A02-Appendix_I_Master_Work_Plan.pdf

PDF 11 KB Posted

Attached to
Mark Twain Mowing Federal contract opportunity
Solicitation number
W912P9-17-R-0001
Issued by
Department of the Army Corps of Engineers Engineering District St Louis

About this file

APPENDIX I

View the file

Other files for this federal contract opportunity

Other files attached to Mark Twain Mowing, newest first.
File Type Posted
Amendment_0003.pdf PDF
049_Typical_Roadway_Mowing.pdf PDF
Contractor_Questions.pdf PDF
App_B_15-31_Mowing_Maps.7z 7Z file
Additional_Contractor_Questions.pdf PDF
051_HF_Lot_Locations.pdf PDF
App_B_32-45_Mowing_Maps.7z 7Z file
App_B_1-15_1.7z 7Z file
Appendix_A.pdf PDF
Summary_of_Changes.pdf PDF
050_Typical_Campsite.pdf PDF
048_Typical_HF_Lot.pdf PDF
App_B_1-14_Mowing_Maps.7z 7Z file
Contractor_Questions.pdf PDF
Attachment_1_Price_Schedule.pdf PDF
Revised_PWS_Amend_0003.pdf PDF
Amendment_0001.pdf PDF
A02-Appendix_A_Grounds_Description_Workload_Estimates.pdf PDF
A02-Appendix_G2_Accident_Prevention_Plan.pdf PDF
A02-Appendix_H_Vegetation_Control_Chart.pdf PDF
A02-Appendix_D_Definitions.pdf PDF
A02-Appendix_B_KEY.pdf PDF
A02-Appendix_C_Data_Requirements.pdf PDF
A02-Appendix_E_Vehicle_Signs.pdf PDF
A02-Appendix_F-2_Pesticide_Usage_Forms.pdf PDF
A02-Appendix_G3_Accident_Prevention_Plan.pdf PDF
A02-Appendix_F-1_Pesticide_Usage_Forms.pdf PDF
A02-Appendix_G2_Accident_Prevention_Plan.pdf PDF
A20_-_Attachment_2_Wage_Determination_15-2309.pdf PDF
A02-Appendix_(Combined)_B-1_-_B-53_Area_Maps_or_Site_Plans.pdf PDF
17_R_0001_Mark_Twain_Mowing.pdf PDF
A22-Attachment_1_-_Price_Schedule.xlsb XLSB spreadsheet
A02-_PWS_Mowing_Contract_2016_Mark_Twain_Lake_(4_0).pdf PDF
Show all 33

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

APPENDIX I

Master Work Plan (Appendix I)

The Master Work Plan shall include at a minimum the following:

1. The equipment and materials to be used,

2. The name and telephone number(s) of supervisor(s) to whom deficiencies should be reported,

3. The name(s) and telephone number(s) of supervisor(s) who can be contacted on a daily basis,

4. The telephone number(s) and mailing address of the Contractor through which he can normally be contacted on a daily basis,

5. The telephone number(s) where persons of authority within the Contractor’s organization can be reached during non-duty hours,

6. The Contractor’s Quality Control Plan including:

a. Identification of authorized Quality Control Inspectors (QCI), whose duty shall be to verify contractor compliance, their vehicles, and work/ inspection schedule.

b. An inspection method identifying deficiencies in the quality of services performed before the level of performance is unacceptable.

c. A method and response time for correcting minor deficiencies and unacceptable work that the Contractor is requested to re-perform.

d. Quality Control Report covering the bid items completed, which shall include, as a minimum, the following:

1. Inspector’s name

2. Contractor/contract number

3. Date

4. Time/Duration of inspection

5. Items/Areas inspected

6. Defects encountered

7. Corrective actions taken

8. Actions to prevent future occurrence

9. Safety/Security violations

10. Unusual conditions

(Note: Quality Control Report shall be maintained by the Contractor for the duration of the contract and may be requested by the Government at any time. The Quality Control Report shall be filled out by the Contractor representative during time of actual services. The Quality Control Report shall be submitted to the Government upon completion of each task order.)

7. The Contractor’s Accident Prevention Program, as required by EM 385-1-1, including:

a. The Administrative Plan, see Appendix E, and

b. The Activity Hazard Analysis, see Appendix E

The Contractor shall submit a Work Plan for each mowing cycle, which shall include, at a minimum the following: -

1. The number of employees and how employees are to be used,

2. The work schedule of each crew,

3. The schedule of work for each contract area including expected dates and times of work to be performed.

APPENDIX I

4. The cell phone number of the Contractor and the Contractor’s supervisor.