SOW_EPOXY_FLOOR_BLDG._35.pdf

PDF 105 KB Posted

Attached to
Install Non-Slip Epoxy Floor in Hangar 35 Federal contract opportunity
Solicitation number
W912JB-16-B-4007
Issued by
Department of the Army Michigan Army National Guard

About this file

Statement of Work

View the file

Other files for this federal contract opportunity

Other files attached to Install Non-Slip Epoxy Floor in Hangar 35, newest first.
File Type Posted
Government_Bid_Certified.pdf PDF
Bid_Opening_Minutes_H35_Install_Epoxy_Floors.pdf PDF
Bid_Opening_Sign_In_Sheet.pdf PDF
BID_ABSTRACT_H35_FLOORING.pdf PDF
BID_OPENING_REMINDER_NOTICE.pdf PDF
Site_Visit_Minutes_H35_Install_Epoxy_Floors.pdf PDF
1427_Floors_Sign_In_Sheet.pdf PDF
Hangar_35_Epoxy_Floor_Paint_Booth_Addition.pdf PDF
W912JB16B4007_VGLZ_162041_Amendment_1.pdf PDF
SELFRIDGE___VISION_2020_12May2014_Revision.pdf PDF
W912JB-16-B-4007_Solicitation.pdf PDF
Install_epoxy_flr_35FP.pdf PDF
ADDENDUM_6_Vision_2020__12May2014.pdf PDF
AFForm66_epoxy_floor_bldg._35.pdf PDF
Base_Access_Form.pdf PDF
Synopsis_Hangar_35_Epoxy_Flooring.pdf PDF
Show all 16

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

STATEMENT OF WORK

Project Number, Title: VGLZ 162041 EPOXY FLOOR HGR. 35 13 Jul 16

The statement of work shall be in strict compliance with those specifications and the requirements identified in this SOW and its attachment, in which case the more stringent/higher quality requirements shall apply. The number of pages in this SOW, including attachments, is 2

1. This SOW provides for, but is not limited to:

A. Provide and install a high performance medium non slip epoxy floor coating. The epoxy floor system shall be installed in accordance with manufacturer’s instructions or recommendations.

B. The contractor is responsible for all floor preparation and repairs prior to the installation.

C. The color for the floor is gray with a medium grit. contractor reinstall lines around eyewash and equipment.

D. The bldg. personal will move all the equipment out of the room.

E. Contractor shall follow all international BLDG. codes , OSHA and STATE requirements.

F. Skilled craftsman shall do all work in a careful and workman like manner. The installation of shall be in accordance with the manufacturer’s recommendation and utilizing the best, current method of the trade.

2. The following options shall be used in lieu of the options listed:

SELFRIDGE ANGB, MICHIGAN

09 96 00 1 HIGH-PERFORMANCE COATINGS

SECTION 09 96 00 - HIGH-PERFORMANCE COATINGS

PART 1 - GENERAL

1.1 RELATED DOCUMENTS

A. Drawings and general provisions of the Contract, including General and Supplementary

Conditions and Division 01 Specification Sections, apply to this Section.

1.2 SUMMARY

A. Section includes surface preparation and application of high-performance coating systems.

B. Related Requirements:

1. Division 05 Sections for shop priming of metal substrates with primers specified in this

Section.

2. Division 09 painting Sections for special-use coatings and general field painting.

1.3 DEFINITIONS

A. Gloss Level 6: 70 to 85 units at 60 degrees, according to ASTM D 523.

B. Gloss Level 7: More than 85 units at 60 degrees, according to ASTM D 523.

1.4 ACTION SUBMITTALS

A. Product Data: For each type of product indicated. Include preparation requirements and application instructions.

B. LEED Submittals:

1. Refer to Section 01 81 13, Sustainable Design Requirements, for information regarding

LEED® submission requirements.

2. The Contractor and/or Subcontractor shall submit the following information under a separate tab for LEED information.

a. A complete list materials.

b. Material costs for each material listed. Material costs shall not include installation or shipping costs.

c. Location of material manufacturer.

d. Location of material extraction/harvest.

e. Post-consumer and pre-consumer recycled content of each material.

f. Product Data for Credit EQ 4.2: For paints and coatings used inside the building envelope during construction provide manufacturer’s literature documenting VOC

SELFRIDGE ANGB, MICHIGAN

09 96 00 2 HIGH-PERFORMANCE COATINGS

content of each product submitted. VOC content shall comply with requirements of credit EQc4.2.

C. Samples for Initial Selection: For each type of topcoat product indicated.

D. Samples for Verification: For each type of coating system and in each color and gloss of topcoat indicated.

1. Submit Samples on rigid backing, 8 inches (200 mm) square.

2. Step coats on Samples to show each coat required for system.

3. Label each coat of each Sample.

4. Label each Sample for location and application area.

E. Product List: For each product indicated, include the following:

1. Cross-reference to paint system and locations of application areas. Use same designations indicated on Drawings and in schedules.

2. Printout of current "MPI Approved Products List" for each product category specified in

Part 2, with the proposed product highlighted.

3. VOC content.

1.5 MAINTENANCE MATERIAL SUBMITTALS

A. Furnish extra materials, from the same product run, that match products installed and that are packaged with protective covering for storage and identified with labels describing contents.

1. Coatings: 5 percent, but not less than of each material and color applied.

1.6 QUALITY ASSURANCE

A. Mockups: Apply mockups of each coating system indicated to verify preliminary selections made under sample submittals and to demonstrate aesthetic effects and set quality standards for materials and execution.

1. Contracting Officer will select one surface to represent surfaces and conditions for application of each coating system specified in Part 3.

a. Other Items: Contracting Officer will designate items or areas required.

2. Final approval of color selections will be based on mockups.

a. If preliminary color selections are not approved, apply additional mockups of additional colors selected by Contracting Officer at no added cost to the

Government.

3. Approval of mockups does not constitute approval of deviations from the Contract

Documents contained in mockups unless Contracting Officer specifically approves such deviations in writing.

SELFRIDGE ANGB, MICHIGAN

09 96 00 3 HIGH-PERFORMANCE COATINGS

4. Subject to compliance with requirements, approved mockups may become part of the completed Work if undisturbed at time of Substantial Completion.

1.7 DELIVERY, STORAGE, AND HANDLING

A. Store materials not in use in tightly covered containers in well-ventilated areas with ambient temperatures continuously maintained at not less than 45 deg F (7 deg C).

1. Maintain containers in clean condition, free of foreign materials and residue.

2. Remove rags and waste from storage areas daily.

1.8 FIELD CONDITIONS

A. Apply coatings only when temperature of surfaces to be coated and surrounding air temperatures are between 50 and 95 deg F (10 and 35 deg C).

B. Do not apply coatings when relative humidity exceeds 85 percent; at temperatures less than

5 deg F (3 deg C) above the dew point; or to damp or wet surfaces.

C. Do not apply exterior coatings in snow, rain, fog, or mist.

PART 2 - PRODUCTS

2.1 HIGH-PERFORMANCE COATINGS, GENERAL

A. MPI Standards: Provide products that comply with MPI standards indicated and are listed in

"MPI Approved Products List."

B. Material Compatibility:

1. Provide materials for use within each coating system that are compatible with one another and substrates indicated, under conditions of service and application as demonstrated by manufacturer, based on testing and field experience.

2. For each coat in a coating system, provide products recommended in writing by manufacturers of topcoat for use in coating system and on substrate indicated.

3. Provide products of same manufacturer for each coat in a coating system.

C. VOC Content: Products shall comply with VOC limits of authorities having jurisdiction and, for interior coatings applied at project site, the following VOC limits, exclusive of colorants added to a tint base, when calculated according to 40 CFR 59, Subpart D (EPA Method 24).

1. Flat Paints and Coatings: 50 g/L.

2. Nonflat Paints and Coatings: 150 g/L.

3. Primers, Sealers, and Undercoaters: 200 g/L.

4. Anti-Corrosive and Anti-Rust Paints Applied to Ferrous Metals: 250 g/L.

5. Zinc-Rich Industrial Maintenance Primers: 340 g/L.

6. Pre-Treatment Wash Primers: 420 g/L.

SELFRIDGE ANGB, MICHIGAN

09 96 00 4 HIGH-PERFORMANCE COATINGS

7. Floor Coatings: 100 g/L.

8. Shellacs, Clear: 730 g/L.

9. Shellacs, Pigmented: 550 g/L.

D. Low-Emitting Materials: Interior coatings shall comply with the testing and product requirements of the California Department of Health Services' "Standard Practice for the

Testing of Volatile Organic Emissions from Various Sources Using Small-Scale Environmental

Chambers."

E. Colors: As indicated on Drawings and/or Delivery Order Requirements.

2.2 EPOXY COATINGS

A. Basis of Design:

1. Provide the following system or alternate system from an alternate manufacturer that meets or exceeds the following:

a. Epoxy Primer: Tennant Coatings ECO-MPE/FSE (1 coat, 5 mils dry film thickness).

b. Pigmented Build-Up Coat: Tennant Coatings ECO-MPE/FSE (12 mils dry film thickness).

c. Urethane Top Coat: Tennant Coatings ECO-HTS (2.93 mils dry film thickness).

2.3 SOURCE QUALITY CONTROL

A. Testing of Coating Materials: The Government reserves the right to invoke the following procedure:

1. The Government will engage the services of a qualified testing agency to sample coating materials. Contractor will be notified in advance and may be present when samples are taken. If coating materials have already been delivered to Project site, samples may be taken at Project site. Samples will be identified, sealed, and certified by testing agency.

2. Testing agency will perform tests for compliance with product requirements.

3. The Government may direct Contractor to stop applying paints if test results show materials being used do not comply with product requirements. Contractor shall remove noncomplying coating materials from Project site, pay for testing, and recoat surfaces coated with rejected materials. Contractor will be required to remove rejected materials from previously coated surfaces if, on recoating with complying materials, the two coatings are incompatible.

SELFRIDGE ANGB, MICHIGAN

09 96 00 5 HIGH-PERFORMANCE COATINGS

PART 3 - EXECUTION

3.1 EXAMINATION

A. Examine substrates and conditions, with Applicator present, for compliance with requirements for maximum moisture content and other conditions affecting performance of the Work.

1. Maximum Moisture Content of Substrates: When measured with an electronic moisture meter as follows:

a. Concrete: 12 percent.

B. Verify suitability of substrates, including surface conditions and compatibility with existing finishes and primers.

C. Proceed with coating application only after unsatisfactory conditions have been corrected.

1. Beginning coating application constitutes Contractor's acceptance of substrates and conditions.

3.2 PREPARATION

A. Comply with manufacturer's written instructions and recommendations in "MPI Architectural

Painting Specification Manual" applicable to substrates indicated.

B. Remove hardware, covers, plates, and similar items already in place that are removable and are not to be painted. If removal is impractical or impossible because of size or weight of item, provide surface-applied protection before surface preparation and painting.

1. After completing painting operations, use workers skilled in the trades involved to reinstall items that were removed. Remove surface-applied protection.

C. Clean substrates of substances that could impair bond of coatings, including dust, dirt, oil, grease, and incompatible paints and encapsulants.

D. Concrete Substrates: Remove release agents, curing compounds, efflorescence, and chalk. Do not coat surfaces if moisture content or alkalinity of surfaces to be coated exceeds that permitted in manufacturer's written instructions.

1. Clean surfaces with pressurized water. Use pressure range of 1500 to 4000 psi (10 350 to

27 580 kPa) at 6 to 12 inches (150 to 300 mm).

2. Abrasive blast clean surfaces to comply with SSPC-SP 7/NACE No. 4, "Brush-Off Blast

Cleaning."

SELFRIDGE ANGB, MICHIGAN

09 96 00 6 HIGH-PERFORMANCE COATINGS

3.3 APPLICATION

A. Apply high-performance coatings according to manufacturer's written instructions and recommendations in "MPI Architectural Painting Specification Manual."

1. Use applicators and techniques suited for coating and substrate indicated.

2. Coat surfaces behind movable equipment and furniture same as similar exposed surfaces.

Before final installation, coat surfaces behind permanently fixed equipment or furniture with prime coat only.

3. Coat back sides of access panels, removable or hinged covers, and similar hinged items to match exposed surfaces.

4. Do not apply coatings over labels of independent testing agencies or equipment name, identification, performance rating, or nomenclature plates.

B. Tint each undercoat a lighter shade to facilitate identification of each coat if multiple coats of the same material are to be applied. Tint undercoats to match color of finish coat, but provide sufficient difference in shade of undercoats to distinguish each separate coat.

C. If undercoats or other conditions show through final coat, apply additional coats until cured film has a uniform coating finish, color, and appearance.

D. Apply coatings to produce surface films without cloudiness, spotting, holidays, laps, brush marks, runs, sags, ropiness, or other surface imperfections. Produce sharp glass lines and color breaks.

3.4 FIELD QUALITY CONTROL

A. Dry Film Thickness Testing: The Government will engage the services of a qualified testing and inspecting agency to inspect and test coatings for dry film thickness.

1. Contractor shall touch up and restore coated surfaces damaged by testing.

2. If test results show that dry film thickness of applied coating does not comply with coating manufacturer's written recommendations, Contractor shall pay for testing and apply additional coats as needed to provide dry film thickness that complies with coating manufacturer's written recommendations.

3.5 CLEANING AND PROTECTION

A. At end of each workday, remove rubbish, empty cans, rags, and other discarded materials from

Project site.

B. After completing coating application, clean spattered surfaces. Remove spattered coatings by washing, scraping, or other methods. Do not scratch or damage adjacent finished surfaces.

C. Protect work of other trades against damage from coating operation. Correct damage by cleaning, repairing, replacing, and recoating, as approved by Contracting Officer, and leave in an undamaged condition.

SELFRIDGE ANGB, MICHIGAN

09 96 00 7 HIGH-PERFORMANCE COATINGS

D. At completion of construction activities of other trades, touch up and restore damaged or defaced coated surfaces.

3. Additional specifications for materials or requirements not included in the specifications:

A. Rez stone system 9400 or equal

4. The following attachments are included in this SOW.

A. 1 DRAWING DATED