A22 - Enclosure A - ENG_Form_6213_Critical Lift Plan (AUG-2024).pdf
PDF 152 KB Posted
- Attached to
- W. Kerr Scott Crane Rental
- Solicitation number
- W912PM26QA048
About this file
ENG Form 6213 (August 2024) is a U.S. Army Corps of Engineers template for documenting critical lift plans for load handling equipment and crane operations. The form is designed to identify, evaluate, and address safety requirements before executing any lifting activity, and it must be completed by a competent person with all required inspections, tests, and preparation requirements verified prior to lift commencement.
The form requires comprehensive documentation across eight main sections: total load weight (including auxiliary blocks, main blocks, lifting beams, slings, jibs, and hoist rope); operator qualifications (certification, type/class/capacity certification, and written employer designation); crane specifications (type, capacity, radius, boom length, boom angle, and jib information); a detailed pre-lift checklist covering inspection, setup, hazard assessment, communication, and meeting requirements; hoist rope specifications (number of parts, diameter, and capacity for main and auxiliary systems); rigging details (hitch types, sling specifications, shackle information); and for mobile cranes, crane placement considerations including bearing pressure, ground conditions, electrical hazards, and obstructions. The form includes designated signature blocks for the crane operator, rigger(s), signal person, lift director, and other personnel, along with attachable pages for load calculations, bearing pressure and ground condition analysis, load charts, operator/rigger/signal person qualifications, and site plans with sequencing. The form references compliance with EM 385-1-1 and identifies CESO as the proponent agency.
View the file
Other files
Show all 21
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
ENG FORM 6213, AUG 2024 PREVIOUS EDITIONS ARE OBSOLETE. Page of
U.S. Army Corps of Engineers (USACE)
LOAD HANDLING EQUIPMENT CRANE OPERATION CRITICAL LIFT PLAN
For use of this form, see EM 385-1-1; the proponent agency is CESO.
PURPOSE: This Critical Lift Plan will identify, evaluate, and address each item below. The load handling activity should only start after all setup and preparation requirements of the plan are in place, all required inspections and test of the LHE and rigging equipment have been completed, and all requirements of the plan continue to be met and no conditions exists that would preclude implementation of the plan.
Prepared By (Competent Person) Contract Number (if applicable)
Location Time Date
A. TOTAL LOAD
1. Load weight lbs.
2. Weight of auxiliary block lbs.
3. Weight of main block lbs.
4. Weight of lifting beam lbs.
5. Weight of slings/shackles lbs.
6. Weight of jib/ext. (erected/stowed) lbs.
7. Weight of hoist rope lbs.
8. Other lbs.
TOTAL WEIGHT: lbs.
Note. Attach on page 2 source of load weight (drawings, calcs, etc.)
B. OPERATOR QUALIFICATIONS
Items Yes No N/A
1. Certified Operator?
3. Certified for type, class & capacity?
4. Designed in writing by employer?
C. CRANE
1. Type of crane
2. Maximum crane capacity lbs.
3. Radius (maximum) ft.
4. Radius (minimum) ft.
5. Boom length (maximum) ft.
6. Boom length (minimum) ft.
7. Crane capacity (max radius) lbs.
8. Crane capacity (min radius) lbs.
9. Boom angle (maximum) deg.
10. Boom angle (minimum) deg.
11. Gross load of crane
12. Lift is lbs.
% of the crane's rated capacity
13. If jib/ext. is to be used, Length ft.
Offset ft.
14. Rated capacity of jib/ext. lbs.
D. PRE-LIFT CHECKLIST
Items Yes No N/A
1. Crane inspected
2. Rigging inspected
3. Crane set-up
4. Overhead hazard check
5. Swing check
6. Counterweight check
7. Operator qualifications
8. Load Test required
9. Anti-Two Block Device functioning correctly
10. Load travel plan is planned for
11. Correct blocking/cribbing identified
12. Rigging gear inspected
13. Tag lines
14. Wind conditions
15. Communication is established and agreed upon
16. Site control
17. Has the pre-lift meeting been held
ENG FORM 6213, AUG 2024 Page of
E. HOIST ROPE
1. Number of parts
Item Main Aux 1 Aux 2
2. Rope diameter
3. Capacity
G. RIGGING
1. Hitch type(s)
2. # of slings Size
3. Sling type
4. Sling assembly capacity lbs.
5. Shackle size(s)
6. Shackle rated capacity(s) lbs.
7. Additional Rigging Information:
F. CRANE PLACEMENT (mobile cranes only)
Items
2. Ground conditions suitable for load?
Note. Attach on page 3 ground condition calculations
Yes No N/A
3. High voltage or electrical hazards are present?
Note. If yes, show on page 4.
4. Obstructions to lift or swing are present?
Note. If yes, show on page 4.
5. Travel with load required?
6. Other?
1. Maximum bearing pressure PSF
Note. Attach bearing pressure calculations on page3.
H. SIGNATURES
Crane Operator
Name Date Signature
Rigger(s)
Name Date Signature
Name Date Signature
Name Date Signature
Signal Person
Name Date Signature
Lift Director
Name Date Signature
Other
Name Title
Signature Date
Name Title
Signature Date
LOAD CALCULATIONS
Show here or attach calculation, drawings, etc.Show here or attach calculation, drawings, etc.
LOAD CALCULATIONS
Show here or attach calculation, drawings, etc.
BEARING PRESSURES & GROUND CONDITIONS
Show here or attach load chart.
LOAD CHART
Attach Qualifications
OPERATOR, RIGGER, SIGNAL PERSON QUALIFICATIONS
Show here or attach site plan and sequencing.
SITE PLAN
ENG FORM 6213, AUG 2024
Page of
PREVIOUS EDITIONS ARE OBSOLETE.
ENG FORM 6213, AUG 2024
Page of U.S. Army Corps of Engineers (USACE)
LOAD HANDLING EQUIPMENT CRANE OPERATION CRITICAL LIFT PLAN
For use of this form, see EM 385-1-1; the proponent agency is CESO.
PURPOSE: This Critical Lift Plan will identify, evaluate, and address each item below. The load handling activity should only start after all setup and preparation requirements of the plan are in place, all required inspections and test of the LHE and rigging equipment have been completed, and all requirements of the plan continue to be met and no conditions exists that would preclude implementation of the plan.
A. TOTAL LOAD
lbs.
lbs.
lbs.
lbs.
lbs.
lbs.
lbs.
lbs.
lbs.
Note. Attach on page 2 source of load weight (drawings, calcs, etc.)
B. OPERATOR QUALIFICATIONS
Items Yes No N/A
1. Certified Operator?
3. Certified for type, class & capacity?
4. Designed in writing by employer?
C. CRANE
lbs.
ft.
ft.
ft.
ft.
lbs.
lbs.
deg.
deg.
lbs.
% of the crane's rated capacity ft.
ft.
lbs.
D. PRE-LIFT CHECKLIST
Items Yes No N/A
1. Crane inspected
2. Rigging inspected
3. Crane set-up
4. Overhead hazard check
5. Swing check
6. Counterweight check
7. Operator qualifications
8. Load Test required
9. Anti-Two Block Device functioning correctly
10. Load travel plan is planned for
11. Correct blocking/cribbing identified
12. Rigging gear inspected
13. Tag lines
14. Wind conditions
15. Communication is established and agreed upon
16. Site control
17. Has the pre-lift meeting been held
E. HOIST ROPE
Item Main Aux 1 Aux 2
G. RIGGING
Size lbs.
lbs.
F. CRANE PLACEMENT (mobile cranes only) Items
2. Ground conditions suitable for load?
Note. Attach on page 3 ground condition calculations Yes No N/A
3. High voltage or electrical hazards are present?
Note. If yes, show on page 4.
4. Obstructions to lift or swing are present?
Note. If yes, show on page 4.
5. Travel with load required?
PSF
Note. Attach bearing pressure calculations on page3.
H. SIGNATURES
Crane Operator Rigger(s) Signal Person Lift Director Other
LOAD CALCULATIONS
LOAD CALCULATIONS
BEARING PRESSURES & GROUND CONDITIONS
LOAD CHART
OPERATOR, RIGGER, SIGNAL PERSON QUALIFICATIONS
SITE PLAN
1.0 darwin.chen@usace.army.mil 2023-05-17 Forms Design Team Darwin Chen 2024-08-31 Eng Form 6213
LOAD HANDLING EQUIPMENT CRANE OPERATION CRITICAL LIFT PLAN
| PrintButton1: |
| saveas: |
| currentPage: |
| pageCount: |
| TextField1: |
| DateField1: |
| lbs1: |
| lbs2: |
| lbs3: |
| lbs4: |
| lbs5: |
| lbs6: |
| lbs7: |
| other8: |
| lbs8: |
| NumericField1: |
| Yes: 0 |
| Yes: 0 |
| Yes: 0 |
| Yes: 0 |
| Yes: 0 |
| Yes: 0 |
| Yes: 0 |
| Yes: 0 |
| Yes: 0 |
| Yes: 0 |
| Yes: 0 |
| Yes: 0 |
| Yes: 0 |
| Yes: 0 |
| Yes: 0 |
| Yes: 0 |
| Yes: 0 |
| Yes: 0 |
| Yes: 0 |
| Yes: 0 |
| Yes: 0 |
| Yes: 0 |
| Yes: 0 |
| Yes: 0 |
| No: 0 |
| No: 0 |
| No: 0 |
| No: 0 |
| No: 0 |
| No: 0 |
| No: 0 |
| No: 0 |
| No: 0 |
| No: 0 |
| No: 0 |
| No: 0 |
| No: 0 |
| No: 0 |
| No: 0 |
| No: 0 |
| No: 0 |
| No: 0 |
| No: 0 |
| No: 0 |
| No: 0 |
| No: 0 |
| No: 0 |
| No: 0 |
| N/A: 0 |
| N/A: 0 |
| N/A: 0 |
| N/A: 0 |
| N/A: 0 |
| N/A: 0 |
| N/A: 0 |
| N/A: 0 |
| N/A: 0 |
| N/A: 0 |
| N/A: 0 |
| N/A: 0 |
| N/A: 0 |
| N/A: 0 |
| N/A: 0 |
| N/A: 0 |
| N/A: 0 |
| N/A: 0 |
| N/A: 0 |
| N/A: 0 |
| N/A: 0 |
| N/A: 0 |
| N/A: 0 |
| N/A: 0 |
| TextField2: |
| craneSignature: |
| rigger1Signature: |
| rigger2Signature: |
| rigger3Signature: |
| signalSignature: |
| liftSignature: |
| other1Signature: |
| other2Signature: |
File details come from the government source that posted it. Updated .