LEED® - NC Version 2009 Checklist NY ANG - Add to Flight Training Unit Building 641 Y = Required must be achieved. Construction or Design prerequisite

D = Design Credit

C = Construction Credit

O = Construction Credit Option, Provide line item in Bid for cost to achieve the credit N = Credit is not being pursued.

D C O N Credit Category Credit Title Notes & Actions

Sustainable Sites (SS) Y SS Prerequisite 1 Construction Activity Pollution Prevention, Erosion and

Sedimentation Control Plan Contractor must meet this prerequisite.

1 SS Credit 1 Site Selection

5 SS Credit 2 Development Density & Community Connectivity

1 SS Credit 3 Brownfield Redevelopment

6 SS Credit 4.1 Alternative Transportation, Public Transportation Access

1 SS Credit 4.2 Alternative Transportation, Bicycle Storage & Changing Rooms

3 SS Credit 4.3 Alternative Transportation, Low Emitting (LE) & Fuel Efficient (FE) Vehicles

2 SS Credit 4.4 Alternative Transportation, Parking Capacity

1 SS Credit 5.1 Site Development, Protect or Restore Habitat Threshold cannot be achieved for open space.

1 SS Credit 5.2 Site Development, Maximize Open Space Credit cannot be achieved

1 SS Credit 6.1 Stormwater Design, Quantity Control

1 SS Credit 6.2 Stormwater Design, Quality Control Credit cannot be achieved

1 SS Credit 7.1 Heat Island Effect, Non-Roof

1 SS Credit 7.2 Heat Island Effect, Roof

1 SS Credit 8 Light Pollution Reduction 11 0 0 15 Subtotal Points Possible (26)

D C O N Credit Category Credit Title Notes & Actions Water Efficiency (WE)

Y WE Prerequisite 1 Water Use Reduction - 20% Reduction Plumbing fixtures are being specified in the project that shall achieve this credit.

2 WE Credit 1.1 Water Efficient Landscaping, Reduce by 50% No potable water use for irrigation.

2 WE Credit 1.2 Water Efficient Landscaping, No Potable Water Use or No Irrigation

See comment for WEc1.1

2 WE Credit 2 Innovative Wastewater Technologies Credit cannot be achieved.

2 2 WE Credit 3.1 Water Use Reduction See comment for WEp1

6 0 0 4 Subtotal Points Possible (10)

Energy and Atmosphere (EA)

Y EA Prerequisite 1 Fundamental Commissioning of the Building Energy Systems Commissioning Authority, is part of the A/E firm but not part of the design team. See Commissioning Specifications.

Y EA Prerequisite 2 Minimum Energy Performance

Y EA Prerequisite 3 Fundamental Refrigerant Management

3 16 EA Credit 1 Optimize Energy Performance 16% for New Buildings / 12% for Existing Building Reno.

7 EA Credit 2 On-Site Renewable Energy

2 EA Credit 3 Enhanced Commissioning Enhanced Commissioning Activities will not be performed.

2 EA Credit 4 Enhanced Refrigerant Management

3 EA Credit 5 Measurement and Verification

2 EA Credit 6 Green Power 3 0 0 32 Subtotal EA Points Possible (35)

Materials and Resources (MR) Y MR Prerequisite 1 Storage & Collection of Recyclables

3 MR Credit 1.1 Building Reuse, Maintain Existing Walls, Floors and Roof Maintain 95% of Existing Walls, Floor & Roof

1 MR Credit 1.2 Building Reuse, Maintain 50% of Interior Non-Structural Element

Maintain 50% of interior non-structural elements.

1 MR Credit 2.1 Construction Waste Management, Divert 50% from Disposal Threshold must be achieved.

1 MR Credit 2.2 Construction Waste Management, Divert 75% from Disposal Threshold must be achieved.

1 MR Credit 3.1 Materials Reuse, 5% Cannot be achieved.

1 MR Credit 3.2 Materials Reuse, 10% Cannot be achieved.

1 MR Credit 4.1 Recycled Content, 10% (post-consumer + 1/2 pre-consumer) Threshold must be achieved.

1 MR Credit 4.2 Recycled Content, 20% (post-consumer + 1/2 pre-consumer) Threshold must be achieved.

1 MR Credit 5.1 Regional Materials, 10% extracted, processed & manufactured Threshold must be achieved.

1 MR Credit 5.2 Regional Materials, 20% extracted, processed & manufactured Threshold must be achieved.

1 MR Credit 6 Rapidly Renewable Materials

1 MR Credit 7 Certified Wood Threshold must be achieved.

0 11 0 3 Subtotal MR Points Possible (14)

Indoor Environmental Quality (EQ)

Y EQ Prerequisite 1 Minimum IAQ Performance Design will meet the ASHRAE 62.1-2007 requirements.

Y EQ Prerequisite 2 Environmental Tobacco Smoke (ETS) Control Smoking will not be allowed in the facility.

1 EQ Credit 1 Outdoor Air Delivery Monitoring Required monitoring devices are part of the design.

1 EQ Credit 2 Increased Ventilation

1 EQ Credit 3.1 Construction IAQ Management Plan, During Construction Contractor must achieve.

1 EQ Credit 3.2 Construction IAQ Management Plan, Before Occupancy Contractor must achieve.

1 EQ Credit 4.1 Low-Emitting Materials, Adhesives & Sealants Materials must meet VOC content.

1 EQ Credit 4.2 Low-Emitting Materials, Paints & Coatings Materials must meet VOC content.

1 EQ Credit 4.3 Low-Emitting Materials, Flooring Systems Flooring must meet requirements.

1 EQ Credit 4.4 Low-Emitting Materials, Composite Wood & Agrifiber Products Materials must meet requirements.

1 EQ Credit 5 Indoor Chemical and Pollutant Source Control

1 EQ Credit 6.1 Controllability of Systems, Lighting

1 EQ Credit 6.2 Controllability of Systems, Thermal Comfort Credit cannot be achieved.

1 EQ Credit 7.1 Thermal Comfort, Design

1 EQ Credit 7.2 Thermal Comfort, Verification

1 EQ Credit 8.1 Daylight and Views, Daylight 75% of Spaces Cannot be achieved.

1 EQ Credit 8.2 Daylight and Views, Views for 90% of Spaces Cannot be achieved.

4 6 0 5 Subtotal EQ Points Possible (15)

Innovation & Design Process (ID)

1 ID Credit 1.1 Exemplary Performance, MRc2, MRc4, MRc5, or MRc7 Contractor is required to achieve exemplary preformance on one the listed credits.

1 ID Credit 1.2 Exemplary Performance, MRc2, MRc4, MRc5, MRc7 Contractor is required to achieve exemplary preformance on one the listed credits.

1 ID Credit 1.3 Exemplary Performance, MRc2, MRc4, MRc5, MRc7 Contractor is required to achieve exemplary preformance on one the listed credits.

1 ID Credit 1.4 Innovation in Design

1 ID Credit 1.5 Innovation in Design

1 ID Credit 2 LEED® Accredited Professional LEED AP is part of the A/E team

0 4 0 2 Subtotal ID Points Possible (6)

Regional Priority (RP)

1 RP Credit 1.1 Regional Priority, MRc1.1 Building reuse - maintain existing walls, floor and roof

Credit is achievable

1 RP Credit 1.2 Regional Priority, MRc1.1 Building reuse - maintain existing walls, floor and roof

Credit is achievable

1 RP Credit 1.3 Regional Priority, MRc1.1 Building reuse - maintain existing walls, floor and roof

Credit is achievable

1 RP Credit 1.4 Regional Priority, SSc7.2 Heat island effect - roof Credit is achievable

1 3 0 0 Subtotal RP Points Possible (4)

TOTAL POINTS POSSIBLE (110)

25 24 0 61

LEED® GREEN BUILDING CERTIFICATION LEVELS

Certified = 40-49

Silver = 50-59

Gold = 60-79

Platinum = 80 and above

SUMMARY

25 Credits shall be the responsibilty of the A/E firm.

24 Credits shall be the responsibility of the contractor 0 Credit(s) shall be identified as Bid Option(s). Contractor shall provide a separate cost to achieve each credit identified as a Bid Option.

49 Credits shall be pursued.