Accreditation
1.7 ENVIRONMENTAL REQUIREMENTS
1.7.1 Submittals for Environmental Performance
1.8 SUSTAINABLE DESIGN REQUIREMENTS
1.8.1 Local/Regional Materials
1.8.2 Forest Stewardship Council (FSC) Certification
1.9 QUALIFICATIONS FOR WELDING WORK
PART 2 PRODUCTS
2.1 FORMWORK MATERIALS
2.1.1 Wood Forms
SECTION 03 30 00 Page 1
2.1.1.1 Concrete Form Plywood (Standard Rough)
2.1.1.2 Overlaid Concrete Form Plywood (Standard Smooth)
2.1.2 Plastic Forms
2.1.3 Carton Forms
2.1.4 Steel Forms
2.2 FORMWORK ACCESSORIES
2.2.1 Form Ties
2.2.2 Waterstops
2.2.2.1 PVC Waterstop
2.2.2.2 Rubber Waterstop
2.2.2.3 Thermoplastic Elastomeric Rubber Waterstop
2.2.2.4 Hydrophilic Waterstop
2.2.3 Biodegradable Form Release Agent
2.2.4 Chamfer Materials
2.2.5 Construction and movement joints
2.2.6 Other Embedded items
2.3 CONCRETE MATERIALS
2.3.1 Cementitious Materials
2.3.1.1 Portland Cement
2.3.1.2 Blended Cements
2.3.1.3 Fly Ash
2.3.1.4 Slag Cement
2.3.1.5 Silica Fume
2.3.1.6 Other Supplementary Cementitious Materials
2.3.2 Water
2.3.3 Aggregate
2.3.3.1 Normal-Weight Aggregate
2.3.3.2 Lightweight Aggregate
2.3.3.3 Recycled Aggregate Materials
2.3.4 Admixtures
2.4 MISCELLANEOUS MATERIALS
2.4.1 Concrete Curing Materials
2.4.2 Nonshrink Grout
2.4.3 Floor Finish Materials
2.4.3.1 Liquid Chemical Floor Hardeners and Sealers
2.4.3.2 Abrasive Aggregate for Nonslip Aggregate Finish
2.4.3.3 Dry Materials for Colored Wear-Resistant Finish
2.4.3.4 Aggregate for Heavy-Duty Wear-Resistant Finish
2.4.3.5 Aggregate for Heavy-Duty Floor Topping
2.4.4 Expansion/Contraction Joint Filler
2.4.5 Joint Sealants
2.4.5.1 Horizontal Surfaces, 3 Percent Slope, Maximum
2.4.5.2 Vertical Surfaces Greater Than 3 Percent Slope
2.4.5.3 Preformed Polychloroprene Elastomeric Type
2.4.5.4 Lubricant for Preformed Compression Seals
2.4.6 Vapor Retarder and Vapor Barrier
2.4.7 Dovetail Anchor Slot
2.5 CONCRETE MIX DESIGN
2.5.1 Properties and Requirements
2.5.2 Durability
2.5.2.1 Alkali-Aggregate Reaction
2.5.2.2 Freezing and Thawing Resistance
2.5.2.3 Corrosion and Chloride Content
2.5.2.4 Sulfate Resistance
2.5.2.5 Concrete Temperature
2.5.2.6 Concrete Permeability
2.5.3 Contractor's Option for Material Only
2.5.4 Trial Mixtures
2.5.5 Ready-Mix Concrete
SECTION 03 30 00 Page 2
2.6 REINFORCEMENT
2.6.1 Reinforcing Bars
2.6.1.1 Galvanized Reinforcing Bars
2.6.1.2 Epoxy-Coated Reinforcing Bars
2.6.1.3 Dual-coated Reinforcing Bars
2.6.1.4 Stainless Steel Reinforcing Bars
2.6.1.5 Headed Reinforcing Bars
2.6.1.6 Bar Mats
2.6.1.7 Headed Shear Stud Reinforcement
2.6.2 Mechanical Reinforcing Bar Connectors
2.6.3 Wire
2.6.4 Welded wire reinforcement
2.6.5 Reinforcing Bar Supports
2.6.6 Dowels for Load Transfer in Floors
2.6.7 Welding
PART 3 EXECUTION
3.1 EXAMINATION
3.2 PREPARATION
3.2.1 General
3.2.2 Subgrade Under Foundations and Footings
3.2.3 Subgrade Under Slabs on Ground
3.2.4 Edge Forms and Screed Strips for Slabs
3.2.5 Reinforcement and Other Embedded Items
3.3 FORMS
3.3.1 Coating
3.3.2 Reshoring
3.3.3 Reuse
3.3.4 Forms for Standard Rough Form Finish
3.3.5 Forms for Standard Smooth Form Finish
3.3.6 Form Ties
3.3.7 Forms for Concrete Pan Joist Construction
3.3.8 Tolerances for Form Construction
3.3.9 Removal of Forms and Supports
3.3.10 Strength of Concrete Required for Removal of Formwork
3.4 WATERSTOP INSTALLATION AND SPLICES
3.4.1 PVC Waterstop
3.4.2 Rubber Waterstop
3.4.3 Thermoplastic Elastomeric Rubber Waterstop
3.4.4 Hydrophilic Waterstop
3.5 PLACING REINFORCEMENT AND MISCELLANEOUS MATERIALS
3.5.1 General
3.5.2 Vapor Retarder and Vapor Barrier
3.5.3 Perimeter Insulation
3.5.4 Reinforcement Supports
3.5.5 Splicing
3.5.6 Future Bonding
3.5.7 Setting Miscellaneous Material
3.5.8 Inspection of Reinforcement
3.5.9 Placing Reinforcement
3.5.10 Spacing of Reinforcing Bars
3.5.11 Concrete Protection for Reinforcement
3.5.12 Welding
3.6 BATCHING, MEASURING, MIXING, AND TRANSPORTING CONCRETE
3.6.1 Measuring
3.6.2 Mixing
3.6.3 Transporting
3.7 PLACING CONCRETE
SECTION 03 30 00 Page 3
3.7.1 Pumping
3.7.2 Cold Weather
3.7.3 Hot Weather
3.7.4 Bonding
3.8 WASTE MANAGEMENT
3.8.1 Mixing Equipment
3.8.2 Hardened, Cured Waste Concrete
3.8.3 Reinforcing Steel
3.8.4 Other Waste
3.9 SURFACE FINISHES EXCEPT FLOOR, SLAB, AND PAVEMENT FINISHES
3.9.1 Defects
3.9.2 Not Against Forms (Top of Walls)
3.9.3 Formed Surfaces
3.9.3.1 Tolerances
3.9.3.2 As-Cast Rough Form
3.9.3.3 Standard Smooth Finish
3.9.4 Smooth-RubbedGrout-Cleaned RubbedCork-FloatedExposed Aggregate
Finish
3.10 FLOOR, SLAB, AND PAVEMENT FINISHES AND MISCELLANEOUS CONSTRUCTION
3.10.1 Finish
3.10.1.1 Scratched
3.10.1.2 Floated
3.10.1.3 Concrete Containing Silica Fume
3.10.1.4 Steel Troweled
3.10.1.5 Nonslip Finish
3.10.1.6 Broomed
3.10.1.7 Pavement
3.10.1.8 Concrete Toppings Placement
3.10.1.9 Chemical-Hardener Treatment
3.10.1.10 Colored Wear-Resistant Finish
3.10.1.11 Heavy-Duty Wear-Resistant Finish
3.10.2 Flat Floor Finishes
3.10.2.1 Measurement of Floor Tolerances
3.10.2.2 Remedies for Out of Tolerance Work
3.10.3 Concrete Walks
3.10.4 Pits and Trenches
3.10.5 Curbs and Gutters
3.10.6 Splash Blocks
3.11 JOINTS
3.11.1 Construction Joints
3.11.1.1 Construction Joints for Constructability Purposes
3.11.2 Isolation Joints in Slabs on Ground
3.11.3 Contraction Joints in Slabs on Ground
3.11.4 Sealing Joints in Slabs on Ground
3.12 CONCRETE FLOOR TOPPING
3.12.1 Standard Floor Topping
3.12.1.1 Preparations Prior to Placing
3.12.1.2 Placing
3.12.1.3 Finishing
3.12.2 Heavy-Duty Floor Topping
3.12.2.1 Heavy-duty Topping Mixture
3.12.2.2 Base Slab
3.12.2.3 Placing
3.12.2.4 Finishing
3.13 CURING AND PROTECTION
3.13.1 Requirements for Type III, High-Early-Strength Portland Cement
3.13.2 Curing Periods
3.13.3 Curing Formed Surfaces
3.13.4 Curing Unformed Surfaces
SECTION 03 30 00 Page 4
3.13.5 Temperature of Concrete During Curing
3.13.6 Protection from Mechanical Injury
3.13.7 Protection After Curing
3.14 FIELD QUALITY CONTROL
3.14.1 Aggregate Testing
3.14.1.1 Fine Aggregate
3.14.1.2 Coarse Aggregate
3.14.2 Concrete Sampling
3.14.3 Concrete Testing
3.14.3.1 Slump Tests
3.14.3.2 Temperature Tests
3.14.3.3 Compressive Strength Tests
3.14.3.4 Air Content
3.14.3.5 Unit Weight of Structural Concrete
3.14.3.6 Chloride Ion Concentration
3.14.3.7 Strength of Concrete Structure
3.14.3.8 Non-Conforming Materials
3.14.3.9 Testing Concrete Structure for Strength
3.15 REPAIR, REHABILITATION AND REMOVAL
3.15.1 Repair of Weak Surfaces
3.15.2 Failure of Quality Assurance Test Results
-- End of Section Table of Contents --
SECTION 03 30 00 Page 5
SECTION 03 30 00
CAST-IN-PLACE CONCRETE
02/19, CHG 8: 05/24
PART 1 GENERAL
1.1 REFERENCES
The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.
AMERICAN CONCRETE INSTITUTE (ACI)
ACI 117 (2010; R 2015) Specifications for Tolerances for Concrete Construction and Materials and Commentary
ACI 121R (2008) Guide for Concrete Construction Quality Systems in Conformance with ISO
ACI 301 (2020) Specifications for Structural Concrete
ACI 302.1R (2015) Guide for Concrete Floor and Slab Construction
ACI 304.2R (2017) Guide to Placing Concrete by Pumping Methods
ACI 304R (2000; R 2009) Guide for Measuring, Mixing, Transporting, and Placing Concrete
ACI 305.1 (2014) Specification for Hot Weather Concreting
ACI 305R (2020) Guide to Hot Weather Concreting
ACI 306.1 (1990; R 2002) Standard Specification for Cold Weather Concreting
ACI 306R (2016) Guide to Cold Weather Concreting
ACI 308.1 (2011) Specification for Curing Concrete
ACI MNL-2 (2019; 11th Edition) ACI Manual of Concrete Inspection
ACI MNL-15 (2020) Field Reference Manual:
Specifications for Concrete Construction ACI 301-20 with Selected ACI References
AMERICAN HARDBOARD ASSOCIATION (AHA)
AHA A135.4 (1995; R 2004) Basic Hardboard
SECTION 03 30 00 Page 6
AMERICAN WELDING SOCIETY (AWS)
AWS D1.4/D1.4M (2018) Structural Welding Code - Reinforcing Steel
ASTM INTERNATIONAL (ASTM)
ASTM A36/A36M (2019) Standard Specification for Carbon Structural Steel
ASTM A53/A53M (2024) Standard Specification for Pipe, Steel, Black and Hot-Dipped, Zinc-Coated, Welded and Seamless
ASTM A184/A184M (2019) Standard Specification for Welded Deformed Steel Bar Mats for Concrete Reinforcement
ASTM A615/A615M (2022) Standard Specification for Deformed and Plain Carbon-Steel Bars for Concrete Reinforcement
ASTM A706/A706M (2024) Standard Specification for Low-Alloy Steel Deformed and Plain Bars for Concrete Reinforcement
ASTM A767/A767M (2019) Standard Specification for Zinc-Coated (Galvanized) Steel Bars for Concrete Reinforcement
ASTM A775/A775M (2022) Standard Specification for Epoxy-Coated Steel Reinforcing Bars
ASTM A780/A780M (2020) Standard Practice for Repair of Damaged and Uncoated Areas of Hot-Dip Galvanized Coatings
ASTM A884/A884M (2019; Errata 1) Standard Specification for Epoxy-Coated Steel Wire and Welded Wire Reinforcement
ASTM A934/A934M (2022) Standard Specification for Epoxy-Coated Prefabricated Steel Reinforcing Bars
ASTM A955/A955M (2020c) Standard Specification for Deformed and Plain Stainless-Steel Bars for Concrete Reinforcement
ASTM A970/A970M (2018) Standard Specification for Headed Steel Bars for Concrete Reinforcement
ASTM A1022/A1022M (2016b) Standard Specification for Deformed and Plain Stainless Steel Wire…
This is the start of the file's text. The full file is on GovTribe.
File details come from the government source that posted it. Updated .