AppR_Dredge Reporting Forms.pdf
PDF 47 KB Posted
- Solicitation number
- W912PL-09-B-0009
About this file
Appendix R Dredge Reporting Forms
View the file
Other files
Show all 45
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
APPENDIX R
DREDGE REPORTING FORMS
IR Site 7 Sediment Remediation, (HD-S2319)
ACOE PERMIT SPL-2007-00708-TS
CLAMSHELL/HOPPER DREDGING
DATE: DREDGE SITE: PIER T WEST BASIN
LOAD NUMBER: DISPOSAL SITE: NORTH SLIP FILL PIER G
DREDGING START TIME: DREDGING STOP TIME:
DISPOSAL START TIME: * DISPOSAL STOP TIME: *
FLOWBACK START TIME: FLOWBACK STOP TIME:
PORT STARBOARD
BARGE DRAFT AT START OF DISPOSAL TRIP: BOW
STERN
BARGE DRAFT ON ARRIVAL AT DISPOSAL SITE: BOW *
STERN *
COMMENTS:
DREDGING AND DISPOSAL OPERATIONS
Requirements Yes If No, Corrective Action Taken
Captain's License Present, *
ACOE Permit Present
Monitoring VHF Channels 13 & 16, *
Electronic Positioning System Functioning, *
Captain of the Port & Pilots Notified, *
Load Capacity Not Exceeded
No Solid Material in Flowback
* Information that is entered by the Contractor’s representative
To the best of my knowledge the information herein is true, accurate, and complete
Contractor’s Representative - Signature Contracting Officer Inspector - Signature
Contractor’s Representative - Printed Name Contracting Officer Inspector - Printed Name
EMERGENCY NOTIFICATIONS: POLB Security (562) 590-4185, USCG (310) 521-3815
R1
HYDRAULIC DREDGING
PIPELINE INTACT?, * DISPOSAL SITE:*
COMMENTS:
DREDGING AND DISPOSAL MONITORING
Direction and Speed of Current, *
General Weather Conditions and Wind Velocity
Appearance of Trash, Floatable Material, Grease, Oil or Oily Slick, or Other Objects
Tide Stage
Discoloration/Turbidity - Size of Plume &
Distance From Dredge or Barge
Odors
Depth of Dredge Operations
Amount of Material Dredged This Day (cy), *
Cumulative Amount Dredged, *
R2
RWQCB FILE 08-133
CLAMSHELL/HOPPER DREDGING
LOAD NUMBER: DISPOSAL SITE: * NORTH SLIP FILL PIER G
DISPOSAL START TIME: * DISPOSAL STOP TIME: *
DREDGING AND DISPOSAL MONITORING
Direction and Speed of Current, *
General Weather Conditions and Wind Velocity
Appearance of Trash, Floatable Material, Grease, Oil or Oily Slick, or Other Objects
Tide Stage
Discoloration/Turbidity - Size of Plume &
Distance From Dredge or Barge
Odors
Depth of Dredge Operations
Amount of Material Dredged This Day (cy), *
Cumulative Amount Dredged, *
R3
REPORT OF POSSIBLE VIOLATION OF
At approximately _______________________ on __________________, 2009, the following incident occurred in connection with the above dredging project:
The Government is investigating the circumstances surrounding this incident. In the event this incident is found to be a violation of the permit, the Government has taken the following steps to ensure compliance with the notification requirements of Special Conditions of the permit:
Reported incident to Army Corps of Engineers, Regulatory Branch at (805) 585-2146 at approximately _______________ on _______________, 2009, and
Spoke to ________________________________________
Left message
Sent fax to (805) 585-2154
AND
Reported incident to USEPA Region IX at (415) 972-3475 at approximately __________ on ______________, 2009, and
Spoke to ________________________________________
Left message
Sent fax to (415) 947-3537
DATE: ___________________________ INSPECTOR: _________________________________
R4