BID ABSTRACT FOR IFB W912PL-09-B-0009
PORT OF LONG BEACH & OTHER LONG BEACH
PROJECTS, LOS ANGELES COUNTY, CA
BID OPENING DATE: 18 SEP 2009
UNRESTRICTED-10% HUBZONE PREF
7 AMENDMENTS
INDEPENDENT GOVERNMENT ESTIMATE
BASE BID ITEMS
ITEM NO. DESCRIPTION ESTIMATED UNIT UNIT PRICE AMOUNT
QUANTITY
Port of Long Beach (Deepening)
1 Mobilization and Demobilization 1 Job Lump Sum $1,012,000.00 1a. Federal ARRA Funded (35% of Item No.1) 1b. Federal CG Funded (15% of Item No. 1) 1c. Non-Federal Funded (50% of Item No. 1)
2 Dredging, D102 w/Placement at F101 90,000 Cubic Yards $13.20 $1,188,000.00 2a. Federal ARRA Funded (First 45,000 Cubic Yards of Item No.2) 2b. Non-Federal Funded (Second 45,000 Cubic Yards of Item No.2)
3 Dredging, D102 w/Placement at F105 & 106 460,000 Cubic Yards $10.00 $4,600,000.00 3a. Federal CG Funded (First 230,000 Cubic Yards of Item No.3) 3b. Non-Federal Funded (Second 230,000 Cubic Yards of Item No.3)
4 Dredging, D103 w/Placement at F103 90,000 Cubic Yards $17.20 $1,548,000.00 4a. Federal ARRA Funded (First 45,000 Cubic Yards of Item No.4) 4b. Non-Federal Funded (Second 45,000 Cubic Yards of Item No.4)
Sub-Total Turning Basin Deepening $8,348,000.00
Pier G North Slip Dike and Dredging
5 Mobilization and Demobilization 1 Job Lump Sum $960,000.00
6 Steel Sheet Pile Wall 1 Job Lump Sum $3,936,000.00
7 Settlement Monitoring 1 Job Lump Sum $144,200.00
8 SWPPP Development & Compliance 1 Job Lump Sum $10,000.00
9 Dredging, D101 w/Placement at F102 15,000 Cubic Yards $14.40 $216,000.00
10 Dredging, D108 w/Placement at F104, F105, & F106 200,000 Cubic Yards $7.20 $1,440,000.00
11 Furnish Concrete Piles 9,000 Linear Feet $109.00 $981,000.00
12 Drive Concrete Piles 88 Each $6,600.00 $580,800.00
13 Storm Drain System 1 Job Lump Sum $860,000.00
14 Crushed Miscellaneous Base 15,000 Tons $27.00 $405,000.00
15 Asphalt Concrete 5,000 Tons $140.00 $700,000.00
16 Wick Drains 1,050,000 Linear Feet $1.27 $1,333,500.00
17 Quarry Run Rock 220,000 Tons $26.00 $5,720,000.00
18 Armor Stone 15,000 Tons $32.40 $486,000.00
19 Furnish and Place Pavement Markings & Signage 1 Job Lump Sum $119,400.00
Sub-Total Pier G North Slip Fill $17,891,900.00
Pier T, West Basin IR Site 7 Sediment Remediation
20 Mobilization and Demobilization 1 Job Lump Sum $648,000.00
21 IR Site 7 Demolition 1 Job Lump Sum $933,000.00
22 Barge Removal 1 Job Lump Sum $864,000.00
23 SWPPP Development and Compliance 1 Job Lump Sum $10,000.00
24 Dredging, D104/D105 w/Placement at F102/F103 587,000 Cubic Yards $15.40 $9,039,800.00
25 Hydroseeding 6 Acres $41,800.00 $250,800.00
26 Restoration & Repair of Temp Irrigation System 1 Job Lump Sum $169,000.00
27 Required Insurance 1 Job Lump Sum $406,000.00
28 On Site SUXOS Personnel 1 Job Lump Sum $450,000.00
Sub-Total West Basin IR Site 7 Sediment Clean-Up $12,770,600.00
Catalina Express Terminal Maintenance Dredging and Demolition
29 Mobilization and Demobilization 1 Job Lump Sum $791,000.00
30 Dredging, D106, w/Placement at F105 37,000 Cubic Yards $16.40 $606,800.00
31 Catalina Landing Demolition 1 Job Lump Sum $253,000.00
Sub-Total Catalina Express Terminal $1,650,800.00
Pier T, West Basin IR Site 7 Sediment Remediation
32 Additional Set-ups 5 Each $39,200.00 $196,000.00
33 Re-Dredging D104/D105 w/Placement at F102/F103 59,000 Cubic Yards $45.40 $2,678,600.00
34 Daily Stand-by Time 14 Days $62,600.00 $876,400.00
35 Hourly Stand-by Time 48 Hours $2,600.00 $124,800.00
Sub-Total West Basin IR Site 7 Sediment Clean-Up (Option) $3,875,800.00
TOTAL BID AMOUNT $44,537,100.00
PROJECTS, LOS ANGELES COUNTY, CA
BID OPENING DATE: 18 SEP 2009
UNRESTRICTED-10% HUBZONE PREF
7 AMENDMENTS
MANSON CONSTRUCTION CO.
5209 E. MARGINAL WAY S
SEATTLE, WA 98134 206-762-0850
BASE BID ITEMS:
ITEM NO. DESCRIPTION ESTIMATED UNIT UNIT PRICE AMOUNT
QUANTITY
Port of Long Beach (Deepening)
1 Mobilization and Demobilization 1 Job Lump Sum $3,400,000.00 1a. Federal ARRA Funded (35% of Item No.1) 1b. Federal CG Funded (15% of Item No. 1) 1c. Non-Federal Funded (50% of Item No. 1)
2 Dredging, D102 w/Placement at F101 90,000 Cubic Yards $13.00 $1,170,000.00 2a. Federal ARRA Funded (First 45,000 Cubic Yards of Item No.2) 2b. Non-Federal Funded (Second 45,000 Cubic Yards of Item No.2)
3 Dredging, D102 w/Placement at F105 & 106 460,000 Cubic Yards $8.00 $3,680,000.00 3a. Federal CG Funded (First 230,000 Cubic Yards of Item No.3) 3b. Non-Federal Funded (Second 230,000 Cubic Yards of Item No.3)
4 Dredging, D103 w/Placement at F103 90,000 Cubic Yards $15.00 $1,350,000.00 4a. Federal ARRA Funded (First 45,000 Cubic Yards of Item No.4) 4b. Non-Federal Funded (Second 45,000 Cubic Yards of Item No.4)
Sub-Total Turning Basin Deepening $9,600,000.00
5 Mobilization and Demobilization 1 Job Lump Sum $800,000.00
6 Steel Sheet Pile Wall 1 Job Lump Sum $3,250,000.00
7 Settlement Monitoring 1 Job Lump Sum $10,000.00
8 SWPPP Development & Compliance 1 Job Lump Sum $10,000.00
9 Dredging, D101 w/Placement at F102 15,000 Cubic Yards $12.00 $180,000.00
10 Dredging, D108 w/Placement at F104, F105, & F106 200,000 Cubic Yards $7.50 $1,500,000.00
11 Furnish Concrete Piles 9,000 Linear Feet $100.00 $900,000.00
12 Drive Concrete Piles 88 Each $3,000.00 $264,000.00
13 Storm Drain System 1 Job Lump Sum $900,000.00
14 Crushed Miscellaneous Base 15,000 Tons $15.00 $225,000.00
15 Asphalt Concrete 5,000 Tons $100.00 $500,000.00
16 Wick Drains 1,050,000 Linear Feet $0.50 $525,000.00
17 Quarry Run Rock 220,000 Tons $27.00 $5,940,000.00
18 Armor Stone 15,000 Tons $41.00 $615,000.00
19 Furnish and Place Pavement Markings & Signage 1 Job Lump Sum $55,000.00
Sub-Total Pier G North Slip Fill $15,674,000.00
Pier T, West Basin IR Site 7 Sediment Remediation
20 Mobilization and Demobilization 1 Job Lump Sum $1,300,000.00
21 IR Site 7 Demolition 1 Job Lump Sum $700,000.00
22 Barge Removal 1 Job Lump Sum $150,000.00
23 SWPPP Development and Compliance 1 Job Lump Sum $10,000.00
24 Dredging, D104/D105 w/Placement at F102/F103 587,000 Cubic Yards $15.00 $8,805,000.00
25 Hydroseeding 6 Acres $5,000.00 $30,000.00
26 Restoration & Repair of Temp Irrigation System 1 Job Lump Sum $70,000.00
27 Required Insurance 1 Job Lump Sum $20,000.00
28 On Site SUXOS Personnel 1 Job Lump Sum $375,000.00
Sub-Total West Basin IR Site 7 Sediment Clean-Up $11,460,000.00
Catalina Express Terminal Maintenance Dredging and Demolition
29 Mobilization and Demobilization 1 Job Lump Sum $50,000.00
30 Dredging, D106, w/Placement at F105 37,000 Cubic Yards $16.00 $592,000.00
31 Catalina Landing Demolition 1 Job Lump Sum $140,000.00
Sub-Total Catalina Express Terminal $782,000.00
Pier T, West Basin IR Site 7 Sediment Remediation
32 Additional Set-ups 5 Each $60,000.00 $300,000.00
33 Re-Dredging D104/D105 w/Placement at F102/F103 59,000 Cubic Yards $20.00 $1,180,000.00
34 Daily Stand-by Time 14 Days $50,000.00 $700,000.00
35 Hourly Stand-by Time 48 Hours $2,200.00 $105,600.00
Sub-Total West Basin IR Site 7 Sediment Clean-Up (Option) $2,285,600.00
TOTAL BID AMOUNT $39,801,600.00
PROJECTS, LOS ANGELES COUNTY, CA
BID OPENING DATE: 18 SEP 2009
UNRESTRICTED-10% HUBZONE PREF
7 AMENDMENTS
DUTRA DREDGING COMPANY
2350 Kerner Boulevard., Suite 200
San Rafael, CA 94901 415-258-6876
BASE BID ITEMS:
ITEM NO. DESCRIPTION ESTIMATED UNIT UNIT PRICE AMOUNT
QUANTITY
Port of Long Beach (Deepening)
1 Mobilization and Demobilization 1 Job Lump Sum $700,000.00 1a. Federal ARRA Funded (35% of Item No.1) 1b. Federal CG Funded (15% of Item No. 1) 1c. Non-Federal Funded (50% of Item No. 1)
2 Dredging, D102 w/Placement at F101 90,000 Cubic Yards $8.50 $765,000.00 2a. Federal ARRA Funded (First 45,000 Cubic Yards of Item No.2) 2b. Non-Federal Funded (Second 45,000 Cubic Yards of Item No.2)
3 Dredging, D102 w/Placement at F105 & 106 460,000 Cubic Yards $14.50 $6,670,000.00 3a. Federal CG Funded (First 230,000 Cubic Yards of Item No.3) 3b. Non-Federal Funded (Second 230,000 Cubic Yards of Item No.3)
4 Dredging, D103 w/Placement at F103 90,000 Cubic Yards $13.25 $1,192,500.00 4a. Federal ARRA Funded (First 45,000 Cubic Yards of Item No.4) 4b. Non-Federal Funded (Second 45,000 Cubic Yards of Item No.4)
Sub-Total Turning Basin Deepening $9,327,500.00
5 Mobilization and Demobilization 1 Job Lump Sum $1,140,000.00
6 Steel Sheet Pile Wall 1 Job Lump Sum $4,200,000.00
7 Settlement Monitoring 1 Job Lump Sum $21,000.00
8 SWPPP Development & Compliance 1 Job Lump Sum $10,000.00
9 Dredging, D101 w/Placement at F102 15,000 Cubic Yards $8.50 $127,500.00
10 Dredging, D108 w/Placement at F104, F105, & F106 200,000 Cubic Yards $14.50 $2,900,000.00
11 Furnish Concrete Piles 9,000 Linear Feet $120.00 $1,080,000.00
12 Drive Concrete Piles 88 Each $4,850.00 $426,800.00
13 Storm Drain System 1 Job Lump Sum $1,220,000.00
14 Crushed Miscellaneous Base 15,000 Tons $16.10 $241,500.00
15 Asphalt Concrete 5,000 Tons $90.00 $450,000.00
16 Wick Drains 1,050,000 Linear Feet $0.46 $483,000.00
17 Quarry Run Rock 220,000 Tons $35.10 $7,722,000.00
18 Armor Stone 15,000 Tons $53.00 $795,000.00
19 Furnish and Place Pavement Markings & Signage 1 Job Lump Sum $38,500.00
Sub-Total Pier G North Slip Fill $20,855,300.00
Pier T, West Basin IR Site 7 Sediment Remediation
20 Mobilization and Demobilization 1 Job Lump Sum $3,225,000.00
21 IR Site 7 Demolition 1 Job Lump Sum $1,420,000.00
22 Barge Removal 1 Job Lump Sum $300,000.00
23 SWPPP Development and Compliance 1 Job Lump Sum $10,000.00
24 Dredging, D104/D105 w/Placement at F102/F103 587,000 Cubic Yards $9.25 $5,429,750.00
25 Hydroseeding 6 Acres $3,000.00 $18,000.00
26 Restoration & Repair of Temp Irrigation System 1 Job Lump Sum $94,200.00
27 Required Insurance 1 Job Lump Sum $1,350.00
28 On Site SUXOS Personnel 1 Job Lump Sum $100,000.00
Sub-Total West Basin IR Site 7 Sediment Clean-Up $10,598,300.00
Catalina Express Terminal Maintenance Dredging and Demolition
29 Mobilization and Demobilization 1 Job Lump Sum $1,150,000.00
30 Dredging, D106, w/Placement at F105 37,000 Cubic Yards $13.00 $481,000.00
31 Catalina Landing Demolition 1 Job Lump Sum $705,000.00
Sub-Total Catalina Express Terminal $2,336,000.00
Pier T, West Basin IR Site 7 Sediment Remediation
32 Additional Set-ups 5 Each $8,150.00 $40,750.00
33 Re-Dredging D104/D105 w/Placement at F102/F103 59,000 Cubic Yards $13.00 $767,000.00
34 Daily Stand-by Time 14 Days $38,500.00 $539,000.00
35 Hourly Stand-by Time 48 Hours $1,600.00 $76,800.00
Sub-Total West Basin IR Site 7 Sediment Clean-Up (Option) $1,423,550.00
TOTAL BID AMOUNT $44,540,650.00