W912P525RA001 Amendment 0007 Changes_10JUL2025.pdf

PDF 147 KB Posted

Attached to
Chickamauga Lock Replacement Approach Wall and Decommissioning Federal contract opportunity
Solicitation number
W912P525RA001
Issued by
Department of the Army Corps of Engineers Engineering District Nashville

About this file

This document is Amendment 0007 to a federal solicitation (W912P525RA001) for the Chickamauga Lock Approach Wall and Decommissioning Project by the U.S. Army Corps of Engineers Nashville District. The amendment updates multiple technical specifications and contract documents, including revisions to sections covering price and payment procedures, special project procedures, quality control, commissioning, site development, concrete materials and placement, painting, instrumentation, electrical systems, and asphalt road construction.

The project involves constructing river and middle approach walls downstream from an existing lock, decommissioning the existing lock, wet commissioning of a new lock chamber, and site restoration. The estimated project price range is between $250,000,000 and $500,000,000, with anticipated award in the Fourth Quarter of Fiscal Year 2025. The contract will have a base and three options, is classified under NAICS code 237990 for Heavy and Civil Engineering Construction, and is set for full and open competition. Downstream approach walls will use pre-cast concrete beams fabricated in 2012, and the project includes constructing two 30-foot diameter mooring cells, plugging lock chamber culverts with concrete, and removing miscellaneous equipment and buildings.

View the file

Other files for this federal contract opportunity

Other files attached to Chickamauga Lock Replacement Approach Wall and Decommissioning, newest first.
File Type Posted
W912P525RA001 A0007 SF 30_Final_15July2025.pdf PDF
CKL Approach Wall and Decommissioning Price Schedule_11JULY2025.xlsx XLSX spreadsheet
CKL Approach Wall and Decommissioning Price Schedule_11JUNE2025.xlsx XLSX spreadsheet
Instructions to Offerors and Procedures for Submission of Offerors and Proposal Evaluation Approach_REV2.pdf PDF
W912P525RA001 A0006 SF 30_Final_17June2025.pdf PDF
W912P525RA001 Amendment 0006 Changes_11Jun2025.pdf PDF
W912P525RA001 A0005 SF 30_Final_16May2025.pdf PDF
CKL Approach Wall and Decommissioning_ 04292025.xlsx XLSX spreadsheet
W912P525RA001 A0004 SF30_final 13May2025.pdf PDF
02APR25 pre-proposal site visit 2 sign in sheets.pdf PDF
W912P525RA001 Amendment 0004 Changes_29Apr2025.pdf PDF
W912P525RA001 A0003 SF30_final 01Apr2025.pdf PDF
W912P525RA001 Amendment 0003 Changes_Updated 28MAR2025.pdf PDF
CKL Approach Wall and Decommissioning_ 03282025.xlsx XLSX spreadsheet
Chickamauga Lock AWD Physical Site Visit Sign-In Sheet (04Mar2025).pdf PDF
W912P525RA001 A0002 SF30_final 20 Mar 25.pdf PDF
Chickamauga Lock AWD RFP Amendment 0002 Letter_signed ssw.pdf PDF
CKL Approach Wall and Decommissioning_2025-02-13.xlsx XLSX spreadsheet
W912P525RA001 A0001 SF 30_final 20 Feb 25.pdf PDF
W912P525RA001 Amendment 0001 Changes_20Feb2025.pdf PDF
Instructions to Offerors and Procedures for Submission of Offerors and Proposal Evaluation Approach_REV1.pdf PDF
CKL Approach Wall and Decommissioning_Virtual Pre-Proposal Meeting Attendee List.xlsx XLSX spreadsheet
Watts Bar Map.pdf PDF
CKL Approach Wall and Decommissioning.xlsx XLSX spreadsheet
US Citizens Security Access Form.pdf PDF
W912P525RA001_final_04Feb2025.pdf PDF
Instructions to Offerors and Procedures for Submission of Offerors and Proposal Evaluation Approach.pdf PDF
DBA WD TN20250145 03Jan2025 (Hamilton County TN Heavy Construction).pdf PDF
Foregin National Contractor Security Access Form.pdf PDF
JA for Brand Name CKL AWD_signed ssw_Redacted.pdf PDF
Show all 30

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

W912P525RA001

AMENDMENT 0007

Chickamauga Lock Approach Wall and Decommissioning

DESCRIPTION OF CHANGES

QUESTIONS

Government answers to questions received from Industry have been provided in Projnet Bidder Inquiry.

AMENDMENT 0006 CHANGES SHEET

Folio No. 5 - Contract Drawing 66W353-AWD “Exterior Elevations” was inadvertently included on the Amendment 0006 Changes Sheet as being revised and this should be ignored for Amendment 0006. This sheet was not revised in Amendment 0006, this drawing sheet was only revised via Amendment 0004.

TECHNICAL SPECIFICATIONS

All revised Specifications, new specifications, revised appendices, and new appendices have been merged into a single document (W912P5-25-R-A001_Am7_Contract Specifications_10JUL25)

1. SECTION 01 22 00 – PRICE AND PAYMENT PROCEDURES

a. Section 01 22 00 has been removed in its entirety and replaced with a revised Section 01 22 00.

i. Paragraph 1.3.3 Lead and Asbestos Abatement has been revised.

ii. Paragraph 1.4.2.19 “Demolition of Spillway Deck and Piers” has been revised.

iii. Paragraph 1.4.2.20 “Demolition and Disposal of Spillway Gate Sets” has been revised.

iv. Paragraph 1.4.2.21 “Demolition of Existing Lock Machinery” has been revised.

v. Paragraph 1.4.2.22 “Demolition of Existing Lock Operation’s Building” has been revised.

vi. Section 1.4.2.31 “Remediation and Restoration of the Electrical Service Room” has been revised.

vii. Paragraph 1.4.2.32 “Remediation and Restoration of the Hazmat Room” has been revised.

viii. The title of Paragraph 1.4.6.5 has been revised to add “Yellow”.

ix. Paragraph 1.4.6.6 “Painting – Approach Wall Beams – Touch Up” has been added.

2. SECTION 01 35 13 – SEPCIAL PROJECT PROCEDURES

a. Section 01 35 13 has been removed in its entirety and replaced with a revised Section 01 35 13.

i. Paragraph 1.5.3 Specific Sequencing has been revised.

3. SECTION 01 45 00 – QUALITY CONTROL

a. Section 01 45 00 has been removed in its entirety and replaced with a revised Section 01 45 00.

i. Paragraph 1.8.4.2 “Responsibilities” has been revised.

4. SECTION 01 91 13 – GENERAL COMMISSIONING

a. Section 01 91 13 has been removed in its entirety and replaced with a revised Section 01 91 13.

i. Clarified commissioning requirements for systems that are primarily GCFI and the contractor shall only provide limited material support for.

ii. Clarified the Commissioning Firm attendance for factory testing and training.

iii. Clarified the subcontracting relationship requirements for both electrical and mechanical commissioning and testing specialists.

5. SECTION 02 41 13 – SITE DEVELOPMENT DEMOLITION WORK AND RESTORATION

a. Section 02 41 13 has been removed in its entirety and replaced with a revised Section 02 41 13.

i. Paragraph 3.1.7 “Fixtures” has been added.

6. SECTION 03 30 01 – CONCRETE: MATERIALS

a. Section 03 30 01 has been removed in its entirety and replaced with a revised Section 03 30 01.

i. Paragraph 3.3.2.3.b “Frequency of Quality Tests” has been revised.

7. SECTION 03 30 02 – CONCRETE: MISTURE PROPORTIONING

a. Section 03 30 02 has been removed in its entirety and replaced with a revised Section 03 30 02.

i. Paragraph 1.5.1 “Concrete Mix Definitions” has been revised.

8. SECTION 03 30 04 – CONCRETE PLACEMENT REQUIREMENTS

a. Section 03 30 04 has been removed in its entirety and replaced with a revised Section 03 30 04.

i. Paragraph 3.7 “Hot Weather Requirements” has been revised.

9. SECTION 03 70 00 – CONCERETE: STRUCTURAL

a. Section 03 70 00 has been removed in its entirety and replaced with a revised Section 03 70 00.

i. Paragraph 1.6.2 “Pumpable Structural Concrete for the Bay 5 Shear Wall (Mix 7)” has been revised.

10. SECTION 09 97 02 – PAINTING: HYDRAULIC STRUCTURES

a. Section 09 97 02 has been removed in its entirety and replaced with a revised Section 09 97 02.

i. Paragraph 3.5 “Painting Schedules” has been revised.

11. SECTION 13 50 00 – INSTRUMENTATION

a. Section 13 50 00 has been removed in its entirety and replaced with a revised Section 13 50 00.

i. Paragraph 1.2.1 “Existing Segmental and Cellular Cofferdam Components” has been revised.

12. SECTION 26 20 00 – INTERIOR DISTRIBUTION SYSTEMS

a. Section 26 20 00 has been removed in its entirety and replaced with a revised Section 26 20 00.

i. Product and installation requirements for limit switches for the public address system pull chain stations have been added.

13. SECTION 32 12 16 – HOT-MIX ASPHALT HMA for ROADS

a. Section 32 12 16 has been removed in its entirety and replaced with a revised Section 32 12 16.

i. Paragraph 1.1 “Scope” has been added.

ii. Paragraph 2.2.4 and Table 4 have been revised.

iii. Paragraph 2.4 has been revised.

14. SUBMITTAL REGISTER

a. The Submittal Register has been removed for the sections that were changed and replaced with a revised submittal register.

CONTRACT DRAWINGS

The following contract drawing sheets were removed and replaced with revised contract drawing sheets:

1. Folio No. 1

a. 61W510-02-AWD “Construction Limits – Lay Down Areas”

b. 61W510-02D-AWD “Contract Base and Option – General Delineation”

c. 61W530-28-AWD “Slot Cutting Details – Sheet 2 of 2”

d. 61W530-43-AWD “Decommissioning Plans – Sheet 2 of 3”

e. 61W530-44-AWD “Decommissioning Plans – Sheet 3 of 3”

f. 61W530-51-AWD “Removal of Visitors Overlook and Oil Storage Building”

g. 61W530-54-AWD “Hazmat Storage Room”

2. Folio No. 2

a. 61W20-22-AWD “Folio 2 Drawing Index Site Development”

b. 61W510-02-AWD “Construction Limits – Lay Down Areas”

c. 61W510-02D-AWD “Contract Base and Option – General Delineation”

d. 61W525-01-AWD “Existing Site - Orientation”

e. 61W525-08-AWD “Existing Site - Orientation”

3. Folio No. 3

a. 15W275-AWD “Facilities Site – Power Plan”

b. 15W277-AWD “Facilities Site – Lighting Plan”

c. 15W278-AWD “Maintenance Storage Building and Electrical Service Rooms Plan”

d. 65W211D-AWD “Electrical – General Notes and Legend”

e. 65W812-AWD “Details and Section - Sheet 3 of 4”

f. 65W815-AWD “Raceway Schedule – Sheet 1 of 7”

g. 65W819-AWD “Raceway Schedule – Sheet 5 of 7”

h. 65W819A-AWD “Raceway Schedule – Sheet 6 of 7”

i. 65W870-AWD “Approach Wall Plans – Sheet 1 of 3”

j. 65W871-AWD “Approach Wall Plans – Sheet 2 of 3”

k. 65W872-AWD “Approach Wall Plans – Sheet 3 of 3”

l. 65W913-AWD “Misc. Schematic Diagram - Sheet 2 of 2”

m. 65W2701 “IP/PBX Bock Diagram”

n. 65W2702-AWD “Telco Riser Diagram”

o. 65W2705-AWD “External Paging System – Plans”

p. 65W2706-AWD “External Paging System – Bloc Diagram”

q. 65W2707-AWD “External Paging System – Details”

r. 65W2708-AWD “Communications – Cable Schedule – Sheet 1 of 2”

s. 65W2758-AWD “Facilities Site IDS Riser Diagram”

t. 65W3728-AWD “Approach Wall Partial Plans – Sheet 1 of 3”

u. 65W3729-AWD “Approach Wall Partial Plans – Sheet 2 of 3”

v. 65W3730-AWD “Approach Wall Partial Plans – Sheet 3 of 3”

The following contract drawing sheets were added to the set of contract drawings:

1. Folio 2

a. 61W525-08-AWD “TVA Power Break Existing Condition”

PRICE BREAKOUT SCHEDULE

1. Base Contract:

a. Contract Line Item 00-B006 “Lab Testing – Direct Shear” has been revised to update the quantity to 6 “each”.

b. Contract Line Item 00-E002 “Painting – Upstream Approach Wall Beams” title has been updated to “Painting – Upstream Approach Wall Beams – Yellow”.

c. Contract Line Item 00-E003 “Painting – Approach Wall Beams -Touch Up” has been added with a quantity of 445 “SF”.

2. Option 1:

a. Contract Line Item 01-Q002 “Lab Testing – Direct Shear” has been revised to update the quantity to

14 “each”.

b. Contract Line Item 01-T002 “Painting – Approach Wall Beams” has been added with a quantity of

772 “SF”.

FAR CLAUSES

1. DFARS 252.236-7001:

a. DFARS Clause 252.236-7001, Contract Drawings and Specifications has been revised.

2. FAR 52.252-3:

a. FAR Provision 52.252-3, Alterations in Solicitation, has been revised.