W912P6-14-B-0011-0006.pdf
PDF 20 KB Posted
- Attached to
- Permanent Barrier I Building Federal contract opportunity
- Solicitation number
- W912P6-14-B-0011
About this file
Amendment 0006 to Solicitation W912P6-14-B-0011
View the file
Other files for this federal contract opportunity
Show all 20
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
W81G6641567706
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print)
30-105-04EXCEPTION TO SF 30
APPROVED BY OIRM 11-84
STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA
FAR (48 CFR) 53.243
SUBJECT: W912P6-14-B-0011, "Chicago Sanitary and Ship Canal (CSSC) Permanent Barrier I, Project-B Building"
IMPORTANT NOTE TO BIDDERS: This amendment revises Draw ing Sheets referred to on Page 2, "SUMMARY OF CHANGES." How ever, the USACE w ill not be issuing hard copies of the corrected pages. The USACE w ill incorporate the revised Draw ing Sheets via the conformed contract set, w hich w ill be in agreement w ith the revisions described herein.
CONTINUED ON THE NEXT PAGE
1. CONTRACT ID CODE PAGE OF PAGES
J 1 2
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
16C. DATE SIGNED
BY 17-Sep-2014
16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR
(Signature of Contracting Officer)(Signature of person authorized to sign)
8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X W912P6-14-B-0011
X 9B. DATED (SEE ITEM 11)
12-Aug-2014
10B. DATED (SEE ITEM 13)
9A. AMENDMENT OF SOLICITATION NO.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.
Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:
(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN
REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE
CONTRACT ORDER NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
10A. MOD. OF CONTRACT/ORDER NO.
2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)
6. ISSUED BY
3. EFFECTIVE DATE
17-Sep-2014
CODE
U. S. ARMY ENGINEER DISTRICT, CHICAGO
231 SOUTH LASALLE STREET SUITE 1500
CHICAGO IL 60604-1437
W912P6 7. ADMINISTERED BY (If other than item 6)
4. REQUISITION/PURCHASE REQ. NO.
CODE
See Item 6
FACILITY CODECODE
EMAIL:TEL:
W912P6-14-B-0011
SECTION SF 30 BLOCK 14 CONTINUATION PAGE
The following items are applicable to this modification:
SUMMARY OF CHANGES
1. CONTRACTOR INQUIRIES: The following are USACE answers to Contractor inquiries:
a. Q: Looking at Drawing A-001 the window info remains the same - Is this correct? Charge weight and standoff distance once evaluated are outside of ASTM standard.
A: Yes, please bid to current Drawing Sheet A-001 and Specification 08 56 53 – BLAST
RESISTANT TEMPURED GLASS WINDOWS.
b. Q: The architect/engineer still has not answered the question regarding the order of operations for the clean agent system. We have been referred to page FA601 on (2) different occasions and that sheet does not answer the question.
A: Please reference the matrix on Drawing Sheet FA-601. The sequence of operations shall follow the columns A through R (from left to right) as laid out on the top of the matrix.
2. SUMMARY OF CHANGES: Contractors shall note that the below listed Drawing Sheet revisions will be incorporated in the conformed Contract Drawing Plan Set.
a. M-001 - Note 27. All rigid ductwork shall be sealed to SMACNA Seal Class A requirement.
b. M-001 – Water gauge pressure classification shall be added to the legend stating SMACNA
Transition from 2” to 1” Water gauge pressure classification.
c. M-104 – Water gauge pressure classification shall be revised from 1 to 2, to 2 to 1 on VAV/8.
d. M-108 – Note will be added stating: Ductwork shall be constructed to SMACNA 1” W.G.
pressure classification for Control and Security Ductwork Layout
e. M-108 – Note will be added stating: Ductwork shall be constructed to SMACNA 2” W.G.
pressure classification for Server Room Supply and Return Air Ductwork Layout
f. M-108 – Note will be added stating: Ductwork in the pulser and spang room shall be constructed to SMACNA 1” W.G. pressure classification
g. M-105, 106, 107 – A note shall be added and read “Flex duct shall note exceed 5’ of length fully stretched. Flex duct shall not be used in lieu of fittings.
(End of Summary of Changes)
File details come from the government source that posted it. Updated .