VGLZ 162008, INSTALL HEATERS – B1427 SELFRIDGE ANGB, MI
ADDENDUM NO. 001 12 May 2016
This addendum applies to the following documents:
( X ) Statement of Work (SOW), dated 20 Jan 2016
( X ) Bldg. 1427 Heater Plans Sheet M-1 dated 20 Nov 2015
Description of Addendum:
1. SOW (Bldg. 129)
A. Page 2, Section 1, paragraph “a” Delete the following; While following the roofline.
B. Page 2, Section 1, paragraph “d” add the following; The natural gas line size will need to be increased to 3” from the gas meter to inside the building as shown on the plans. All exterior gas piping shall be painted to match building exterior. Interior gas piping does not need to be painted.
2. Bldg. 1427 Heater Plans Sheet M-1
A. Replace B1427 Heater Plans sheet M-1 dated 20 Nov 2015 with the new plan that is attached and is dated 12 May 2016. The only thing that changed is the gas supply line from the meter to inside the building needs to be increased to 3”.
END OF ADDENDUM NO. 001