Bid_Opening_Minutes_H35_Install_Epoxy_Floors.pdf

PDF 160 KB Posted

Attached to
Install Non-Slip Epoxy Floor in Hangar 35 Federal contract opportunity
Solicitation number
W912JB-16-B-4007
Issued by
Department of the Army Michigan Army National Guard

About this file

Bid opening minutes.

View the file

Other files for this federal contract opportunity

Other files attached to Install Non-Slip Epoxy Floor in Hangar 35, newest first.
File Type Posted
Government_Bid_Certified.pdf PDF
Bid_Opening_Sign_In_Sheet.pdf PDF
BID_ABSTRACT_H35_FLOORING.pdf PDF
BID_OPENING_REMINDER_NOTICE.pdf PDF
Site_Visit_Minutes_H35_Install_Epoxy_Floors.pdf PDF
1427_Floors_Sign_In_Sheet.pdf PDF
Hangar_35_Epoxy_Floor_Paint_Booth_Addition.pdf PDF
W912JB16B4007_VGLZ_162041_Amendment_1.pdf PDF
SELFRIDGE___VISION_2020_12May2014_Revision.pdf PDF
ADDENDUM_6_Vision_2020__12May2014.pdf PDF
AFForm66_epoxy_floor_bldg._35.pdf PDF
W912JB-16-B-4007_Solicitation.pdf PDF
Install_epoxy_flr_35FP.pdf PDF
SOW_EPOXY_FLOOR_BLDG._35.pdf PDF
Base_Access_Form.pdf PDF
Synopsis_Hangar_35_Epoxy_Flooring.pdf PDF
Show all 16

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

MICHIGAN AIR NATIONAL GUARD

127th MISSION SUPPORT GROUP

SELFRIDGE ANG BASE MICHIGAN

16 August 2016

MEMORANDUM FOR RECORD

FROM: 127 MSC

Contracting Division

43200 Maple St, Bldg. 105

Selfridge ANGB, MI 48045-5213

SUBJECT: Bid Opening for Solicitation W912JB-16-B-4007, Project No. VGLZ 162041: VGLZ 162041

HANGAR 35 INSTALL EPOXY FLOORING.

1. Bid opening held this date at the Contracting Division conference room commencing at: 2:00 PM in conjunction with subject Request for Proposal. For list of attendees see sign in sheet.

2. Contract Specialist David Brown explained the process, and Hugh Black from the government’s team for the project was in attendance. Steven Stocking was the Bid Opening Officer.

A. PROJECT DESCRIPTION: Provide and install a high performance medium non slip epoxy floor coating. The epoxy floor system shall be installed in accordance with manufacturer’s instructions or recommendations.

B. The contractor is responsible for all floor preparation and repairs prior to the installation.

C. The color for the floor is gray with a medium grit. Contractor to reinstall lines around eyewash and equipment.

D. The bldg. personal will move all the equipment out of the room.

3. Proposals are due NLT 16 August 2016 at 2:00PM local time. Offerors can hand carry bids to 127

MSC Lobby and deposit bids in a bid depository. Offerors are advised that this project is currently funded and that offers must be good for 60 days.

a. Magnitude of project is less than $25,000.00

b. After the notice to proceed is issued the project has a performance time of 30 calendar days for project completion.

c. A Site Visit will be held immediately after this pre-proposal conference at the construction site.

d. When amendments are issued they will be posted on FBO.

e. Payment Bond will not be required for this project based on Independent Government

Estimate. A Bid Bond is not required.

f. Liquidated damages are not applicable to this project.

g. Warranty of Construction clause is incorporated and applies to this project.

h. The most current wage determination is incorporated into the solicitation and will be made part of the resultant contract but it is the contractor's responsibility to keep track of the most current wage rate. Currently DBA Mod 04 dated 24 June 2016.

i. Safety measures are always a part of Government contracts and the Army Corp of

Engineers manual is incorporated in the contract.

j. RFI procedures were reviewed as follows:

i. Email technical questions in RFI format to the Contracting for resolution.

ii. All RFI questions and answers will be emailed out as soon as possible.

k. Please recall that only the Contracting Officer can approve changes such as price, schedule, specifications, and clauses with formal written notice typically in the form of a solicitation amendment or task order modification. Work undertaken regarding changes not formally approved by the Contracting Officer (save for COR approved no cost field changes) is at the Contractor’s risk.

l. This requirement is currently funded.

4. The project description was stated in the FBO IFB Synopsis Hangar 35 Install Epoxy Flooring notice sent out with the Notice of Solicitation Form on 13 July 2016.

5. It was explained prior to bid due time that Selfridge had a network outage that didn’t allow for the display of www.time.gov as called for in the solicitation package. One contractor at the bid opening was able to provide their cell phone with the time.gov site, and it was displayed on the bid opening table. Five (5) bids were received, and 5 bids were read.

6. The bid opening concluded at 2:15pm on Tuesday 16 August 2016.

8/16/2016

X David Brown

David Brown

Contract Specialist

Signed by: BROWN.DAVID.ALLAN.1096981950 http://www.time.gov/

File details come from the government source that posted it. Updated .