Pre-Bid_RFI_W912L6-16-R-0007_Log_12-01-16.pdf

PDF 37 KB Posted

Attached to
Medium Altitude Manned ISR Beddown
Solicitation number
W912L6-16-R-0007
Issued by

View the file

Other files

File Type Posted
W912L6-16-R-0007-0005.pdf PDF
Pre-Bid_RFI_W912L6-16-R-0007_Log_12-19-161.pdf PDF
W912L6-16-R-0007-0004.pdf PDF
Amendment_LEED_and_Commissioning_Deducts.pdf PDF
H-131.pdf PDF
W912L6-16-R-0007-0003.pdf PDF
H-132.pdf PDF
Requested_photos_30_Nov_2016.pdf PDF
H-122.pdf PDF
Pre-Bid_RFI_W912L6-16-R-0007_Log_11-30-16.pdf PDF
H-121.pdf PDF
RFI_78_Attachment.pdf PDF
ED201.pdf PDF
RFI_52_attachment_Specification_Section_01000.pdf PDF
si_schedule_5-25-2016.pdf PDF
STATEMENT_OF_SPECIAL_INSPECTIONS_5-25-2016.pdf PDF
00_22_13.00_20_R2.pdf PDF
W912L6-16-R-0007-0002.pdf PDF
Pre-Bid_RFI_W912L6-16-R-0007_Log_11-21-16.pdf PDF
Pre-Bid_RFI_W912L6-16-R-0007_Log_11-21-16.pdf PDF
ANG_hangar_study_recommended_changes_.docx DOCX document
Hangar_Foam_Fire_Suppression_System_Inadvertent_Activations_Final.pdf PDF
CS101_-_Revised.pdf PDF
Criteria_Changes.docx DOCX document
ANGETL_15-01-03_Fire_Protection_Design_Guidance.pdf PDF
Requested_photos_21_Nov_2016.pdf PDF
Pre-Bid_RFI_W912L6-16-R-0007_Log_11-17-16.pdf PDF
Pre-Bid_RFI_W912L6-16-R-0007_11-14-2016__Answered.pdf PDF
00_22_13.00_20_R1.pdf PDF
Appendix_F9_Hazardous_Material_Report.pdf PDF
Bldg_1011_Information_Slides.pdf PDF
EXHIBIT_B.doc DOC document
EXHIBIT_A.doc DOC document
EXHIBIT_C.doc DOC document
Attendance_Sheet_Bldg._1011_9_Nov_16_W912L6-16-R-0007.pdf PDF
EXHIBIT_F.DOC DOC document
W912L6-16-R-0007-0001.pdf PDF
OK_ANG_Bldg_1011_Specs_Vol_2_07152016.pdf PDF
00_22_13.00_20.pdf PDF
OK_ANG_Bldg_1011_Specs_Vol_1_07152016.pdf PDF
W912L6-16-R-0007.pdf PDF
General_Requirements.pdf PDF
B_Final_Design_OK_ANG.pdf PDF
Show all 43

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Date: RFI No. RFP Reference (Sect/Para/Page)

QUESTION GOVERNMENT RESPONSE

11/8/2016 1 Solicitation Section 2.5.2.1.1

The Solicitation references Exhibit A for evaluation of experience. However, Exhibit A cannot be found. Please provide Exhibit A.

Exhibit A Uploaded.

11/8/2016 2 Solicitation Section 2.5.2.2

The Solicitation references Exhibit B Subcontractor/Team/Key Personnel Information and Consent Form". However, Exhibit B cannot be found. Please provide Exhibit B.

Exhibit B Uploaded.

11/8/2016 3 Solicitation Section 2.5.3.2

The Solicitation references Exhibit C for Past/Present Performance. However, Exhibit C cannot be found. Please provide Exhibit C.

Exhibit C Uploaded.

11/8/2016 4 Solicitation Section 2.4.4

Section states pages and charts shall be on 8.5x11 inch paper.

This will be very small formatting for the proposal schedule, making it difficult to read. Can the proposal schedule be on 11x17 inch paper?

8.5x11 inch paper.

11/8/2016 5 N/A The drawings state they are the "Final Design Submittal".

Please confirm these are the construction drawings and that no additional design is anticipated from the successful offeror.

Government confirms there will be no other drawings from the A&E and government unless amended prior to award.

(Documents are sealed by the DOR as final and issued for bid.)

11/8/2016 N/A Is an Independent Fire Protection Engineer needed to review/approve the "Final Design Submittal" fire protection drawings?

No. The Final Design Submittal issued by Benham was prepared and signed and sealed by a Registered Fire Protection Engineer and are to be used as the Construction Documents. No approval of these documents by another FPE is required. The contractor's FPE may use the signed sealed documents as a bridging document for their design.

However, the Contractor's FPE will be fully responsible for the fire protection systems design and acceptance.

11/8/2016 6 Drawing Sheet F-0001, Note 2.

Please confirm all the current bid documents, designs, and calculations comply with all applicable codes, standards, and all minimum AF ETL 02-15, the UFCs, and the AHJ requirements.

To the best of our knowledge, all current bid documents comply with the required minimum codes and standards.

The hydraulic calculations are to be used as a basis of design and shall be verified by the contractor's FPE. Please note that this design complies with the new Air Force foam system requirements which are not addressed in ETL 02-15.

11/8/2016 7 N/A Please confirm the FP contractor is to provide shop drawings that have been reviewed/approved by the FPE to meet the government's criteria as found in the bid documents.

Yes. Per the specifications, the FPE shall be subcontracted by the Prime Contractor and shall be fully responsible for signing and sealing all fire alarm/MNS and fire protection systems as required by the ANG ETL.

11/8/2016 8 N/A Can the FPE who prepared the contract drawings also perform the FPE services to the successful offeror?

No. This is a conflict of interest. A third party FPE shall be hired.

11/8/2016 9 00 22 13.00 20 Pricing is required for pipe asbestos abatement. Please provide the asbestos assessment specifying the quantity and extent of asbestos found.

The design documents were based on information provided per the Hazardous Materials report. The exact quantity of asbestos containing pipe insulation fittings is not known, however the unit price per CLIN 0001AB shall be based on 100 units.

11/8/2016 10 Solicitation Section 00100 Para 3.

RFIs are to be sent to "christine.m.walker30.mail.mil". This appears to be a typo. Please clarify the correct address.

christine.m.walker30.mil@mail.mil

11/9/2016 11 00 22 13.00 20 Part 1 1.1

CLIN 0001AB appears to be mislabeled as 0001AE on the (boxed out portion) schedule of values. It appears it should it read 0001AB. Will the government confirm or re-issue bid sheet to correct this? Or, Shall we make this correction on the form? Is there an Excel version of the bid form available?

Corrected to CLIN 0001AB and uploaded. There is not an excel version available.

11/9/2016 12 N/A At the site visit, it sounded as if email (PDF) proposal submissions were acceptable, instead of the hardcopies required in the RFP. Please confirm an electronic submission is acceptable.

Email proposals are not accepted. Per instructions there is to be a CD included with the hard copy submissions.

Pre-Bid RFI Log for W912L6-16-R-0007 Bldg 1011 Medium Altitude Manned ISR Beddown, YZEU139006

QUESTION GOVERNMENT RESPONSE

Pre-Bid RFI Log for W912L6-16-R-0007 Bldg 1011 Medium Altitude Manned ISR Beddown, YZEU139006

11/9/2016 13 N/A At the site visit, furniture was observed in the areas to be renovated. Who is responsible for removing the personal effects? Who is responsible for removing the govt furniture?

If the contractor is responsible, is the furniture returned to the govt or disposed of by the contractor?

Personal effects to be removed by the government.

Furniture is to be removed by the contractor. Furniture to be disposed of by the contractor.

11/9/2016 14 N/A At the site visit, a hoist was observed in the areas to be renovated. Who is responsible for removing the hoist? If the contractor is responsible, is the hoist to be returned to the govt or disposed of by the contractor?

Contractor is to remove the hoist. Hoist is to be disposed of by the contractor.

11/15/2016 15 00100 para 3.3

The referenced paragraph states RFIs must be received no later than 5 working days prior to closing. At the site visit it was stated they are due by 11-17-16. Please clarify. 11/17/2016 is correct

11/15/2016 16 N/A

For a project of this nature, a site office will be required. Will the contractor be allowed to utilize existing ANG space or do we need to provide a temporary office? If contractor is to provide a site office, is temporary electrical easily accessible and available within 200'?

Contractor may utilize either lean-to of the building for office space. The existing building has electrical power service as shown in the drawings? You may place a trailer on the North East side of the building if you desire. The Annex will not be available for contractor usage.

11/15/2016 17 00010 Notes

4. Line items 0002 through 0002 are Option Line Items. See FAR Provision 52.217-5 Evaluation of Options, Section 00100. See FAR Clause 52.217-7 in Section 00700. Option lines items are shown in plans and specifications as ABIs.

Line item 0002, Option 1 is ABI 1. Please confirm this should state Line items 0002 through 0004. Confirmed

11/15/2016 18 N/A

The Supplemental Instructions to Bidders does not reference CLINs 0003 and 0004. Please clarify what takes precedence;

document 00 22 13.00 20 or the Solicitation pages. Solicitation Pages

11/15/2016 19 Div 28 para 2.1.1

“Standard Products” Only lists Notifier and Gamewell-FCI as “Pre-approved manufactures.” Can Simplex be added as a Pre-approved Manufacturer for this project? No

11/15/2016 20

When project drawings are downloaded, it appears that the pdf drawings were created to be 11”x17” and are “not to scale”. Please provide pdf drawings that can be reproduced “to scale”.

Not sure what is meant by 'downloaded'. Drawings provided on CD and the pdfs were created full size (30x42).

11x17 is therefore not a true half size reproduction if that is the issue.

11/15/2016 21 Can the proposal due date be extended to allow time to print scalable drawings? No

11/15/2016 22 Vol 2, Part 2

Offerors shall discuss their performance using the Performance Relevancy Questionnaire format, Exhibit A, Part

1. Prepare not more than (3-5) of these documents.

Contractors should select their projects carefully because the quality of the contractor’s relevant performance is more important than the quantity of projects submitted. However, Exhibit A Performance Relevancy states to prepare not more than three (3) of these documents. Please clarify what the maximum number of projects can be provided for Past/Present Performance information. Prepare not more than (3-5) of these documents.

11/16/2016 23 DDC control

They are asking for different equipment then the JCI equipment that has been installed on base--are they using LonMark or Lon Controls instead of the Metasys that we have install in all other buildings on base?

System can be either Lon or Bacnet with Bacnet as the preferred option. The base is in the process of converting to Bacnet. System must interface with the bases JCI Metasys system and the operational control for the building must be controlled by the existing Metasys server which must be reprogrammed for this building.

11/16/2016 24 Cut Off Date

Section 3.3 of the RFP states that "all questions and requests for information (RFI) must be received NOT LATER THAN the fifth working day prior to closing…". This would put the RFI cut off date at 11/28/16. However, it was mentioned at the pre-bid meeting that RFI's were due by 11/17/16. Please advise if contractors and subcontractors can have until 11/28/2016 to review plans and formulate questions regarding this project.

No, questions are due on 11/17/16. this is to allow the government to answer the question before closing.

QUESTION GOVERNMENT RESPONSE

Pre-Bid RFI Log for W912L6-16-R-0007 Bldg 1011 Medium Altitude Manned ISR Beddown, YZEU139006

11/16/2016 25 Will the 3 Story Structure on the North end of the Building be occupied

Yes, The 3 story Annex on the North end of the building will be occupied and building electrical power, com, water, hot water heat, fire alarm and fire suppression outages must be made on Friday, Saturdays and Sundays. Contractor must maintain these services to the this area during the duration of the contract

11/16/2016 26 VRF Is there any information on the size of lines for the VRF This will be provided by the MFG recommendations

1/17/2016 27

ETL 11-11

Request RFP Drawing GI001

RFP Drawing GI001 requires compliance with ETL 11-11, but this document could not be located on WBDG or on the Air National Guard website.

Please provide this criteria.

ETL 11-11 has been superseded by ETL 15-01-03 and the attached 28 October 2016 Hangar Foam Memo

11/17/2016 28

ETL 15-01-03 /

15-03-01 RFP

Section 21 30

The specs list ETL 15-03-01 but RFP drawing sheet GI001 lists ETL 15-01-03. I was unable to locate either ETL on WBDG or the Air National Guard website. Please provide this ETL. ANG ETL 15-01-03 is correct 15-03-01 is a typo

11/17/2016 29

ETL 98-8

Applicability RFP Drawing Sheet GI001 and Specifications

Drawing GI001 lists ETL 98-8 but this ETL is not listed as applicable in the specifications. Please confirm no provisions of ETL 98-8 apply to this project.

ETL 98-8 only applies to the existing facilities that are generally outside of this scope of work.

11/17/2016 30

Seismic Bracing Requirements for Fire Suppression Piping RFP Specification 21 13 13.00 10 paragraph

3.4.1, RFP

Drawing S-001

RFP Drawing S-001 indicates the seismic design category is B which would not normally require seismic bracing for fire suppression piping per ASCE 7 Paragraph 13.1.4. RFP Specification 21 13

13.00 10 (Wet Pipe) 3.4.1 requires seismic bracing but the high expansion foam spec (21 13 20.00 30) does not require seismic bracing. Also, Spec 21 13

13.00 10 requires seismic bracing design to comply with UFC 3-310-04. But, UFC 3-310-04 paragraph B-3.2.4 implies that piping constructed in accordance with NFPA 13 is not within the purview of UFC 3-310-04. Please confirm which systems require seismic bracing and explain intent of UFC 3- 310-04 reference as it relates to fire suppression system seismic bracing design.

The wet pipe system seismic requirements shall comply with Category B requirements and NFPA 13. The foam system piping shall comply with General Note #6 on Sheet FX-104 and all foam piping shall be seismically braced (regardless of the seismic design category). The intent of UFC 3-310-04 is for the mounting of the generators per ETL 15-01-03 Section 9.7.2 and not the system piping.

11/17/2016 31

AFCEC

Guidance Criteria RFP Drawing Sheet

GI001.

RFP Drawing Sheet GI001 lists "AFCEC Guidance for Addressing Hangar Fire Suppression Requirements - Criteria Changes" as an applicable criteria. The only version of this document we have is undated and not titled to match sheet GI001 and therefore I am not sure if it is the identical criteria.

Please provide the specific version of this AFCEC Guidance document with which our design is required to comply.

The A/E has been provided the same untitled document from the Air Force and the Air National Guard and they are not dated nor titled. The documents will be provided.

11/17/2016 32

Access to design criteria RFP Section 21 30 00, 28 31 76, 21 13

13.00 10, and 21 13 20.00 30

Please provide ANG ETL 15-03-01 referenced in the RFP.

This ETL is not published on the WBDG and cannot be otherwise located. Provided

11/17/2016 33 tile finishes finish schedule IN-602 has PWB-1 and is not listed on interior finish schedule page IN-601 and PWT-1 is not on any room detail but is on the finish schedules --are all these the same.

Do not see wall tile drawings for Men's restroom 2nd floor

IN-602 incorrectly lists the code for wall base in restrooms as PWB-1. The correct material code is PTB-1 as shown on IN-601 and on Toilet elevation drawings. PWT-1 is shown on Interior Finish Schedule, Interior Room Finish Schedule and on Toilet Elevations IN-502 - IN-503. Elevations for Men's B212 are shown on sheet IN-502, details 1, 2, 4, 5.

QUESTION GOVERNMENT RESPONSE

Pre-Bid RFI Log for W912L6-16-R-0007 Bldg 1011 Medium Altitude Manned ISR Beddown, YZEU139006

11/17/2016 34

RFP Specification 21 90 00 paragraph 1.1.c and 1.4

RFP specification section 21 90 00 paragraph 1.4 includes the requirement to "engage commissioning service personnel that specialize in the types of inspections and tests to be performed." But the subsequent paragraph suggests the project FPE is responsible for commissioning. The language "commissioning service personnel" sounds like something different than the project FPE, but I do not believe this was the intent. Please confirm the intent of the RFP is for the FPE described in the fire protection system sections to also serve as the commissioning agent as defined by 21 90 00, assuming they have experience performing acceptance testing, integrated testing, and commissioning of the stated systems.

It is not the intent that the Commissioning Agent(s) be an FPE. For example, some foam systems may require a Commissioning Agent to be brought in from the foam system manufacturer to provide all commissioning, testing, balancing, ect. The Det-Tronics releasing system could also require a factory commissioning agent if the installing contractor does not have Factory Certifications to provide final testing. These Commissioning Agents should coordinate with the FPE to devlop the testing plans and schedule. However, if the FPE has experience in the integrated testing of all these systems, they may also serve as the Commissioning Agent.

11/17/2016 35 RFI Cut Off Date

Section 3.3 of the RFP states that "all questions and requests for information (RFI) must be received NOT LATER THAN the fifth working day prior to closing…". This would put the RFI cut off date at 11/28/16. However, it was mentioned at the pre-bid meeting that RFI's were due by 11/17/16. Please advise if contractors and subcontractors can have until 11/28/2016 to review plans and formulate questions regarding this project.

Official cut off date was 17 Nov 2016. We will accept RFIs after that date but they may not be answered be fore RFP due date.

11/17/2016 36

Electronic Submission of Bids

It was discussed at the pre-bid site meeting that electronic submission of bids would be acceptable. However, the RFP currently only contains instructions for hand-delivered bids.

Can the government please provide specific instructions for the electronic submission of bids?

Answered RFI 12

11/17/2016 37 Requests for Work on Fridays

It was discussed at the pre-bid site meeting that contractors could put in a request to perform work on Fridays. Can a "blanket" request be submitted to request permission to work all Fridays for the duration of the contract (provided that government inspections are not scheduled to take place on Fridays)?

NO, insulation policy is that weekend Entry Access Lists are provided weekly.

11/17/2016 38

User Furniture & Accessories to Remain

Can the Government please confirm that all of the existing User furniture & office equipment (desks, tables, chairs, refrigerators, etc.) will be removed by the Government before construction begins? Are any of these types of items to be left behind for the demolition contractor to dispose of? Answered RFI 13.

11/17/2016 39

Geotechnical Report Drawing Sheet S-500

No geotechnical data was provided as part of the bid package.

Based on the dimensions shown on sheet S-500, the excavations for the new elevator pits will exceed 8' in depth.

Does the geotechnical report indicate that the contractor may encounter any ground water while excavating to these depths?

Per General Structural Note B.1 on Sheet S-001, a copy of the Final Geotechnical Report is available for inspection at the Base Civil Emgineer Resident Office. The Geotechnical Report for this project indicates groundwater can be expected at depths of 13 to 23 feet below grade.

11/17/2016 40

Exterior Electrical Transformer @ NW Corner Drawing Sheets

CS-101 & ES-100

Keyed note 10 on sheet CS-101 indicates that the transformer that is to be installed on the NW corner of the facility is being relocated. However, sheet ES-100 states that the contractor is to provide this transformer. Is this an existing transformer that is to be relocated from its current location? If so, where is the transformer currently?

The transformer to be installed on the NW corner of the facility is new and is to be provided by the contractor.

11/17/2016 41

Structural Steel for Elevator 2 @ Lean- To A Drawing Sheets S-400, S- 401 & S-500

The structural drawings (sheet S-400 in particular) indicate that no new structural steel needs to be installed or existing steel removed for the installation of Elevator 2 at Lean-To A.

All structural steel in the Elevator 2 drawings is shown as existing with no notes regarding removal. Is this accurate?

The Elevator 2 shaft in Leanto A is a new, structurally independent CMU structure located inside the existing parachute tower. The existing steel tower structure will remain in place and does not require modification as part of this project.

11/17/2016 42

Glass Vestibules on South Side of Building Spec Section 01 11 00

Paragraph 1.1.1 (b)(1) of spec section 01 11 00 (Summary of Work) states that "there are two glass enclosures at the south side of the facility previously added as vestibules that will be removed in their entirety". No reference to these enclosures (or their removal) can be found in the demolition drawings.

Can the government please provide more detail regarding what glass enclosures are to be removed?

The referenced enclosures will be removed by the Govt.

They are referenced in the documents for informational and coordination purpose only.

QUESTION GOVERNMENT RESPONSE

Pre-Bid RFI Log for W912L6-16-R-0007 Bldg 1011 Medium Altitude Manned ISR Beddown, YZEU139006

11/17/2016 43

Annex & North Lean-To (Lean-To A) Occupancy

Will both the Annex & Lean-To A remain occupied during construction? These areas will require some demolition and installation of new systems (fire suppression, fire alarm, mass notification). Is this work to be performed after hours? How is the contractor to perform life safety work in occupied areas?

Both the Annex & Lean-To will remain occupied during construction. The work can be performed during work hours or after hours. A Phasing Plan shall be developed by the FPE shall be provided to help maintain protection and to provide minimum interruption (Spec. 28 31 76 Sect. 3.3)

11/17/2016 44

Project Scheduling Software Specification Section 01 32

17.00 20

Spec section 01 32 17.00 20 states that Primavera P6 will be used for scheduling purposes on this project. Is acceptable for the contractor to utilize Microsoft Project and convert the schedule files to P6 for government use? That is acceptable.

11/17/2016 45

Contractor FPE & Fire Protection System Commissioning Specification Section 21 90 00

Paragraph 1.4 of spec section 21 90 00 states that the contractor's FPE is to be responsible for the design and commissioning of the fire protection system (to include fire alarm, mass notification, fire sprinkler, fire pumps, and foam systems). Typically, fire alarm & mass notification drawings are prepared by a fire alarm contractor (usually a NICET III technician) and fire suppression (sprinkler & foam systems) are designed by a fire suppression contractor. Is the governments intent that the prime contractor employ/hire a single fire protection engineer to review/approve/stamp the designs developed by these parties and perform commissioning on all of the fire protection systems?

The fire protection systems for the hangar and building protects high value asset and require the full oversight of an FPE. NICET certification or years experience is not a substitute for the FPE qualification. As clearly indicated in the specifications, the prime contractor shall hire an FPE. This FPE shall develop and design the fire protection systems documents with the fire alarm, MNS, foam, and sprinkler system contractors. The final drawings shall be signed and sealed by the FPE. The FPE shall have full control and input in the systems design and commissioning.

11/17/2016 46

Zodiac, Inc.

Commissioning Authority

The project specifications state that the plumbing, HVAC & electrical commissioning is to be performed by Zodiac, Inc.

under a sub consultant agreement with Benham Design (designer of record). Can the government confirm if the fees for the commissioning effort were included in the design fee of this project? Or should the contractor contact Zodiac and obtain pricing for the commissioning effort? The fees for Zodiac are included with the design fees.

11/17/2016 47

Hazardous Material Abatement Drawing Sheets G- 002, H-121, H- 122, H-131, H-132

The sheet index on sheet G-002 states that sheets H-121 & 122 pertain to the abatement of lead based paint (LBP) and sheets H-131 & 132 pertain to the abatement of asbestos.

However, in reviewing these sheets, all four (4) sheets are labeled "LBP Diagram", but all contain notes about asbestos remediation (H-131 is a duplicate of H-121, and H-132 is a duplicate of H-122… all of which only contain notes regarding asbestos abatement. Can the government please advise if these sheets are supposed to be duplicates?

The noted drawing sheets have been corrected. Refer to the attached documents.

11/17/2016 48 Fire Pump House Foundation

Is a slab and/or foundation required for the premanufactured fire pump house? If so, can the government please provide a design? This would likely be far more cost effective than having contractors hire a structural engineer to design such a small feature.

Yes, foundations are required. The pump house slab/foundation shall be designed by the contractor based on the pump house size selected as stated in the Specification 21 30 00 Section 1.8.1. The fire pump house shown is a basis of design and the pad size/loads can change.

11/17/2016 49 Spec Section 01 45 35

Paragraph 1.2 of Spec Section 01 45 35 states that the Statement of Special Inspections & the Schedule of Special Inspections are included as an attachment. Can the government please advise on where these attachments can be found?

See attached Statement of Special Inspections and Schedule of Special Inspections referenced in Specification Section 01 45 35, "Special Inspections."

11/17/2016 50

Environmental Engineer Spec Section 01 45

00.00 10

The experience matrix in paragraph 3.4.4 of Spec Section 01 45 00.00 10 lists an environmental engineer as a required part of the CQC Personnel. What is the environmental engineers' intended purpose? Is this person only required to oversee the abatement portion of the contract?

The environmental engineer would oversee the abatement portion of the contract and any other applicable element of environmental protection as required by temporary control, permit or jurisdiction.

11/17/2016 51

Temporary Construction Facilities

In order to reduce the construction footprint and possibly reduce costs, would it be acceptable for the contractor to utilize the hangar bay space to house the temporary construction trailer, dumpster & laydown area? Yes

QUESTION GOVERNMENT RESPONSE

Pre-Bid RFI Log for W912L6-16-R-0007 Bldg 1011 Medium Altitude Manned ISR Beddown, YZEU139006

11/17/2016 52

Subfactor 1:

Experience and Capability

Section 2.5.2.2 Subfactor 1 Experience and Qualifications states that we should "refer to Specification Section 01000, paragraph 36, for the minimum qualification requirements for key personnel." Section 01000 was not included in the original RFP documents. Can this section be provided? It was posted as a separate attachment.

11/17/2016 53 Subfactor 5: LEED Experience

Section 2.5.2.3.2 Subfactor 5 notes that resumes are limited to two pages each. However, key personnel resumes are already being provided in Subfactor 1. Please confirm if resumes are required for Subfactor 5 as well, and if so, what positions should be submitted.

If not previously provided then provide them according to this section.

11/17/2016 54 Volume 2: Part 2

Section 2.5.3.4 says to prepare "not more than 3-5" Performance Relevancy Questionnaires. However, the Exhibit A form says to prepare "not more than 3" of the documents.

Please confirm how many Performance Relevancy Questionnaires should be submitted. Answered RFI 22.

11/17/2016 55 References Can previously completed Past Performance Questionnaires be submitted in lieu of the Exhibit C Reference Package?

No, questionnaires are suppose to be sent directly to contracting office not to contractor that is proposing on the solicitation.

11/17/2016 56

Project Site Personnel 01 35 26 / 01 45 00.00

Paragraph 1.6.1.2 of Section 01 35 26 states that the QC Manager can be the SSHO on this project, and paragraph

3.4.2 of Section 01 45 00.00 10 states that this same CQC System Manager may also have duties as the Project Superintendent. If both of these statements were applied literally, a GC bidder could conceivably bid this project utilizing a single site person, which we do not believe is the intent for this project. Please clarify if these statements are both intended to be a part of this RFP, and clarify the required site personnel for this project.

The superintendant can hold double duty as either the QC Manager OR the SSHO, but not both.

11/17/2016 57 Bid Due Date RFP

/ SF 1442

Mondays are difficult days for large competitive bids, would Base Contracting please consider moving the bid due date to Tuesday the 6th, or Wednesday the 7th? Will Change due date to 6 December 2016

11/17/2016 58 RFP Final Design Drawings

The drawings that were issued as a part of the RFP are all 11x 17 size, and many of the drawings do not have any dimensions on them therefore the scale is incorrect. Could the drawings please be re-issued in their proper/original size? Answered RFI 20.

11/17/2016 59 RFP Name

What is name of this project that you would like us to use?

The FBO and the majority of the forms (including this one) call it "Medium Altitude Manned ISR Beddown;" however the SF 1442 refers to it as "Renovate Bldg 1011." We just want to refer to it with the same name the Government will use, to avoid confusion. Thank you. Medium Altitude Manned ISR Beddown

11/17/2016 60 Factor 2: Safety Activities

Regarding the requirements for Factor 2 Safety Activities, Training and documentation, is the Government referring to how we document training; or to how we document Safety Procedures; or some other type of documentation?. Thank you. Both training and procedures.

11/17/2016 61 Electrical Service Continuation

What areas will require electrical service continuation during the construction phases? First, second and third floor of the Annex

11/17/2016 62 Temporary Power Will the hanger require temporary power? What will be the temporary requirements if any? The hangar will not require temporary power

11/17/2016 63 Electrical Service Cutover

During the electrical transfer cutover, what is the maximum allowable down time for the areas being supplied from the service being transferred? 3 Days, Friday Saturday and Sunday.

11/17/2016 64 Panel Location E-

Please provide the location of the existing panel "G". The prints reference Hanger 2. See attachment Sheet ED201.

11/17/2016 65 Panel Location E-

Please provide the location of the existing panel "A". The prints reference Hall A208. See attachment Sheet ED201.

11/17/2016 66 Panel Location E-

Please provide the location of the existing panel "M". The prints reference Mech X304. See attachment Sheet ED201.

11/17/2016 67 Panel Location E-

Please provide the location of the existing panel "L". The prints reference Annex X202A See attachment Sheet ED201.

QUESTION GOVERNMENT RESPONSE

Pre-Bid RFI Log for W912L6-16-R-0007 Bldg 1011 Medium Altitude Manned ISR Beddown, YZEU139006

11/17/2016 68 Transformer Location Please provide the location of the existing transformer "T12". See attachment Sheet ED201.

11/17/2016 69

1000 kva Medium Voltage Transformer E- 601 Who is supplying the 1000kva medium voltage transformer? 1000kVA transformer will be provided by the contractor

11/17/2016 70 Fire Alarm - Fire Pump House Will all fire alarm peripherals be pre installed?

No, the fire alarm devices will not be pre-installed. The fire alarm system shall be an extension of the building fire alarm system and shall be the same manufacturer and products as the building fire alarm system. If this question is in regards to the fire alarm flow switches and tampers, this is to be coordinated with the fire sprinkler provider.

11/16/2016 71 RFP Section 00010 Notes

Item 4 identifies CLIN 0002 as Option 1 ABI 1.

What distinguishes CLIN 0003 from CLIN 0002 which appears to be the same area based on room identifications? Answered with modification 2 of the solicitation

11/16/2016 72

21 13 20 Low- Level High Expansion Foam Fire Extinguishing Systems for Aircraft Hangars

1.7.6 Duration of Discharge mentions an overhead pre-action

sprinkler system specified in Section 21 13 13. Is this to be a wet-pipe system?

Disregard mention of a pre-action sprinkler system. Wet-pipe sprinkler is to be installed.

11/16/2016 73 21 30 00 Fire Pumps pump start/stop pressures.

Drawing GI001 references the following Engineering Technical Letters.

Please provide access.

ANG ETL 11-11 Reducing Inappropriate Hangar Fire Suppression Activations

ANG ETL 15-01-03 Fire Protection Design Guidance (1 May 2015)

AFCEC Guidance for Addressing Hangar Fire Suppression Requirements - Criteria Changes

ANG Hangar Fire Protection Study Recommendations

Drawing FD001 Demolition Note 7 states that protection for building shall be uninterrupted.

Is new sprinkler piping to be placed in service before old sprinkler piping is removed?

at 215 psi. Refer to Sheet FX402 “Fire Pump Operation Sequence” for more details. However, if a different pump is selected, the settings may vary.

ETL documents were provided in RFI 31 & 32.

Sprinkler systems for the Annex (area between Column lines 1-4 & FG-AB) shall remain uninterrupted. Outages for less than 24 hours will be allowed. A fire watch for a 24 hour duration will be provided by the base. This outage shall be coordinated with the base for available personell for the fire watch. Sprinkler systems for the other areas of renovation may be demolished and replaced with the contruction phasing and no fire watches are needed. Also, refer to RFI 25.

11/16/2016 74

Drawing FX101 General Note 6 references pipe racks and catwalks.

Please provide drawings so that we can determine where these exceed four feet in width.

There are no complete as-built drawings of the pipe racks.

There are no longer catwalks in the hangar. All areas with new sprinkler systems shall be verified with a site survey.

Partial drawings are attached showing areas where potential pipe rack widths will cause sprinkler obstructions. Also, refer to mechanical drawings for new ductwork over 48".

11/16/2016 75

Drawing FX101 General Note 7 references high volume low speed fans.

Please identify HVLSF locations on the drawings.

There are four HVLSF fans located approximately in each half of the hangar. The fans are non-functioning and are not required to be de-activated by the fire alarm or foam control systems. However, provide sprinkler spacing per NFPA 13 for HVLS fans. See attached.

QUESTION GOVERNMENT RESPONSE

Pre-Bid RFI Log for W912L6-16-R-0007 Bldg 1011 Medium Altitude Manned ISR Beddown, YZEU139006

11/16/2016 76

Drawing FX101 Keyed Note 7 along with Drawing FX103 Keyed Notes 1 & 2 identify Lean-To "B" to have new piping feeding existing piping to remain.

With the existing piping not shown with sizes on the drawings, please identify a demand GPM and psi for each point of connection so that we size this new feed piping correctly in our proposals.

The existing systems for the Annex and both Lean-To's were pipe schedule designed. Since there will be no alterations to the sprinkler heads (just replacment of), per UFC 3-600-01, the pipe schedule method may still be utilized to feed the sprinkler systems. Alternately, if the contractor wants to reduce the feed main pipe size based on the new fire pump performance curve, the areas may be hydraulically calculated per UFC 3-600-01. As-built sprinkler drawings have been attached and are to be used as information only. If hydraulic analysis is provided, all sprinkler head locations shall be field verified.

11/16/2016 77

Drawing FX101 Keyed Note 6 identifies the Main in Lean-to "A" to remain.

Keyed note 3 is not clearly associated with Lean-to "A".

Is Keyed note 1 or 3 applicable to keyed not 6?

Annex is the area from column 1-4 and FG-AB. Keyed note # 3 is not associated with the Annex. Keyed note 1-3 shall not be applicable to keyed note 6. ""Lean-to A is misnamed throughout page" However, Notes are correct

11/16/2016 78

Drawing FX401 Keyed Note 12 states to set the pressure reducing valve to 90 psi.

May the pressure reducing valve be set based on hydraulic calculations of balancing the hangar bay overhead sprinkler system with the high-expansion foam system, so lot at it does not exceed 175 psi?

Yes, the pressure reducing valve may be set at a pressure corresponding with the hydraulic calculations where approved by the FPE. The contract documents are only a basis of design.

11/16/2016 79

Drawing FX402 Keyed Note 12 states that the backflow preventer is to be a double check valve. High-Expansion foam will be added to the water downstream via the inductor.

Will a double-check valve be accepted by the City of Oklahoma City, or will the backflow preventer need to be a Reduced Pressure Zone?

Provide a double check valve assembly as shown on the contract documents.