W912P525RA001 Amendment 0004 Changes_29Apr2025.pdf

PDF 142 KB Posted

Attached to
Chickamauga Lock Replacement Approach Wall and Decommissioning Federal contract opportunity
Solicitation number
W912P525RA001
Issued by
Department of the Army Corps of Engineers Engineering District Nashville

About this file

This document is Amendment 0004 for the Chickamauga Lock Approach Wall and Decommissioning federal contract (W912P525RA001). The amendment introduces comprehensive updates across multiple technical specifications, including revisions to sections covering water diversion, concrete materials and placement, foundation drilling, steel setting, painting, electrical systems, and earth excavation. Key contract drawing sheets in multiple folios were replaced, and the price breakout schedule was adjusted, with updates to contract line items such as steel setting piles for riverside and landside walls and the addition of a "Diversion and Care of Water" line item.

The amendment also modified FAR clauses, specifically DFARS 252.236-7001 (Contract Drawings and Specifications) and FAR 52.252-3 (Alterations in Solicitation). These changes reflect ongoing refinements to the project specifications and requirements, which align with the broader U.S. Army Corps of Engineers Nashville District project for constructing river and middle approach walls, decommissioning the existing lock, and completing site restoration activities at the Chickamauga Lock site in Chattanooga, Tennessee.

View the file

Other files for this federal contract opportunity

Other files attached to Chickamauga Lock Replacement Approach Wall and Decommissioning, newest first.
File Type Posted
W912P525RA001 Amendment 0007 Changes_10JUL2025.pdf PDF
W912P525RA001 A0007 SF 30_Final_15July2025.pdf PDF
CKL Approach Wall and Decommissioning Price Schedule_11JULY2025.xlsx XLSX spreadsheet
CKL Approach Wall and Decommissioning Price Schedule_11JUNE2025.xlsx XLSX spreadsheet
Instructions to Offerors and Procedures for Submission of Offerors and Proposal Evaluation Approach_REV2.pdf PDF
W912P525RA001 A0006 SF 30_Final_17June2025.pdf PDF
W912P525RA001 Amendment 0006 Changes_11Jun2025.pdf PDF
W912P525RA001 A0005 SF 30_Final_16May2025.pdf PDF
CKL Approach Wall and Decommissioning_ 04292025.xlsx XLSX spreadsheet
W912P525RA001 A0004 SF30_final 13May2025.pdf PDF
02APR25 pre-proposal site visit 2 sign in sheets.pdf PDF
W912P525RA001 A0003 SF30_final 01Apr2025.pdf PDF
W912P525RA001 Amendment 0003 Changes_Updated 28MAR2025.pdf PDF
CKL Approach Wall and Decommissioning_ 03282025.xlsx XLSX spreadsheet
Chickamauga Lock AWD Physical Site Visit Sign-In Sheet (04Mar2025).pdf PDF
W912P525RA001 A0002 SF30_final 20 Mar 25.pdf PDF
Chickamauga Lock AWD RFP Amendment 0002 Letter_signed ssw.pdf PDF
CKL Approach Wall and Decommissioning_2025-02-13.xlsx XLSX spreadsheet
Instructions to Offerors and Procedures for Submission of Offerors and Proposal Evaluation Approach_REV1.pdf PDF
CKL Approach Wall and Decommissioning_Virtual Pre-Proposal Meeting Attendee List.xlsx XLSX spreadsheet
W912P525RA001 A0001 SF 30_final 20 Feb 25.pdf PDF
W912P525RA001 Amendment 0001 Changes_20Feb2025.pdf PDF
Watts Bar Map.pdf PDF
CKL Approach Wall and Decommissioning.xlsx XLSX spreadsheet
Instructions to Offerors and Procedures for Submission of Offerors and Proposal Evaluation Approach.pdf PDF
DBA WD TN20250145 03Jan2025 (Hamilton County TN Heavy Construction).pdf PDF
US Citizens Security Access Form.pdf PDF
W912P525RA001_final_04Feb2025.pdf PDF
Foregin National Contractor Security Access Form.pdf PDF
JA for Brand Name CKL AWD_signed ssw_Redacted.pdf PDF
Show all 30

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

W912P525RA001

AMENDMENT 0004

Chickamauga Lock Approach Wall and Decommissioning

DESCRIPTION OF CHANGES

QUESTIONS

Government answers to questions received from Industry have been provided in Projnet Bidder Inquiry.

TECHNICAL SPECIFICATIONS

All revised Specifications, new specifications, revised appendices, and new appendices have been merged into a single document (W912P5-25-R-A001_Am4_Contract Specifications)

1. SECTION 01 57 24 – DIVERSION AND CARE OF WATER

a. Section 01 57 24 Diversion and Care of Water has been removed in its entirety and replaced with a revised Section 01 57 24.

i. Paragraph 1.1.1, Cofferdam, has been revised.

2. SECTION 02 20 20 – FLOWABLE FILL – CONTROLLED LOW STRENGTH MATERIAL (CLSM)

a. Section 02 20 20 Flowable Fill – Controlled Low Strength Material (CLSM) has been removed in its entirety and replaced with a revised Section 02 20 20.

i. Paragraph 1.2, Summary, has been revised.

3. SECTION 03 11 14 – CONCRETE: FORMWORK

a. Section 03 11 14 has been removed in its entirety and replaced with a revised Section 03 11 14.

i. Paragraph 1.7 Sample Pannels has been revised.

4. SECTION 03 30 01 – CONRETE: MATERIALS

a. Section 03 30 01 has been removed in its entirety and replaced with a revised Section 03 30 01.

i. Paragraph 2.10 Epoxy Resin has been revised.

ii. Table C has been revised.

5. SECTION 03 30 04 – CONCRETE PLACEMENT REQUIREMENTS

a. Section 03 30 04 has been removed in its entirety and replaced with a revised Section 03 30 04.

i. Paragraph 3.8 Special Temperature Controlled Concrete has been revised.

6. SECTION 03 41 34 – INSTALLATION OF GOVERNMENT FURNSIHED PRECAST CONCRETE

BEAMS

a. Section 03 41 34 has been removed in its entirety and replaced with a revised Section 03 41 34.

i. Paragraph 3.1.2.2.1.i Test Injection Results has been revised.

7. SECTION 09 90 00 – PAINTS AND COATINGS

a. Section 09 90 00 has been removed in its entirety and replaced with a revised Section 09 90 00.

i. Paragraph 1.1 Scope has been revised.

ii. Paragraph 3.13 Paint Tables has been revised.

8. SECTION 09 97 02 – PAINTING: HYDRAULIC STRUCTURES

a. Section 09 97 02 has been removed in its entirety and replaced with a revised Section 09 97 02.

i. Paragraph 3.5 “System NO. 3-A-Z and 5-A-Z” has been revised.

9. SECTION 13 34 19.06 – METAL BUILDING SYSTEMS

a. Section 13 34 19.06 has been removed in its entirety and replaced with a revised Section 13 34 19.06.

i. Paragraph 3.4.13 Contractor’s Twenty (20) Year No Penal Sum Warranty has been revised.

10. SECTION 26 20 00 – INTERIOR DISTRIBUTION SYSTEMS

a. Section 26 20 00 has been removed in its entirety and replaced with a revised Section 26 20 00.

i. Paragraph 3.1.13.5 Grounding for Downstream Approach Piers has been revised.

11. SECTION 31 00 00 – EARTH EXCAVATION AND FILL PLACEMENT

a. Section 31 00 00 has been removed in its entirety and replaced with a revised Section 31 00 00.

i. Paragraph 1.4.10.1 Cohesive Material has been revised.

ii. Paragraph 1.4.19 Bay 5 Earthen Structure Excavation has been removed.

iii. Paragraph 3.13.4.2 Degradable Rock has been revised.

iv. Paragraph 3.7 Final Grade of Surfaces to Support Concrete has been revised.

12. SECTION 31 32 23 – FOUNDATION DRILLING AND GROUTING

a. Section 31 32 23 has been removed in its entirety and replaced with a revised Section 31 32 23.

i. Paragraph 3.6.1 General has been revised.

ii. Paragraph 3.7.1 General has been revised.

13. SECTION 31 63 15 – BAY 5 SHEAR WALL STRAND ANCHORS

a. Section 31 63 15 has been removed in its entirety and replaced with a revised Section 31 63 15.

i. Paragraph 3.2.7 Waterproofing Anchor Holes has been revised.

CONTRACT DRAWINGS

The following contract drawing sheets were removed and replaced with revised contract drawing sheets:

1. Folio No. 1

a. 61W510-02D-AWD “Contract Base and Option – General Delineation”

b. 61W510-121-AWD “Monolith M1 – Concrete – Sheet 1 of 3”

c. 61W520-53-AWD “Downstream Intermediate Piers Shell Structure, Reinforcement Details, Sheet

1 of 2””

d. 61W530-51-AWD “Removal of Visitors Overlook and Oil Storage Building”

e. 61W530-54-AWD “Hazmat Storage Room”

2. Folio No. 2

a. 61W525-22-AWD “Site Sign and Striping Plan”

b. 61W510-02D-AWD “Contract Base and Option – General Delineation”

3. Folio No. 4

a. 65W415A-AWD “120/208V Lighting Panelboard – Schedules – Sheet 2 of 2”

b. 61W785-AWD “Cable Schedule – Sheet 2 of 3”

c. 61W815-AWD “Raceway Schedule – Sheet 1 of 7”

d. 61W820-AWD “Lock Grounding System – Diagrammatic Single Line”

4. Folio No. 5

a. 66W353-AWD “Exterior Elevations”

PRICE BREAKOUT SCHEDULE

1. Base Contract:

a. Contract Line Item 00-D004 "Steel Setting Piles -Riverside Wall" has been updated to reflect the correct quantity of 470 Linear Foot.

2. Option 1:

a. Contract Line Item 01-P011 “Diversion and Care of Water” has been added with a quantity of 1 “job”.

b. Contract Line Item 01-S002 “Steel Setting Piles – Landside Wall” has been updated to reflect the correct quantity of 1,050 Linear Foot.

3. Option 3:

a. Contract Line Item 03-AH11 has been updated to provide reference to Contract Drawing Sheet 15W275-AWD Folio 4.

FAR CLAUSES

1. DFARS 252.236-7001:

a. DFARS Clause 252.236-7001, Contract Drawings and Specifications has been revised.

2. FAR 52.252-3:

a. FAR Provision 52.252-3, Alterations in Solicitation, has been revised.