This is a detailed pricing schedule spreadsheet for the Chickamauga Lock Replacement Approach Wall and Decommissioning project, containing line item pricing for a base contract and three options. The base contract includes general requirements, existing conditions work, concrete work, metals, electrical systems, and waterway construction items. Option 1 focuses on downstream approach wall construction for the landside wall. Option 2 covers mooring cell construction and cofferdam removal. Option 3 encompasses lock decommissioning activities, site restoration, and utility work.
The related contract opportunity indicates this is a full and open competition with an estimated price range of $250-500 million, to be awarded in Q4 FY2025 under NAICS 237990. The project requires a Project Labor Agreement and involves constructing river and middle approach walls, decommissioning the existing lock, wet commissioning of the new lock chamber, and site restoration in Chattanooga, TN. A pre-proposal site visit is scheduled for February 20, 2025. The contract will use pre-cast concrete beams fabricated in 2012 currently stored at another TVA facility. Key work includes building two 30-foot diameter mooring cells, plugging the existing lock chamber with concrete, installing a concrete thrust block, and removing miscellaneous equipment and buildings.
View the file
Other files for this federal contract opportunity
Show all 30
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Base Price Schedule
| PRICE SCHEDULE | ||||||
| Approach Wall and Lock Decommissioning | ||||||
| Chickamauga Lock Replacement | ||||||
| Ready to Advertise (RTA) | ||||||
| New AWD Bid Sheet | ||||||
| Base Contract | ||||||
| BID ITEM | DESCRIPTION | SPECIFICATION NUMBER | EST. QTY. | UNIT | UNIT | |
| PRICE | ESTIMATED |
AMOUNT
| 01 | Div 01 GENERAL REQUIREMENTS | |||||
| 00-A001 | Formal Partnering Meeting | 01 00 00 | 1 | JB | $ | $ |
| 00-A002 | Mobilization and Demobilization | 01 22 00 | 1 | JB | $ | $ |
| 00-A003 | Premiums for Performance and Payment Bonds | 01 22 00 | 1 | JB | $ | $ |
| 00-A004 | Railroad Flagman | 01 22 00 | 6 | DAY | $ | $ |
| 00-A005 | Data Management | 01 31 00 | 1 | JB | $ | $ |
| 00-A006 | Maintenance and Protection of Traffic | 01 50 00 | 1 | JB | $ | $ |
| 00-A007 | Maintain QA Testing Lab and QA Field Office | 01 50 00 | 36 | MO | $ | $ |
| 00-A008 | Diversion and Care of Water | 01 57 24 | 1 | JB | $ | $ |
| 00-A009 | As-Built Drawings | 01 78 00 | 1 | JB | $ | $ |
| 00-A010 | Commissioning | 01 91 13 | 1 | JB | $ | $ |
| 00-A011 | Commissioning - Performance Verification Testing | 01 91 13 | 1 | JB | $ | $ |
| 00-A012 | Commissioning - Post Construction Endurance Testing | 01 91 13 | 1 | JB | $ | $ |
| 02 | Div 02 EXISTING CONDITIONS | |||||
| 00-B001 | Overburden Drilling | 02 32 00 | 200 | LF | $ | $ |
| 00-B002 | Overburden Drilling - OVER 200 LF | 02 32 00 | 100 | LF | $ | $ |
| 00-B003 | Overburden - Split Spoon Sampling | 02 32 00 | 135 | EA | $ | $ |
| 00-B004 | Verification Core Drilling, Vertical Holes HQ | 02 32 00 | 72 | LF | $ | $ |
| 00-B005 | Core Drilling, Vertical Holes | 02 32 00 | 125 | LF | $ | $ |
| 00-B006 | Lab Testing- Direct Shear | 02 32 00 | 20 | EA | $ | $ |
| 00-B007 | Downhole Imaging | 02 32 00 | 290 | LF | $ | $ |
| 00-B008 | Downhole Imaging - OVER 290 LF | 02 32 00 | 100 | LF | $ | $ |
| 00-B009 | Segmental Cofferdam Modifications - Standard Light and Fixture Removal, and instrumentation | 02 41 13 and 02 41 17 | 1 | JB | $ | $ |
| 00-B010 | Demolition of Spillway Deck and Piers | 02 41 17 | 1 | JB | $ | $ |
| 00-B011 | Demolition and Disposal of Spillway Gate Set - Bay 5 | 02 41 17 | 1 | EA | $ | $ |
| 00-B012 | Removal of Spillway Gate Sets (4) and Disposal of Gate Sets (2) to Include Salvaging Components | 02 41 17 | 4 | EA | $ | $ |
| 00-B013 | Cofferdam Removal - Phase 1 (Drawing 61W510-11) | 02 41 18 | 1 | JB | $ | $ |
| 00-B014 | Downstream Cofferdam Stability Berm Removal and Downstream approach material removal | 02 41 18 | 1 | JB | $ | $ |
| 00-B015 | Watertightness Testing of Rock Prior to Excavation for Thrust Block | 02 32 00 | 1 | JB | $ | $ |
| 03 | Div 03 CONCRETE | ||||||
| 00-C001 | Waterstop | 03 15 14 | 1 | JB | $ | $ | |
| 00-C002 | Reinforcing Steel - Material | 03 20 02 | 100 | Ton | $ | $ | |
| 00-C003 | Place Rebar | 03 20 02 | 100 | Ton | $ | $ | |
| 00-C004 | Drill and Grout #11 Dowels; Monolith M1 Second Placement | 03 20 02 | 25 | EA | $ | $ | |
| 00-C005 | Cement, Type II, MH - Low Alkali and Moderate Heat | 03 30 01 | 1200 | Ton | $ | $ | |
| 00-C006 | Class F Fly Ash | 03 30 01 | 900 | Ton | $ | $ | |
| 00-C007 | Tremie Concrete (5ksi) | 03 31 07 | 2000 | CY | $ | $ | |
| 00-C008 | Downstream Government Directed Additional Tremie Concrete | 03 31 07 | 35 | CY | $ | $ | |
| 00-C009 | Downstream Install Precast Beams and Appurtenances - Riverside Wall | 03 41 34 | 1 | JB | $ | $ | |
| 00-C010 | Upstream Install Precast Beams and Appurtenances | 03 41 34 | 1 | JB | $ | $ | |
| 00-C011 | Upstream Skirt Panels and Appurtenances | 03 41 34 | 1 | JB | $ | $ | |
| 00-C012 | Structural Concrete (5ksi) | 03 70 00 | 2000 | CY | $ | $ | |
| 00-C013 | Pier Concrete (5.5ksi) | 03 80 00 | 2395 | CY | $ | $ | |
| 00-C014 | Precast Beams Non-destructive Testing (Riverside and Landside walls) | 03 41 34 | 1 | JB | $ | $ | _____________ |
| 00-C015 | Precast Beams Crack Repair - Riverside Wall | 03 41 34 | 1600 | LF | $ | $ | _____________ |
| 00-C016 | Precast Beams Defect Repair - Riverside Wall | 03 41 34 | 1600 | SF | $ | $ | _____________ |
| 00-C017 | Precast Beams Surface Coating - Riverside Wall | 03 41 34 | 36000 | SF | $ | $ | _____________ |
| 00-C018 | Block 45 Stairs - Construct Landing and Install Precast Stairs | 03 70 00 | 1 | JB | $ | $ | _____________ |
| 05 | Div 05 METALS | |||||
| 00-D001 | Spillway Operating Deck Access Stairway | 05 51 00 | 1 | JB | $ | $ |
| 00-D002 | Crane Stops | 05 50 14 | 1 | JB | $ | $ |
| 00-D003 | Nose Pier and Intermediate Pier Metals - Riverside Wall | 05 59 20 | 1 | JB | $ | $ |
| 00-D004 | Steel Setting Piles - Riverside Wall | 05 50 14 | 385 | LF | $ | $ |
| 00-D005 | Miscellaneous Metal | 05 50 15 | 1 | JB | $ | $ |
| 00-D006 | Wall Armor | 05 50 15 | 1 | JB | $ | $ |
| 00-D007 | Prefabricated Guardrail Installation | 05 50 15 | 450 | LF | $ | $ |
| 09 | Div 09 FINISHES | |||||
| 00-E001 | Painting - Upstream Approach Wall Nose Pier Stripes | 09 97 00 | 1 | JB | $ | $ |
| 10 | Div 10 SPECIALTIES | |||||||
| 00-F001 | Permanent Exterior Signage | 10 14 03 and 10 14 04 | 1 | JB | $ | $ | ||
| 00-F002 | Fire Sprinkler System | 10 44 17 | 1 | JB | $ | $ | ||
| 00-F003 | Plumbing System | 10 44 17 | 1 | JB | $ | $ | ||
| 00-F004 | Operations Building Commissioning | 10 44 17 | 1 | JB | $ | $ | ||
| 00-F005 | Temporary pump for fire protection system | 1 | JB | $ | ||||
| . | ||||||||
| 13 | Div 13 SPECIAL CONSTRUCTION | |||||||
| 00-G001 | Instrumentation Installation and Commissioning | 13 50 00 | 1 | JB | $ | $ | ||
| 00-G002 | Instrumentation Monitoring Program | 13 50 00 | 36 | MO | $ | ___________________________ | $ | _______________ |
| 26 | Div 26 ELECTRICAL | |||||
| 00-H001 | Replacement Lock Upstream Approach Wall Electrical Systems | 26 20 00 | 1 | JB | $ | $ |
| 00-H002 | Replacement Lock Downstream Approach Wall Electrical Systems - Riverside Wall | 26 20 00 | 1 | JB | $ | $ |
| 00-H003 | Post-Spillway Demolition Grounding System Connection | 26 20 00 | 1 | JB | $ | $ |
| 00-H004 | Post-Spillway Demolition Electrical Systems Repair | 26 20 00 | 1 | JB | $ | $ |
| 00-H005 | Replacement Lock Exterior Lighting | 26 56 00 | 1 | JB | $ | $ |
| 00-H006 | Power System Study | 26 05 73 | 1 | JB | $ | $ |
| 28 | Div 28 ELECTRONIC SAFETY AND SECURITY | |||||
| 00-J001 | Security CCTV System | 28 23 23 | 1 | JB | $ | $ |
| 31 | Div 31 EARTHWORK | |||||
| 00-K001 | Install Downstream Approach Wall Intermediate Piers - Riverside Wall | 31 32 23 | 2 | EA | $ | $ |
| 00-K002 | Install Downstream Approach Wall Nose Piers - Riverside Wall | 31 32 23 | 1 | EA | $ | $ |
| 00-K003 | 48" Downstream Approach Wall Pier Guide Pipe Pile Rock Sockets - Riverside Wall | 31 63 28 | 145 | LF | $ | $ |
| 00-K004 | Furnish and Install Post Tensioned Anchors | 31 68 15 | 3040 | LF | $ | $ |
| 00-K005 | Additional Performance Tests | 31 68 15 | 3 | EA | $ | $ |
| 00-K006 | Additional Proof Tests | 31 68 15 | 3 | EA | $ | $ |
| 00-K007 | Additional Watertightness Testing | 31 68 15 | 16 | EA | $ | $ |
| 00-K008 | Consolidation Grouting | 31 68 15 | 2337 | CF | $ | $ |
| 00-K009 | Redrilling Consolidation Grout | 31 68 15 | 1952 | LF | $ | $ |
| 00-K010 | Government Requested Standby - Consolidation Grouting | 31 68 15 | 32 | HR | $ | $ |
| 00-K011 | Supplementary Extended Creep Tests | 31 68 15 | 4 | EA | $ | $ |
| 00-K012 | Earth Retention System for Thrust Block - Design | 31 23 05 | 1 | JB | $ | $ |
| 32 | Div 32 EXTERIOR IMPROVEMENTS | |||||
| 00-L001 | Flagpole Construction | Various | 1 | JB | $ | $ |
| 33 | Div 33 UTILITIES | |||||
| 00-M001 | Medium Voltage Distribution - Bay 5 to Lock | 33 71 02 | 1 | JB | $ | $ |
| 00-M002 | 2-inch Tempoary Domestic Water Line for Operations Building (routed across channel) | 33 11 00 | 1 | JB | $ | $ |
| 00-M003 | 8-inch Temporay Fire Protection Line for Operations Building (routed across channel) | 33 11 00 | 1 | JB | $ | $ |
| 00-M004 | Temporary sanitary sewer facility for Operations Building (Contractor determined/provided) | 33 11 00 | 1 | JB | $ | $ |
| 00-M005 | Temporary FDC Connection for Ops Building | 33 11 00 | 1 | EA | $ | $ |
| 00-M006 | Fire Hydrant Assembly | 33 11 00 | 1 | EA | $ | $ |
| 35 | Div 35 WATERWAY AND MARINE CONSTRUCTION | |||||
| 00-N001 | Tow Haulage Systems - Procurement of all tow haulage components | 35 01 41 | 1 | JB | $ | $ |
| 00-N002 | Tow Haulage Installation and Acceptance Test - Upstream | 35 01 41 | 1 | JB | $ | $ |
| 00-N003 | Lock Machinery | 35 08 40 | 1 | JB | $ | $ |
| 00-N004 | Floating Mooring Bitts | 35 08 40 | 1 | JB | $ | $ |
| 00-N005 | Compressed Air System | 35 08 40 | 1 | JB | $ | $ |
| 00-N006 | Miter Gate Spray System | 35 08 40 | 1 | JB | $ | $ |
| 00-N007 | Service Water System | 35 08 40 | 1 | JB | $ | $ |
| 00-N008 | Lock Gallery Sump Pump System | 35 08 40 | 1 | JB | $ | $ |
| 00-N009 | Downstream Pier Excavation | 35 20 24 | 450 | CY | $ | $ |
TOTAL ESTIMATED AMOUNT $
Page &P of &N
Option 1 Price Schedule
| PRICE SCHEDULE | ||||||
| Approach Wall and Lock Decommissioning | ||||||
| Chickamauga Lock Replacement | ||||||
| Ready to Advertise (RTA) | ||||||
| New AWD Bid Sheet | ||||||
| Option 1 | ||||||
| BID ITEM | DESCRIPTION | SPECIFICATION NUMBER | EST. QTY. | UNIT | UNIT | |
| PRICE | ESTIMATED |
AMOUNT
| 01 | Div 01 GENERAL REQUIREMENTS | |||||
| 01-P001 | Formal Partnering Meeting | 01 00 00 | 1 | JB | $ | $ |
| 01-P002 | Mobilization and Demobilization | 01 22 00 | 1 | JB | $ | $ |
| 01-P003 | Premiums for Performance and Payment Bonds | 01 22 00 | 1 | JB | $ | $ |
| 01-P004 | Railroad Flagman | 01 22 00 | 6 | DAY | $ | $ |
| 01-P005 | Data Management | 01 31 00 | 1 | JB | $ | $ |
| 01-P006 | Maintenance and Protection of Traffic | 01 50 00 | 1 | JB | $ | $ |
| 01-P007 | Maintain QA Testing Lab and QA Field Office | 01 50 00 | 18 | MO | $ | $ |
| 01-P008 | As-Built Drawings | 01 78 00 | 1 | JB | $ | $ |
| 01-P009 | Commissioning | 01 91 13 | 1 | JB | $ | $ |
| 01-P010 | Helper Boat | 01 00 00 | 24 | MO | $ | $ |
| 02 | Div 02 EXISTING CONDITIONS | |||||
| 01-Q001 | Verification Core Drilling, Vertical Holes HQ | 02 32 00 | 168 | LF | $ | $ |
| 01-Q002 | Lab Testing- Direct Shear | 02 32 00 | 20 | EA | $ | $ |
| 01-Q003 | Protection Cell Removal | 02 41 18 | 1 | JB | $ | $ |
| 03 | Div 03 CONCRETE | |||||
| 01-R001 | Reinforcing Steel - Material | 03 20 02 | 115 | Ton | $ | $ |
| 01-R002 | Place Rebar | 03 20 02 | 115 | Ton | $ | $ |
| 01-R003 | Cement, Type II, MH - Low Alkali and Moderate Heat | 03 30 01 | 1500 | Ton | $ | $ |
| 01-R004 | Class F Fly Ash | 03 30 01 | 1250 | Ton | $ | $ |
| 01-R005 | Tremie Concrete (5ksi) | 03 31 07 | 4000 | CY | $ | $ |
| 01-R006 | Downstream Government Directed Additional Tremie Concrete | 03 31 07 | 65 | CY | $ | $ |
| 01-R007 | Downstream Install Precast Beams and Appurtenances - Landside Wall | 03 41 34 | 1 | JB | $ | $ |
| 01-R008 | Pier Concrete (5.5ksi) | 03 80 00 | 4100 | CY | $ | $ |
| 01-R009 | Precast Beams Crack Repair - Landside Wall | 03 41 34 | 2400 | LF | $ | $ |
| 01-R010 | Precast Beams Defect Repair - Landside Wall | 03 41 34 | 2400 | SF | $ | $ |
| 01-R011 | Precast Beams Surface Coating - Landside Wall | 03 41 34 | 54000 | SF | $ | $ |
| 05 | Div 05 METALS | |||||
| 01-S001 | Nose Pier and Intermediate Pier Metals - Landside Wall | 05 59 20 | 1 | JB | $ | $ |
| 01-S002 | Steel Setting Piles - Landside Wall | 05 50 14 | 815 | LF | $ | $ |
| 01-S003 | Miscellaneous Metal | 05 50 15 | 1 | JB | $ | $ |
| 01-S004 | Wall Armor | 05 50 15 | 1 | JB | $ | $ |
| 10 | Div 10 SPECIALTIES | |||||
| 01-T001 | Permanent Exterior Signage | 10 14 03 and 10 14 04 | 1 | JB | $ | $ |
| 13 | Div 13 SPECIAL CONSTRUCTION | |||||||
| 01-U001 | Instrumentation Monitoring Program | 13 50 00 | 1 | JB | $ | $ | ||
| 01-U002 | Instrumentation Installation | 13 50 50 | 18 | MO | $ | ___________________________ | $ | _______________ |
| 26 | Div 26 ELECTRICAL | |||||
| 01-V001 | Replacement Lock Downstream Approach Wall Electrical Systems - Landside Wall | 26 20 00 | 1 | JB | $ | $ |
| 01-V002 | Replacement Lock Exterior Lighting | 26 56 00 | 1 | JB | $ | $ |
| 28 | Div 28 ELECTRONIC SAFETY AND SECURITY | |||||
| 01-W001 | Lock Operations CCTV System | 28 23 23 | 1 | JB | $ | $ |
| 31 | Div 31 EARTHWORK | |||||
| 01-X001 | Install Downstream Approach Wall Intermediate Piers - Landside Wall | 31 32 23 | 6 | EA | $ | $ |
| 01-X002 | Install Downstream Approach Wall Nose Piers - Landside Wall | 31 32 23 | 1 | EA | $ | $ |
| 01-X003 | 48" Downstream Approach Wall Pier Guide Pipe Pile Rock Sockets - Landside Wall | 31 63 28 | 305 | LF | $ | $ |
| 35 | Div 35 WATERWAY AND MARINE CONSTRUCTION | |||||
| 01-Y001 | Tow Haulage Installation and Acceptance Test - Downstream | 35 01 41 | 1 | JB | $ | $ |
| 01-Y002 | Downstream Pier Excavation | 35 20 24 | 915 | CY | $ | $ |
| 01-Y003 | Service Water System - Downstream Approach Wall | 35 08 40 | 1 | JB | $ | $ |
TOTAL ESTIMATED AMOUNT $
Option 2 Price Schedule
| PRICE SCHEDULE | ||||||
| Approach Wall and Lock Decommissioning | ||||||
| Chickamauga Lock Replacement | ||||||
| Ready to Advertise (RTA) | ||||||
| New AWD Bid Sheet | ||||||
| Option 2 | ||||||
| BID ITEM | DESCRIPTION | SPECIFICATION NUMBER | EST. QTY. | UNIT | UNIT | |
| PRICE | ESTIMATED |
AMOUNT
| 01 | Div 01 GENERAL REQUIREMENTS | |||||
| 02-Z001 | Mobilization and Demobilization | 01 22 00 | 1 | JB | $ | $ |
| 02-Z002 | Premiums for Performance and Payment Bonds | 01 22 00 | 1 | JB | $ | $ |
| 02-Z003 | Data Management | 01 31 00 | 1 | JB | $ | $ |
| 02-Z004 | Maintenance and Protection of Traffic | 01 50 00 | 1 | JB | $ | $ |
| 02-Z005 | Maintain QA Testing Lab and QA Field Office | 01 50 00 | 12 | MO | $ | $ |
| 02-Z006 | As-Built Drawings | 01 78 00 | 1 | JB | $ | $ |
| 02 | Div 02 EXISTING CONDITIONS | |||||
| 02-AA01 | Demolition of Mooring Cells | 02 41 17 | 4 | EA | $ | $ |
| 02-AA02 | Cofferdam Removal - Phase 2 (Drawing 61W510-11) | 02 41 18 | 1 | JB | $ | $ |
| 03 | Div 03 CONCRETE | |||||
| 02-AB01 | Cement, Type II, MH - Low Alkali and Moderate Heat | 03 30 01 | 20 | Ton | $ | $ |
| 02-AB02 | Class F Fly Ash | 03 30 01 | 20 | Ton | $ | $ |
| 02-AB03 | Tremie Concrete (5ksi) | 03 31 07 | 90 | CY | $ | $ |
| 09 | Div 09 FINISHES | |||||
| 02-AC01 | Painting - Mooring Cells | 09 97 00 | 1 | JB | $ | $ |
| 10 | Div 10 SPECIALTIES | |||||
| 02-AD01 | Permanent Exterior Signage | 10 14 03 and 10 14 04 | 1 | JB | $ | $ |
| 13 | Div 13 SPECIAL CONSTRUCTION | |||||
| 02-AE01 | Instrumentation Monitoring Program | 13 50 00 | 12 | MO | $ | $ |
| 31 | Div 31 EARTHWORK | |||||
| 02-AF01 | Mooring Cell Aggregate Fill | 31 00 00 | 1 | JB | $ | $ |
| 02-AF02 | Redrilling Grouted Holes | 31 32 12 | 575 | LF | $ | $ |
| 02-AF03 | Metal Sheet Piling | 31 41 16 | 1 | JB | $ | $ |
| 02-AF04 | Construction of Mooring Cells | 31 41 16 | 2 | EA | $ | $ |
TOTAL ESTIMATED AMOUNT $
Option 3 Price Schedule
| PRICE SCHEDULE | ||||||
| Approach Wall and Lock Decommissioning | ||||||
| Chickamauga Lock Replacement | ||||||
| Ready to Advertise (RTA) | ||||||
| New AWD Bid Sheet | ||||||
| Option 3 | ||||||
| BID ITEM | DESCRIPTION | SPECIFICATION NUMBER | EST. QTY. | UNIT | UNIT | |
| PRICE | ESTIMATED |
AMOUNT
| 01 | Div 01 GENERAL REQUIREMENTS | |||||
| 03-AG01 | Formal Partnering Meeting | 01 00 00 | 1 | JB | $ | $ |
| 03-AG02 | Mobilization and Demobilization | 01 22 00 | 1 | JB | $ | $ |
| 03-AG03 | Premiums for Performance and Payment Bonds | 01 22 00 | 1 | JB | $ | $ |
| 03-AG04 | Data Management | 01 31 00 | 1 | JB | $ | $ |
| 03-AG05 | Maintenance and Protection of Traffic | 01 50 00 | 1 | JB | $ | $ |
| 03-AG06 | Maintain QA Testing Lab and QA Field Office | 01 50 00 | 18 | MO | $ | $ |
| 03-AG07 | Diversion and Care of Water | 01 57 24 | 1 | JB | $ | $ |
| 03-AG08 | As-Built Drawings | 01 78 00 | 1 | JB | $ | $ |
| 03-AG09 | Commissioning | 01 91 13 | 1 | JB | $ | $ |
| 02 | Div 02 EXISTING CONDITIONS | |||||
| 03-AH01 | Verification Core Drilling, Vertical Holes HQ | 02 32 00 | 455 | LF | $ | $ |
| 03-AH02 | Core Drilling, Vertical Holes | 02 32 00 | 120 | LF | $ | $ |
| 03-AH03 | Downhole Imaging | 02 32 00 | 650 | LF | $ | $ |
| 03-AH04 | Concrete Conduit Box Removal | 02 41 13 | 1 | JB | $ | $ |
| 03-AH05 | Existing Pullbox Modifications | 02 41 13 | 1 | JB | $ | $ |
| 03-AH06 | Contractor Access Ramp and Work Bench Restoration | 02 41 13 | 1 | JB | $ | $ |
| 03-AH07 | Maintenance shop existing access demolition | 02 41 13 | 1 | JB | $ | $ |
| 03-AH08 | Maintenance shop parking lot milling for Resurfacing | 02 41 13 | 1 | JB | $ | $ |
| 03-AH09 | Existing 24 inch CMP demolition (61W525-03-AWD) | 02 41 13 | 1 | JB | $ | $ |
| 03-AH10 | Toe Drain & Manhole Demolition (61W525-03-AWD) | 02 41 13 | 1 | JB | $ | $ |
| 03-AH11 | Dam Toe Light Pole Removal (61W525-03-AWD) | 02 41 13 | 1 | JB | $ | $ |
| 03-AH12 | Overhead electrical line removal (61W525-04-AWD) | 02 41 13 | 1 | JB | $ | $ |
| 03-AH13 | Eastern Lake Access Stripping | 02 41 13 | 1 | JB | $ | $ |
| 03-AH14 | Trailhead Parking Lot Milling (61W525-06-AWD) | 02 41 13 | 1 | JB | $ | $ |
| 03-AH15 | Contractor Parking lots Stripping as required (61W525-07-AWD) | 02 41 13 | 1 | JB | $ | $ |
| 03-AH16 | Existing Maintenance BLDG Canopy Shed Demolition | 02 41 13 | 1 | JB | $ | $ |
| 03-AH17 | Demolition of Existing Lock Machinery | 02 41 17 | 1 | JB | $ | $ |
| 03-AH18 | Demolition of Existing Lock Operations Building | 02 41 17 | 1 | JB | $ | $ |
| 03-AH19 | Demolition and Relocation of Existing Lock Upper Guidewall Beams and Piers Above EL 660.0 | 02 41 17 | 1 | JB | $ | $ |
| 03-AH20 | Place Rock Fill in Existing Lock Recesses | 02 41 17 | 1 | JB | $ | $ |
| 03-AH21 | Salvage of Floating Mooring Bitts | 02 42 91 | 1 | JB | $ | $ |
| 03-AH22 | Salvage of the Culvert Valves | 02 42 91 | 1 | JB | $ | $ |
| 03-AH23 | Remediation and Restoration of the Electrical Service Rooms | Various | 1 | JB | $ | $ |
| 03-AH24 | Remediation and Restoration of the Hazmat Room | Various | 1 | JB | $ | $ |
| 03-AH25 | Strip or Cover of Operations Building and Parking Lot Area | Various | 1 | JB | $ | $ |
| 03-AH26 | Catch basin and drain removal (61W525-2-AWD) | 02 42 91 | 1 | JB | $ | $ |
| 03-AH27 | Trailhead Drive Milling, Stripping and Roadbed Preparation | 02 42 91 | 1 | JB | $ | $ |
| 03-AH28 | Trailhead Drive Parking Lot Milling in Preparation for Resurfacing (61W525-04-AWD) | 02 42 91 | 1 | JB | $ | $ |
| 03-AH29 | Trailer Removal X 2 and Foundation Demolition (61W525-04-AWD) | Various | 1 | JB | $ | $ |
| 03-AH30 | Trailer Relocation x 1 and Foundation Demolition (61W525-04-AWD) | Various | 1 | JB | $ | $ |
| 03-AH31 | Future Greenway Area Stripping | 32 92 19 | 1 | JB | $ | $ |
| 03-AH32 | Stripping of area west of Maintenance Shop | 32 92 19 | 1 | JB | $ | $ |
| 03-AH33 | Resident Engineer Office Milling | 02 41 13 | 1 | JB | $ | $ |
| 03-AH34 | Decommisioning and Demolition of Existing Lift Station | Drawings | 1 | JB | $ | $ |
| 03 | Div 03 CONCRETE | |||||
| 03-AJ01 | Waterstop | 03 15 14 | 1 | JB | $ | $ |
| 03-AJ02 | 2" LDPE Foam Expansion Joint | 03 15 14 | 1 | JB | $ | $ |
| 03-AJ03 | Reinforcing Steel - Material | 03 20 02 | 835 | Ton | $ | $ |
| 03-AJ04 | Place Rebar | 03 20 02 | 835 | Ton | $ | $ |
| 03-AJ05 | Drill and Grout #6 Dowels; Waterstop Recess | 03 20 02 | 72 | EA | $ | $ |
| 03-AJ06 | Drill and Grout #8 Dowels; Existing Culverts and Cable Tunnel | 03 20 02 | 26 | EA | $ | $ |
| 03-AJ07 | Cement, Type II, MH - Low Alkali and Moderate Heat | 03 30 01 | 8300 | Ton | $ | $ |
| 03-AJ08 | Class F Fly Ash | 03 30 01 | 5600 | Ton | $ | $ |
| 03-AJ09 | Roughen/Preparation of Concrete Surface in Culverts and Cable Tunnel | 03 30 04 | 8045 | SF | $ | $ |
| 03-AJ10 | Culvert Valve and Cable Tunnel Plugs | 03 31 07 and 03 80 00 | 1700 | CY | $ | $ |
| 03-AJ11 | Inspection Shafts | 03 41 33 and 03 80 00 | 1 | JB | $ | $ |
| 03-AJ12 | Contact Grout for Culverts and Cable Tunnel Plugs | 03 61 00 | 230 | CF | $ | $ |
| 03-AJ13 | Structural Concrete (5ksi) | 03 70 00 | 42000 | CY | $ | $ |
| 03-AJ14 | 10in. Paved Portland cement pavement (4 ksi) with dowels | 03 70 01 | 4050 | SY | $ | $ |
| 03-AJ15 | Culvert Valve Display Slab (4 ksi) | 03 70 01 | 1 | JB | $ | $ |
| 03-AJ16 | Operations Lot 30 x 50 ft Concrete Slab (4 ksi) | 03 70 01 | 1 | JB | $ | $ |
| 03-AJ17 | Miscellaneous Concrete (3ksi) | 03 70 01 | 1100 | CY | $ | $ |
| 03-AJ18 | Pier Concrete (5.5ksi) | 03 80 00 | 5 | CY | $ | $ |
| 03-AJ19 | Concrete Slot Cutting | 03 81 19 | 1 | JB | $ | $ |
| 03-AJ20 | Tremie Concrete (5ksi) | 03 31 07 | 450 | CY | $ | $ |
| 05 | Div 05 METALS | |||||
| 03-AK01 | Miscellaneous Metal | 05 50 15 | 1 | JB | $ | $ |
| 03-AK02 | Prefabricated Guardrail Installation | 05 50 15 | 450 | LF | $ | $ |
| 07 | Div 07 THERMAL AND MOISTURE PROTECTION | |||||
| 03-AL01 | Operations Building - Waterproofing | 07 13 53 | 1 | JB | $ | $ |
| 09 | Div 09 FINISHES | |||||
| 03-AM01 | Painting - Hazmat Room | 09 97 00 | 1 | JB | $ | $ |
| 03-AM02 | Painting - Electrical Service Rooms | 09 97 00 | 1 | JB | $ | $ |
| 10 | Div 10 SPECIALTIES | |||||
| 03-AN01 | Permanent Exterior Signage | 10 14 03 and 10 14 04 | 1 | JB | $ | $ |
| 03-AN02 | Fire Sprinkler System | 10 44 17 | 1 | JB | $ | $ |
| 03-AN03 | Plumbing System | 10 44 17 | 1 | JB | $ | $ |
| 03-AN04 | Operations Building Commissioning | 10 44 17 | 1 | JB | $ | $ |
| 13 | Div 13 SPECIAL CONSTRUCTION | |||||
| 03-AP01 | Instrumentation Monitoring Program | 13 50 00 | 12 | MO | $ | $ |
| 03-AP02 | Instrumentation Installation | 13 50 00 | 1 | JB | $ | $ |
| 03-AP03 | Instrumentation Maintenance and Modifications - Existing Lock | 13 50 00 | 1 | JB | ||
| 03-AP04 | Cylinder Storage Building | 13 34 19.06 and others | 1 | JB | $ | $ |
| 03-AP05 | Crane Storage Shed Construction (61W525-24-AWD) | Various | 1 | JB | $ | $ |
| 23 | Div 23 HEATING, VENTILATIONS, AND AIR CONDITIONING (HVAC) | |||||
| 03-AQ01 | Testing, Adjusting, and Balancing (TAB) | 23 05 95 | 1 | JB | $ | $ |
| 03-AQ02 | Heating and Ventilation Equipment - Cylinder Storage Building | Division 23, Section 08 91 00 | 1 | JB | $ | $ |
| 03-AQ03 | Heating and Ventilation Equipment - Hazmat Room | Division 23, Section 08 91 00 | 1 | JB | $ | $ |
| 03-AQ04 | Heating and Ventilation Equipment - Electrical Service Rooms | Division 23, Section 08 91 00 | 1 | JB | $ | $ |
| 26 | Div 26 ELECTRICAL | |||||
| 03-AR01 | HAZMAT Room Electrical Systems/Lighting | 26 20 00/26 51 00 | 1 | JB | $ | $ |
| 03-AR02 | Site Exterior Lighting | 26 56 00 | 1 | JB | $ | $ |
| 03-AR03 | Landside Electrical Room Systems/Lighting | 26 20 00/26 51 00 | 1 | JB | $ | $ |
| 03-AR04 | Riverside Electrical Room Systems/Lighting | 26 20 00/26 51 00 | 1 | JB | $ | $ |
| 03-AR05 | Existing Maintenance Building Interior Electrical Systems | 26 20 00 | 1 | JB | $ | $ |
| 03-AR06 | Cylinder Storage Building Interior Electrical Systems/Lighting/Lightning Protection | 26 20 00/26 41 00/26 51 00 | 1 | JB | $ | $ |
| 03-AR07 | Relocation of Miscellaneous Electrical Systems On Existing Lock | 26 20 00/33 71 02 | 1 | JB | $ | $ |
| 03-AR08 | Repair of Existing Lock Grounding System Post Slot Cutting | 26 20 00/33 71 02 | 1 | JB |
| 27 | Div 27 COMMUNICATIONS | |||||
| 03-AS01 | Fiber Optic Data Transmission System - Maintenance Building | 27 21 10 | 1 | JB | $ | $ |
| 03-AS02 | Fiber Optic Data Transmission System - Cylinder Storage Building | 27 21 10 | 1 | JB | $ | $ |
| 03-AS03 | Fiber Optic Data Transmission System - Site ESS | 27 21 10 | 1 | JB | $ | $ |
| 03-AS04 | Telecom Cabling System - Maintenance Building | 27 21 10 | 1 | JB | $ | $ |
| 03-AS05 | Telecom Cabling System - Cylinder Storage Building | 27 21 10 | 1 | JB | $ | $ |
| 28 | Div 28 ELECTRONIC SAFETY AND SECURITY | |||||
| 03-AT01 | ESS/Access Control - Site Perimeter and Buildings | 28 20 01 | 1 | JB | $ | $ |
| 03-AT02 | Security CCTV System | 28 23 23 | 1 | JB | $ | $ |
| 03-AT03 | Fire Detection System - HAZMAT Room | 28 31 00 / 28 31 64 | 1 | JB | $ | $ |
| 03-AT04 | Fire Detection System - Maintenance Building | 28 31 00 / 28 31 64 | 1 | JB | $ | $ |
| 03-AT05 | Fire Detection System - Cylinder Storage Building | 28 31 00 / 28 31 64 | 1 | JB | $ | $ |
| 31 | Div 31 EARTHWORK | |||||
| 03-AU01 | Manage, and Place Material for New Maintenance Shop Ramp | 31 00 00 | 1 | JB | $ | $ |
| 03-AU02 | Earthwork for Operations Parking Lot Area | 31 00 00 | 1 | JB | $ | $ |
| 03-AU03 | Manage, and Place Material for Maint. Shop lot and Thrust Block access | 31 00 00 | 1 | JB | $ | $ |
| 03-AU04 | Manage, and Place Material for New Operations Building Ramp | 31 00 00 | 1 | JB | $ | $ |
| 03-AU05 | Maintenance Ramp Retaining Wall Construction (61W525-15-AWD) | 31 00 00 | 1 | JB | $ | $ |
| 03-AU06 | Manage, and Place Downstream Lock Chamber Fill | 31 00 00 | 1 | JB | $ | $ |
| 03-AU07 | Manage, and Place Upstream Lock Chamber Fill | 31 00 00 | 1 | JB | $ | $ |
| 03-AU08 | Geotextile Installations | 31 05 22 | 13000 | SY | $ | $ |
| 03-AU09 | Rock Excavation | 31 23 05 | 6034 | CY | $ | $ |
| 03-AU10 | Dental Excavation (15% surface area) | 31 23 05 | 247 | CY | $ | $ |
| 03-AU11 | Line Drilling (6" Spacing) | 31 23 05 | 844 | SY | $ | $ |
| 03-AU12 | Thrust Block Overburden Excavation | 31 23 05 | 18325 | CY | $ | $ |
| 03-AU13 | Redrilling Grouted Holes | 31 32 12 | 575 | LF | $ | $ |
| 03-AU14 | Drill Grout Holes in Rock | 31 32 23 | 8,068 | LF | $ | $ |
| 03-AU15 | Pressure Washing (Hydraulic) | 31 32 23 | 72 | HR | $ | $ |
| 03-AU16 | Pressure Testing (Hydraulic) | 31 32 23 | 884 | EA | $ | $ |
| 03-AU17 | Grout Mixes | 31 32 23 | 1,195 | CY | $ | $ |
| 03-AU18 | Placing Grout | 31 32 23 | 1,195 | CY | $ | $ |
| 03-AU19 | Government Requested Standby - Grouting | 31 32 23 | 24 | HR | $ | $ |
| 03-AU20 | Dental Concrete | 31 60 00 | 247 | CY | $ | $ |
| 03-AU21 | Foundation Preparation | 31 60 00 | 1645 | SY | $ | $ |
| 03-AU22 | Impervious Liner (Seepage Barrier) | 31 00 00 | 1 | JB | $ | $ |
| 03-AU23 | Earth Retention System for Thrust Block - Construction | 31 23 05 | 1 | JB | $ | $ |
| 32 | Div 32 EXTERIOR IMPROVEMENTS | |||||
| 03-AV01 | Aggregate Base Course Grade D | 32 11 23 | 3175 | Ton | $ | $ |
| 03-AV02 | TDOT Crushed stone | 32 11 23 | 3000 | Ton | $ | $ |
| 03-AV03 | TDOT #57 Stone | 32 11 23 | 1350 | Ton | $ | $ |
| 03-AV04 | TDOT #2 Stone | 32 11 23 | 3715 | Ton | $ | $ |
| 03-AV05 | Asphalt Pavement - Binder Course AC (PG64-22) GR "B-M2" | 32 12 16 | 3550 | Ton | $ | $ |
| 03-AV06 | Asphalt Pavement - Wearing Course ACS (PG64-22) GR "D" | 32 12 16 | 1680 | Ton | $ | $ |
| 03-AV07 | Pavement Markings | 32 17 24 | 1 | JB | $ | $ |
| 03-AV08 | Final Security Fencing | 32 31 13 | 1 | JB | $ | $ |
| 03-AV09 | Main Access Gate Installation | 32 31 13 | 1 | EA | $ | $ |
| 03-AV10 | 6-Foot Personnel Gate Installation | 32 31 13 | 1 | EA | $ | $ |
| 03-AV11 | 12-Foot Personnel Gate Installation | 32 31 13 | 1 | EA | $ | $ |
| 03-AV12 | Double Swing Gate Installation | 32 31 13 | 1 | EA | $ | $ |
| 03-AV13 | Barrier Swing Gate Installation | 32 31 13 | 1 | EA | $ | $ |
| 03-AV14 | Greenway (Contractor Laydown Area) Temp, and Perm, Seeding | 32 92 19 | 1 | JB | $ | $ |
| 03-AV15 | Designated Disposal Area Temp. and Permanent Seeding | 32 92 19 | 1 | JB | $ | $ |
| 03-AV16 | Operations Parking Lot Area Temp, and Permanent Seeding | 32 92 19 | 1 | JB | $ | $ |
| 03-AV17 | Contractor Parking Lot North of RE Office Temp, and Permanent Seeding | 32 92 19 | 1 | JB | $ | $ |
| 03-AV18 | Topsoil | 32 92 19 | 19000 | TN | $ | $ |
| 03-AV19 | Tree Plantings | 32 93 00 | 30 | EA | $ | $ |
| 03-AV20 | Shrub Plantings | 32 93 00 | 400 | EA | $ | $ |
| 33 | Div 33 UTILITIES | |||||
| 03-AW01 | 2-inch Domestic Water Line for Operations Building | 33 11 00 | 1 | JB | $ | $ |
| 03-AW02 | FDC Connection for Ops Building | 33 11 00 | 1 | EA | $ | $ |
| 03-AW03 | 8-inch Fire Protection Line for Operations Building | 33 11 00 | 1 | JB | $ | $ |
| 03-AW04 | 6-inch Fire Protection Line for the Operations Building | 33 11 00 | 1 | JB | $ | $ |
| 03-AW05 | Fire hydrant assemblies | 33 11 00 | 1 | EA | $ | $ |
| 03-AW06 | 8-inch Fire Protection Line for Maintenance Building | 33 11 00 | 1 | JB | $ | $ |
| 03-AW07 | 2 in. Force Main Sewer from Operations Building | 33 30 00 | 1 | JB | $ | $ |
| 03-AW08 | Site Electrical Distribution - Maintenance Building | 33 71 02 | 1 | JB | $ | $ |
| 03-AW09 | Site Electrical Distribution - Cylinder Storage Building | 33 71 02 | 1 | JB | $ | $ |
| 03-AW10 | Site Electrical Distribution - Landside Electrical Room | 33 71 02 | 1 | JB | $ | $ |
| 03-AW11 | Site Electrical Distribution - Site ESS/Perimeter | 33 71 02 | 1 | JB | $ | $ |
| 03-AW12 | 30 in. Class IV RCP | 33 11 00 | 70 | LF | $ | $ |
| 03-AW13 | 24 in. Class IV RCP | 33 11 00 | 779 | LF | $ | $ |
| 03-AW14 | 24 in. Class III RCP | 33 11 00 | 100 | LF | $ | $ |
| 03-AW15 | 12 in. Smooth Wall HDPE (toe drain) | 33 11 00 | 560 | LF | $ | $ |
| 03-AW16 | Construction and Commissioning of New Lift Station | 33 30 00 | 1 | JB | $ | $ |
| 34 | Div 34 TRANSPORTATION | |||||
| 03-AX01 | Curb Construction | 34 71 13 | 325 | LF | $ | $ |
| 03-AX02 | Vehicular Guardrail Installation | 34 71 13 | 1200 | LF | $ | $ |
| 03-AX03 | Parking Bumpers | 34 71 13 | 35 | EA | $ | $ |
| 03-AX04 | Bollards | 34 71 13 | 20 | EA | $ | $ |
| 35 | Div 35 WATERWAY AND MARINE CONSTRUCTION | |||||
| 03-AY01 | Furnish, Manage, and Place TDOT Class C Riprap | Various | 2500 | TN | $ | $ |
| 03-AY02 | Furnish, Manage, and Place TDOT Class B Riprap | Various | 1600 | TN | $ | $ |
| 03-AY03 | Furnish, Manage, and Place TDOT Class A Riprap | Various | 1500 | TN | $ | $ |
| 03-AY04 | Furnish, Manage, and Place Bedding Stone for Riprap | Various | 1675 | TN | $ | $ |
| 46 | Div 46 WATER AND WASTEWATER EQUIPMENT | |||||
| 03-AZ01 | Aerating Fountain Construction | 46 51 00.00 10 | 1 | JB | $ | $ |
TOTAL ESTIMATED AMOUNT $