This solicitation is for repair work on Building 399 Sections B and C at Fort Benning, Georgia. The Department of the Army Corps of Engineers Engineering District Savannah is seeking bids to repair failed and failing systems in the building, including exterior walls, windows, fire protection, interior walls, doors, interior finishes, floors, ceilings, plumbing, HVAC, building controls, electrical, communications, building information systems, site utilities, and minor parking improvements. The scope also includes necessary demolition and hazardous material abatement work. Bids are due on June 15, 2021 in response to solicitation number W912HN21B3007. The acquisition will follow FAR Part 14 procedures for sealed bidding and be awarded on a best value basis.
View the file
Other files
Show all 20
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
FOUO
Technical Specifications
Olson Hall Bldg 399 Ft. Benning, GA
PN 90737
July 2021
Prepared by Stantec Consulting Services Inc.
Raleigh, North Carolina
With consultants
AME Consulting Engineers, PC Charlotte, North Carolina
Engineered Designs Inc.
Cary, North Carolina
The Fire Consultants Inc.
Apex, North Carolina
Prepared for U.S. Army Corps of Engineers Savannah District
Ready to Advertise (RTA)
ARCHITECTURAL
ELECTRICAL MECHANICAL
STRUCTURAL CIVIL
FIRE PROTECTION
TELECOMMUNICATIONS
07/22/21
ARCHITECTURAL
7/16/2021
BUILDING 399 TRAINEE BARRACKS UPGRADE PROGRAM (TBUP) PHASE 2
FT. BENNING, GA
PROJECT TABLE OF CONTENTS Page | 1
READY TO ADVERTISE
PROJECT TABLE OF CONTENTS
DIVISION 01 - GENERAL REQUIREMENTS
01 11 00 SUMMARY OF WORK
01 14 00 WORK RESTRICTIONS
01 20 00 PRICE AND PAYMENT PROCEDURES
01 30 00 ADMINISTRATIVE REQUIREMENTS
01 32 01.00 10 PROJECT SCHEDULE
01 33 00 SUBMITTAL PROCEDURES
01 33 29 SUSTAINABILITY REQUIREMENTS AND REPORTING
ATTACHMENT A - HPSB GUIDING PRINCIPLES CHECKLIST
01 35 26 GOVERNMENT SAFETY REQUIREMENTS
01 42 00 SOURCES FOR REFERENCE PUBLICATIONS
01 45 00.00 10 QUALITY CONTROL
01 45 00.15 10 RESIDENT MANAGEMENT SYSTEM CONTRACTOR MODE (RMS CM)
01 45 35 SPECIAL INSPECTIONS
01 50 00 TEMPORARY CONSTRUCTION FACILITIES AND CONTROLS
01 57 19 TEMPORARY ENVIRONMENTAL CONTROLS
01 58 00 PROJECT IDENTIFICATION
01 74 19 CONSTRUCTION WASTE MANAGEMENT AND DISPOSAL
01 78 00 CLOSEOUT SUBMITTALS
01 78 23 OPERATION AND MAINTENANCE DATA
01 91 00.15 10 TOTAL BUILDING COMMISSIONING
ATTACHMENT A-OWNER’S PROJECT REQUIREMENTS DOCUMENT
ATTACHEMNT B-DESIGN ANALYSIS
ATTACHMENT C-DESIGN PHASE COMMISSIONING PLAN
DIVISION 02 - EXISTING CONDITIONS
02 41 00 *1 DEMOLITION AND DECONSTRUCTION
02 42 51 CARPET REMOVAL AND RECLAMATION
02 82 00 ASBESTOS REMEDIATION
APPENDIX A-HAZMAT REPORT (ATTACHED AT THE END OF THE
SPEC DOCUMENT)
02 83 00 LEAD REMEDIATION
APPENDIX A-HAZMAT REPORT (ATTACHED AT THE END OF THE
SPEC DOCUMENT)
02 85 00 MOLD REMEDIATION
DIVISION 03 – CONCRETE
03 01 00 REHABILITATION OF CONCRETE
03 01 30 RESTORATION OF CONCRETE IN HISTORIC STRUCTURES
03 30 00 CAST-IN-PLACE CONCRETE
PROJECT TABLE OF CONTENTS Page | 2
READY TO ADVERTISE
DIVISION 04 – MASONRY
04 01 20.70 UNIT MASONRY CLEANING AND RESTORATION
04 20 00 UNIT MASONRY
DIVISION 05 – METALS
05 12 00 STRUCTURAL STEEL
05 40 00 COLD-FORMED METAL FRAMING
05 50 13 MISCELLANEOUS METAL FABRICATIONS
05 52 00 METAL RAILINGS
DIVISION 06 - WOOD, PLASTICS, AND COMPOSITES
06 10 00 ROUGH CARPENTRY
06 20 00 FINISH CARPENTRY
06 61 16 SOLID SURFACING FABRICATIONS
DIVISION 07 - THERMAL AND MOISTURE PROTECTION
07 05 23 PRESSURE TESTING AN AIR BARRIER SYSTEM FOR AIR TIGHTNESS
07 16 16 *1 CRYSTALLINE WATERPROOFING
07 17 00 BENTONITE WATERPROOFING
07 21 13 BOARD AND BLOCK INSULATION
07 21 16 MINERAL FIBER BLANKET INSULATION
07 27 10.00 10 BULIDNG AIR BARRIER SYSTEM
07 27 19.01 SELF-ADHERING AIR BARRIERS
07 27 26 FLUID-APPLIED MEMBRANE AIR BARRIERS
07 27 36 SPRAY FOAM AIR BARRIERS
07 60 00 FLASHING AND SHEET METAL
07 84 00 FIRESTOPPING
07 92 00 JOINT SEALANTS
DIVISION 08 – OPENINGS
08 11 13 STEEL DOORS AND FRAMES
08 14 00 WOOD DOORS
08 31 00 ACCESS DOORS AND PANELS
08 34 73 SOUND CONTROL DOOR ASSEMBLIES
08 41 13 *1 ALUMINUM-FRAMED ENTRANCES AND STOREFRONTS
08 51 13 *1 ALUMINUM WINDOWS
08 71 00 DOOR HARDWARE
08 81 00 GLAZING
08 91 00 METAL WALL LOUVERS
DIVISION 09 – FINISHES
09 22 00 SUPPORTS FOR PLASTER AND GYPSUM BOARD
PROJECT TABLE OF CONTENTS Page | 3
READY TO ADVERTISE
09 24 23 CEMENT STUCCO
09 29 00 GYPSUMBOARD
09 30 10 CERAMIC, QUARRY, AND GLASS TILING
09 51 00 ACOUSTICAL CEILINGS
09 65 00 RESILIENT FLOORING
09 90 00 PAINTS AND COATINGS
DIVISION 10 – SPECIALTIES
10 11 00 VISUAL DISPLAY UNITS
10 14 00.20 INTERIOR SIGNAGE
10 21 13 TOILET COMPARTMENTS
10 26 00 WALL AND DOOR PROTECTION
10 28 13 TOILET ACCESSORIES
10 51 13 METAL LOCKERS
DIVISION 12 – FURNISHINGS
12 24 13 ROLLER WINDOW SHADES
DIVISION 14 – CONVEYING EQUIPMENT
14 21 23 ELECTRIC TRACTION PASSENGER ELEVATORS
DIVISION 21 - FIRE SUPPRESSION
21 12 00 STANDPIPE SYSTEMS
21 13 13 *1 WET PIPE SPRINKLER SYSTEMS, FIRE PROTECTION
23 13 16 DRY PIPE SPRINKER SYSTEMS, FIRE PROTECTION
DIVISION 22 – PLUMBING
22 00 00 PLUMBING, GENERAL PURPOSE
22 07 19.00 40 PLUMBING PIPING INSULATION
DIVISION 23 - HEATING, VENTILATING, AND AIR CONDITIONING (HVAC)
23 03 00.00 20 BASIC MECHANICAL MATERIALS AND METHODS
23 05 15 COMMON PIPING FOR HVAC
23 05 48.00 40 VIBRATION AND SEISMIC CONTROLS FOR HVAC PIPING AND
EQUIPMENT
23 05 93 TESTING, ADJUSTING, AND BALANCING FOR HVAC
23 07 00 THERMAL INSULATION FOR MECHANICAL SYSTEMS
23 09 00 INSTRUMENTATION AND CONTROL FOR HVAC
23 09 13 INSTRUMENTATION AND CONTROL DEVICES FOR HVAC
23 09 23.01 LONWORKS DIRECT DIGITAL CONTROL FOR HVAC AND OTHER
BUILDING
CONTROL SYSTEMS
PROJECT TABLE OF CONTENTS Page | 4
READY TO ADVERTISE
23 11 20 FACILITY GAS PIPING
23 23 00 REFRIGERANT PIPING
23 25 00 CHEMICAL TREATMENT OF WATER FOR MECHANICAL SYSTEMS
23 30 00 HVAC AIR DISTRIBUTION
23 52 00 HEATING BOILERS
23 64 10 WATER CHILLERS, VAPOR COMPRESSION TYPE
23 64 26 CHILLED, CHILLED-HOT, AND CONDENSER WATER PIPING
SYSTEMS
23 81 00 DECENTRALIZED UNITARY HVAC EQUIPMENT
23 81 47 *1 WATER-LOOP AND GROUND-LOOP HEAT PUMP SYSTEMS
DIVISION 25 – INTEGRATED AUTOMATION
25 05 11.01 CYBERSECURITY FOR FACILITY-RELATED CONTROL SYSTEMS
(HVAC)
ATTACHMENT A - L-L-L CCI CHECKLIST - HVAC
25 05 11.02 CYBERSECURITY FOR FACILITY-RELATED CONTROL SYSTEMS
(FIRE ALARM)
ATTACHMENT A – L-L-L CCI CHECKLIST - FAMNS
DIVISION 26 – ELECTRICAL
26 20 00.00 20 BASIC ELECTRICAL MATERIALS AND METHODS
26 08 00 APPARATUS INSPECTION AND TESTING
26 20 00 INTERIOR DISTRIBUTION SYSTEM
26 28 01.00 10 COORDINATED POWER SYSTEM PROTECTION
26 29 23 ADUSTABLE SPEED DRIVE (ASD) SYSTEMS UNDER 600 VOLTS
26 36 00.00 10 AUTOMATIC TRANSFER SWITCH AND BY-PASS/ISOLATION SWITCH
26 51 00 INTERIOR LIGHTING
26 56 00 EXTERIOR LIGHTING
DIVISION 27 – COMMUNICATIONS
27 05 13.43 TELEVISION DISTRIBUTION SYSTEM
27 05 28.36 40 CABLE TRAYS FOR COMMUNICATIONS SYSTEMS
27 10 00 BUILDING TELECOMMUNICATIONS CABLING SYSTEM
DIVISION 28 – ELECTRONIC SAFETY and SECURITY
28 31 76 INTERIOR FIRE ALARM SYSTEM, ADDRESSABLE
DIVISION 31 - EARTHWORK
31 00 00 EARTHWORK
31 31 16.13 CHEMICAL TERMITE CONTROL
DIVISION 32 - EXTERIOR IMPROVEMENTS
32 11 20 BASE COURSE FOR RIGID AND SUBBASES FOR FLEXIBLE PAVING
32 12 16.16 ROAD-MIX ASPHALT PAVING
PROJECT TABLE OF CONTENTS Page | 5
READY TO ADVERTISE
32 13 13.06 PORTLAND CEMENT PAVEMENT FOR ROADS AND SITE FACILITIES
32 16 19 CONCRETE CURBS, GUTTERS AND SIDEWALKS
32 17 23 *1 PAVEMENT MARKINGS
32 92 19 SEEDING
32 92 23 SODDING
DIVISION 33 – UTILITIES
33 11 23 NATURAL GAS AND LIQUID PETROLEUM PIPING
33 71 02 UNDERGROUND ELECTRICAL DISTRIBUTION
APPENDIX A – HAZMAT REPORT
-- End of Project Table of Contents –
Building 399 Trainee Barracks Upgrade Program (TBUP) Phase 2 PN 90737 Ft, Benning, GA
SECTION TABLE OF CONTENTS
DIVISION 01 - GENERAL REQUIREMENTS
SECTION 01 11 00
SUMMARY OF WORK
08/15
PART 1 GENERAL
1.1 SUBMITTALS
1.2 WORK COVERED BY CONTRACT DOCUMENTS
1.2.1 Project Description
1.2.2 Location
1.3 OCCUPANCY OF PREMISES
1.4 EXISTING WORK
1.5 LOCATION OF UNDERGROUND UTILITIES
1.5.1 Notification Prior to Excavation
1.6 SALVAGE MATERIAL AND EQUIPMENT
PART 2 PRODUCTS
PART 3 EXECUTION
-- End of Section Table of Contents --
SECTION 01 11 00 Page 1
THIS PAGE INTENTIONALLY LEFT BLANK
SECTION 01 11 00 Page 2
SECTION 01 11 00
SUMMARY OF WORK
08/15
PART 1 GENERAL
1.1 SUBMITTALS
Government approval is required for submittals with a "G" designation;
submittals not having a "G" designation are for information only. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government. Submittals with an "S" are for inclusion in the Sustainability eNotebook, in conformance with Section 01 33 29 SUSTAINABILITY REPORTING. Submit the following in accordance with Section 01 33 00 SUBMITTAL PROCEDURES:
SD-01 Preconstruction Submittals
Salvage Plan ; G, RO
1.2 WORK COVERED BY CONTRACT DOCUMENTS
1.2.1 Project Description
This is a three story, permanent construction barracks built in 1929, currently designated to house Non Commission Officer Academy (NCOA) Senior Enlisted students and permanent party personnel. The entire facility is in failed or failing condition. This project will correct the state of disrepair throughout the building. The facility has never undergone any comprehensive infrastructure systems restoration- only patchwork repairs have been accomplished. The following building components and systems will be restored and repaired for the following reasons:
Hazardous Material/Demolition: Hazardous materials have not been abated from the building. Asbestos and lead base paint will be identified in a hazardous materials survey and will be abated as part of the project. This project will demolish some elements of the building as part of the process to accomplish the repairs. Work will be accomplished separate from the living areas and no personnel will be exposed to any type of hazards following local and federal regulations.
Architectural: Some of the architectural systems that have been identified and have failed include windows, doors, walls, floors, and ceilings.
Because of the deterioration, the water entering some of the sleeping areas is causing damage in the listed architectural components. Moreover, exterior doors and windows do not meet antiterrorism standard compliance in UFC 4-010-01 and TM 5-853-1.
Mechanical and Plumbing Systems: The air conditioning and heating systems do not meet current ASHRAE criteria and do not comply with current Army energy requirements. They are currently energy inefficient. It is estimated that a 10% to 15% energy saving could be achieved through system repair by replacement. The existing facility lacks proper humidity controls and air changes. The air conditioning system does not properly control the condensation buildup above the ceilings. The plumbing shows signs of wear with evidence of leakage in latrine areas. The laundry vents
SECTION 01 11 00 Page 3 are failing and require repair. During the use of air conditioning systems, condensation causes deterioration of all finish materials on walls, floors, and ceilings, creating an unacceptable mold and mildew situation which may affect the health of Soldiers living in these quarters.
Electrical and Lighting Systems: The electrical system was not designed to meet modern electrical demand and is failing. Lighting fixtures are energy inefficient fluorescent fixtures with magnetic ballasts. The electrical panels are antiquated and do not meet the NFPA 70 code requirements. The entire electrical system needs to be restored.
Fire Safety: Building 399 lacks a fire suppression system in all areas and requires the installation of a wet pipe fire suppression system to meet code requirements in NFPA 101. Additionally, fire and smoke detection, fire alarms and notification systems must be repaired by replacement. A mass notification system is also required to meet code.
Furniture, Fixture and Equipment: Loose furniture listed in furniture legend is not included in the contractor's scope of work, however, all roller shades listed (A-2 through A-6) are including in the contractor's scope) as well as shower curtains, rods, bulletin boards, closet shelving and all fixed FF&E items.
1.2.2 Location
The work is located at Fort Benning, Georgia . The exact location will be shown by the Contracting Officer.
1.3 OCCUPANCY OF PREMISES
Building portions B & C will not be occupied. The remaining portions of the building will be occupied during performance of work under this Contract. Those areas must remain accessible by occupants and utilities remain operational. Occupancy notifications will be posted in a prominent location in the work area.
Before work is started, arrange with the Contracting Officer a sequence of procedure, means of access, space for storage of materials and equipment, and use of approaches, corridors, and stairways.
Failure to obtain entry approval to the installation will not affect the contract price or time of completion.
1.4 EXISTING WORK
In addition to FAR 52.236-9 Protection of Existing Vegetation, Structures, Equipment, Utilities, and Improvements:
a. Remove or alter existing work in such a manner as to prevent injury or damage to any portions of the existing work which remain.
b. Repair or replace portions of existing work which have been altered during construction operations to match existing or adjoining work, as approved by the Contracting Officer. At the completion of operations, existing work must be in a condition equal to or better than that which existed before new work started.
c. Contractor shall be responsible for removing and disposing of any
SECTION 01 11 00 Page 4 mattresses, furniture, appliances, etc. left in the rooms.
1.5 LOCATION OF UNDERGROUND UTILITIES
Obtain digging permits prior to start of excavation, and comply with Installation requirements for locating and marking underground utilities.
Contact local utility locating service a minimum of 7 days prior to excavating, to mark utilities, and within sufficient time required if work occurs on a Monday or after a Holiday. Verify existing utility locations indicated on contract drawings, within area of work.
Identify and mark all other utilities not managed and located by the local utility companies. Scan the construction site with Ground Penetrating Radar (GPR), electromagnetic, or sonic equipment, and mark the surface of the ground or paved surface where existing underground utilities or utilities encased in pier structures are discovered. Verify the elevations of existing piping, utilities,and any type of underground or encased obstruction not indicated, or specified to be removed, that is indicated or discovered during scanning, in locations to be traversed by piping, ducts, and other work to be conducted or installed. Verify elevations before installing new work closer than nearest manhole or other structure at which an adjustment in grade can be made.
1.5.1 Notification Prior to Excavation
Notify the Contracting Officer at least 48 hours prior to starting excavation work.
1.6 SALVAGE MATERIAL AND EQUIPMENT
Items designated by the Contracting Officer to be salvaged remain the property of the Government. Segregate, itemize, deliver and off-load the salvaged property at the Government designated storage area located within five miles of the construction site.
Provide a salvage plan , listing material and equipment to be salvaged, and their storage location. Maintain property control records for material or equipment designated as salvage. Use a system of property control that is approved by the Contracting Officer. Store and protect salvaged materials and equipment until disposition by the Contracting Officer.
Items to be salvaged:
a. Fire Alarm equipment.
b. Fire Alarm field devices.
PART 2 PRODUCTS
Not used.
PART 3 EXECUTION
Not used.
-- End of Section --
SECTION 01 11 00 Page 5
SECTION 01 11 00 Page 6
SECTION TABLE OF CONTENTS
DIVISION 01 - GENERAL REQUIREMENTS
SECTION 01 14 00
WORK RESTRICTIONS
11/ 11, CHG 11: 11/ 20
PART 1 GENERAL
1.1 SUBMITTALS
1.2 SPECIAL SCHEDULING REQUIREMENTS
1.3 CONTRACTOR ACCESS AND USE OF PREMISES
1.3.1 Activity Regulations
1.3.1.1 Subcontractors and Personnel Contacts
1.3.1.2 Personnel Entry Approval
1.3.1.3 No Smoking Policy
1.3.2 Working Hours
1.3.3 Work Outside Regular Hours
1.3.4 Occupied Buildings
1.3.5 Utility Cutovers and Interruptions
1.4 SECURITY REQUIREMENTS
PART 2 PRODUCTS
PART 3 EXECUTION
SECTION 01 14 00 Page 1
SECTION 01 14 00 Page 2
SECTION 01 14 00
WORK RESTRICTIONS
11/ 11, CHG 11: 11/ 20
PART 1 GENERAL
1.1 SUBMITTALS
Government approval is required for submittals with a "G" or "S" classification. Submittals not having a "G" or "S" classification are for information only. When used, a code following the "G" classification identifies the office that will review the submittal for the Government.
Submit the following in accordance with Section 01 33 00 SUBMITTAL
PROCEDURES:
SD-01 Preconstruction Submittals
List of Contact Personnel
1.2 SPECIAL SCHEDULING REQUIREMENTS
a. The existing facility will remain in operation during the entire construction period. The Contractor must conduct his operations so as to cause the least possible interference with normal operations of the activity.
b. Permission to interrupt any Activity roads, railroads, or utility service must be requested in writing a minimum of 15 calendar days prior to the desired date of interruption.
c. The work under this contract requires special attention to the scheduling and conduct of the work in connection with existing operations. Identify on the construction schedule each factor which constitutes a potential interruption to operations.
1.3 CONTRACTOR ACCESS AND USE OF PREMISES
1.3.1 Activity Regulations
Ensure that Contractor personnel employed on the Activity become familiar with and obey Activity regulations including safety, fire, traffic and security regulations. Keep within the limits of the work and avenues of ingress and egress. Wear appropriate personal protective equipment (PPE) in designated areas. Do not enter any restricted areas unless required to do so and until cleared for such entry. Mark Contractor equipment for identification.
1.3.1.1 Subcontractors and Personnel Contacts
Provide a list of contact personnel of the Contractor and subcontractors including addresses and telephone numbers for use in the event of an emergency. As changes occur and additional information becomes available, correct and change the information contained in previous lists.
SECTION 01 14 00 Page 3
1.3.1.2 Personnel Entry Approval
Failure to obtain entry approval will not affect the contract price or time of completion.
1.3.1.3 No Smoking Policy
Smoking is prohibited within and outside of all buildings on installation, except in designated smoking areas. This applies to existing buildings, buildings under construction and buildings under renovation. Discarding tobacco materials other than into designated tobacco receptacles is considered littering and is subject to fines. The Contracting Officer will identify designated smoking areas.
1.3.2 Working Hours
Regular working hours will consist of an 9 hour period established by the Contracting Officer, between 7 a.m. and 4:00 p.m., Monday through Friday and 7 a.m. to 3:30 p.m. on Saturday, excluding Government holidays.
1.3.3 Work Outside Regular Hours
Work outside regular working hours requires Contracting Officer approval.
Make application 15 calendar days prior to such work to allow arrangements to be made by the Government for inspecting the work in progress, giving the specific dates, hours, location, type of work to be performed, contract number and project title. Based on the justification provided, the Contracting Officer may approve work outside regular hours. During periods of darkness, the different parts of the work must be lighted in a manner approved by the Contracting Officer. Make utility cutovers after normal working hours or on Saturdays, Sundays, and Government holidays unless directed otherwise.
1.3.4 Occupied Buildings
The Contractor shall be working in and around existing buildings which are occupied. Do not enter the buildings without prior approval of the Contracting Officer.
The existing buildings and their contents must be kept secure at all times. Provide temporary closures as required to maintain security as directed by the Contracting Officer.
Provide dust covers or protective enclosures to protect existing work that remains, and Government material during the construction period.
Relocate movable furniture away from the Contractor's working area as required to perform the work, protect the furniture, and replace the furniture in their original locations upon completion of the work. Leave attached equipment in place, and protect them against damage, or temporarily disconnect, relocate, protect, and reinstall them at the completion of the work.
The Government will remove and relocate other Government property in the areas of the buildings scheduled to receive work.
1.3.5 Utility Cutovers and Interruptions
a. Make utility cutovers and interruptions after normal working hours or
SECTION 01 14 00 Page 4 on Saturdays, Sundays, and Government holidays. Conform to procedures required in paragraph WORK OUTSIDE REGULAR HOURS.
b. Ensure that new utility lines are complete, except for the connection, before interrupting existing service.
c. Interruption to water, sanitary sewer, storm sewer, telephone service, electric service, air conditioning, heating, fire alarm, compressed air, and natural gas are considered utility cutovers pursuant to the paragraph WORK OUTSIDE REGULAR HOURS. Such interruptions are further limited to 8 hours. This time limit includes time for deactivation and reactivation.
d. Operation of Station Utilities: The Contractor must not operate nor disturb the setting of control devices in the station utilities system, including water, sewer, electrical, and steam services. The Government will operate the control devices as required for normal conduct of the work. The Contractor must notify the Contracting Officer giving reasonable advance notice when such operation is required.
1.4 SECURITY REQUIREMENTS
Contract Clause FAR 52.204-2 Security Requirements and Alternate II ," "FAC 5252.236-9301, Special Working Conditions and Entry to Work Area," and the following apply:
Submit for approval, at least 15 days prior to the desired date of entry, an original alphabetical list of personnel who require entry into Government property to perform work on the project.
Furnish for each person:
a. Name
b. Date and Place of Birth
c. Citizenship
d. Home Address
e. Driver's License or Photo Identification
PART 2 PRODUCTS
Not Used
PART 3 EXECUTION
Not Used
SECTION 01 14 00 Page 5
SECTION 01 14 00 Page 6
SECTION TABLE OF CONTENTS
DIVISION 01 - GENERAL REQUIREMENTS
SECTION 01 20 00
PRICE AND PAYMENT PROCEDURES
11/ 20, CHG 1: 02/ 21
PART 1 GENERAL
1.1 REFERENCES
1.2 SUBMITTALS
1.3 CONTRACT COST BREAKDOWN
1.4 CONTRACTOR'S INVOICE AND CONTRACT PERFORMANCE STATEMENT
1.5 SINGLE JOB PAYMENT ITEMS
1.6 UNIT PRICE PAYMENT ITEMS
1.6.1 Deformed Steel Bars for Concrete Reinforcement
1.6.1.1 Payment
1.6.1.2 Measurement
1.6.1.3 Unit of Measure
PART 2 PRODUCTS
PART 3 EXECUTION
SECTION 01 20 00 Page 1
SECTION 01 20 00 Page 2
SECTION 01 20 00
PRICE AND PAYMENT PROCEDURES
11/ 20, CHG 1: 02/ 21
PART 1 GENERAL
1.1 REFERENCES
The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.
ASTM INTERNATIONAL (ASTM)
ASTM A615/A615M (2020) Standard Specification for Deformed and Plain Carbon-Steel Bars for Concrete Reinforcement
1.2 SUBMITTALS
Government approval is required for submittals with a "G" or "S" classification. Submittals not having a "G" or "S" classification are for information only. When used, a code following the "G" classification identifies the office that will review the submittal for the Government.
Submit the following in accordance with Section 01 33 00 SUBMITTAL
PROCEDURES:
SD-03 Product Data
Weight Certificates
1.3 CONTRACT COST BREAKDOWN
The Contractor must furnish within 30 days after the date of Notice to Proceed, and prior to the submission of its first partial payment estimate, a breakdown of its single job pay item or items which will be reviewed by the Contracting Officer as to propriety of distribution of the total cost to the various accounts. Any unbalanced items as between early and late payment items or other discrepancies will be revised by the Contracting Officer to agree with a reasonable cost of the work included in the various items. This Contract cost breakdown will then be utilized as the basis for progress payments to the Contractor.
1.4 CONTRACTOR'S INVOICE AND CONTRACT PERFORMANCE STATEMENT
1.5 SINGLE JOB PAYMENT ITEMS
Payment items for the work of this Contract for which Contract job payments will be made are listed in the SCHEDULE and described below. All costs for items of work, which are not specifically mentioned to be included in a particular job or unit price payment item, are included in the listed job item most closely associated with the work involved. The job price and payment made for each item listed constitutes full compensation for furnishing all plant, labor, materials, and equipment, and performing any associated Contractor quality control, environmental protection, meeting safety requirements, tests and reports, and for
SECTION 01 20 00 Page 3 performing all work required for which separate payment is not otherwise provided.
1.6 UNIT PRICE PAYMENT ITEMS
Payment items for the work of this Contract on which the Contract unit price payments will be made are listed in the SCHEDULE and described below. The unit price and payment made for each item listed constitutes full compensation for furnishing all plant, labor, materials, and equipment, and performing any associated Contractor quality control, environmental protection, meeting safety requirements, tests and reports, and for performing all work required for each of the unit price items.
1.6.1 Deformed Steel Bars for Concrete Reinforcement
1.6.1.1 Payment
Payment will be made for costs associated with furnishing, transporting, delivering, and placing deformed steel bars for concrete reinforcement, which includes steel in laps as indicated or as required. No payment will be made for the additional steel in laps which are authorized for the convenience of the Contractor. No separate payment will be made for accessories; include payment in the Contract unit price for the items of work to which the accessories are incidental.
1.6.1.2 Measurement
The measured lengths of deformed steel bars for concrete reinforcement will be converted to weights for the size of bars listed by the use of the nominal weights per lineal foot specified in ASTM A615/A615M .
1.6.1.3 Unit of Measure
Unit of measure: per pound in place.
PART 2 PRODUCTS
Not Used
PART 3 EXECUTION
Not Used
SECTION 01 20 00 Page 4
SECTION TABLE OF CONTENTS
DIVISION 01 - GENERAL REQUIREMENTS
SECTION 01 30 00
ADMINISTRATIVE REQUIREMENTS
11/20
PART 1 GENERAL
1.1 REFERENCES
1.2 SUBMITTALS
1.3 PROGRESS AND COMPLETION PICTURES
1.4 MINIMUM INSURANCE REQUIREMENTS
1.5 SUPERVISION
1.5.1 Superintendent Qualifications
1.5.2 Minimum Communication Requirements
1.5.3 Duties
1.5.4 Non-Compliance Actions
1.6 PRECONSTRUCTION CONFERENCE
1.6.1 Attendees
1.7 MOBILIZATION
PART 2 PRODUCTS
PART 3 EXECUTION
SECTION 01 30 00 Page 1
SECTION 01 30 00 Page 2
SECTION 01 30 00
ADMINISTRATIVE REQUIREMENTS
11/20
PART 1 GENERAL
1.1 REFERENCES
The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.
U.S. ARMY CORPS OF ENGINEERS (USACE)
EM 385-1-1 (2014) Safety and Health Requirements Manual
1.2 SUBMITTALS
Government approval is required for submittals with a "G" or "S" classification. Submittals not having a "G" or "S" classification are for information only. When used, a code following the "G" classification identifies the office that will review the submittal for the Government.
Submit the following in accordance with Section 01 33 00 SUBMITTAL
PROCEDURES:
SD-01 Preconstruction Submittals
Progress and Completion Pictures
1.3 PROGRESS AND COMPLETION PICTURES
Photographically document site conditions prior to start of construction operations. Provide monthly, and within one month of the completion of work, digital photographs, 1600x1200x24 bit true color 300 dpi minimum resolution in JPEG file format showing the sequence and progress of work.
Take a minimum of 20 digital photographs each week throughout the entire project from a minimum of ten different viewpoints selected by the Contractor unless otherwise directed by the Contracting Officer. Submit with the monthly invoice two sets of digital photographs, each set on a separate compact disc (CD) or data versatile disc (DVD), cumulative of all photos to date. Indicate photographs demonstrating environmental procedures. Provide photographs for each month in a separate monthly directory and name each file to indicate its location on the view location sketch. Also provide the view location sketch on the CD or DVD as a digital file. Include a date designator in file names. Photographs provided are for unrestricted use by the Government.
1.4 MINIMUM INSURANCE REQUIREMENTS
Provide the minimum insurance coverage required by FAR 28.307-2 Liability, during the entire period of performance under this contract. Provide other insurance coverage as required by State law.
SECTION 01 30 00 Page 3
1.5 SUPERVISION
1.5.1 Superintendent Qualifications
Provide project superintendent with a minimum of 10 years experience in construction with at least 5 of those years as a superintendent on projects similar in size and complexity. The individual must be familiar with the requirements of EM 385-1-1 and have experience in the areas of hazard identification and safety compliance. The individual must be capable of interpreting a critical path schedule and construction drawings. The qualification requirements for the alternate superintendent are the same as for the project superintendent. The Contracting Officer may request proof of the superintendent's qualifications at any point in the project if the performance of the superintendent is in question.
For projects where the superintendent is permitted to also serve as the Quality Control (QC) Manager as established in Section 01 45 00.00 10 QUALITY CONTROL, the superintendent must have qualifications in accordance with that section.
1.5.2 Minimum Communication Requirements
Have at least one qualified superintendent, or competent alternate, capable of reading, writing, and conversing fluently in the English language, on the job-site at all times during the performance of Contract work.In addition, if a Quality Control (QC) representative is required on the Contract, then that individual must also have fluent English communication skills.
1.5.3 Duties
The project superintendent is primarily responsible for managing subcontractors and coordinating day-to-day production and schedule adherence on the project. The superintendent is required to attend partnering meetings, and quality control meetings. The superintendent or qualified alternative must be on-site at all times during the performance of this contract until the work is completed and accepted.
1.5.4 Non-Compliance Actions
The Project Superintendent is subject to removal by the Contracting Officer for non-compliance with requirements specified in the contract and for failure to manage the project to ensure timely completion.
Furthermore, the Contracting Officer may issue an order stopping all or part of the work until satisfactory corrective action has been taken. No part of the time lost due to such stop orders is acceptable as the subject of claim for extension of time for excess costs or damages by the Contractor.
1.6 PRECONSTRUCTION CONFERENCE
, prior to commencing any work at the site, coordinate with the Contracting Officer a time and place to meet for the Preconstruction Conference . The conference must take place within 35 calendar days after award of the contract, but prior to commencement of any work at the site.
The purpose of this conference is to discuss and develop a mutual understanding of the administrative requirements of the Contract including but not limited to: daily reporting, invoicing, value engineering, safety, base-access, outage requests, hot work permits, schedule requirements, SECTION 01 30 00 Page 4 quality control, schedule of prices or earned value report, shop drawings, submittals, cybersecurity, prosecution of the work, government acceptance, final inspections and contract close-out. Contractor must present and discuss their basic approach to scheduling the construction work and any required phasing.
1.6.1 Attendees
Contractor attendees must include the Project Manager, Superintendent, Site Safety and Health Officer (SSHO), Quality Control Manager and major subcontractors.
1.7 MOBILIZATION
Contractor shall mobilize to the jobsite within 60 calendar days of contract award. Mobilize is defined as having equipment AND having a physical presence of at least one person from the contractor's team on the jobsite.
PART 2 PRODUCTS
Not Used
PART 3 EXECUTION
Not Used
SECTION 01 30 00 Page 5
SECTION 01 30 00 Page 6
SECTION TABLE OF CONTENTS
DIVISION 01 - GENERAL REQUIREMENTS
SECTION 01 32 01.00 1
PROJECT SCHEDULE
02/15
PART 1 GENERAL
1.1 REFERENCES
1.2 SUBMITTALS
1.3 PROJECT SCHEDULER QUALIFICATIONS
PART 2 PRODUCTS
2.1 SOFTWARE
2.1.1 Government Default Software
2.1.2 Contractor Software
2.1.2.1 Primavera
2.1.2.2 Other Than Primavera
PART 3 EXECUTION
3.1 GENERAL REQUIREMENTS
3.2 BASIS FOR PAYMENT AND COST LOADING
3.2.1 Activity Cost Loading
3.2.2 Withholdings / Payment Rejection
3.3 PROJECT SCHEDULE DETAILED REQUIREMENTS
3.3.1 Level of Detail Required
3.3.2 Activity Durations
3.3.3 Procurement Activities
3.3.4 Mandatory Tasks
3.3.5 Government Activities
3.3.6 Standard Activity Coding Dictionary
3.3.6.1 Workers Per Day (WRKP)
3.3.6.2 Responsible Party Coding (RESP)
3.3.6.3 Area of Work Coding (AREA)
3.3.6.4 Modification Number (MODF)
3.3.6.5 Bid Item Coding (BIDI)
3.3.6.6 Phase of Work Coding (PHAS)
3.3.6.7 Category of Work Coding (CATW)
3.3.6.8 Feature of Work Coding (FOW)
3.3.7 Contract Milestones and Constraints
3.3.7.1 Project Start Date Milestone and Constraint
3.3.7.2 End Project Finish Milestone and Constraint
3.3.7.3 Interim Completion Dates and Constraints
3.3.7.3.1 Start Phase
3.3.7.3.2 End Phase
3.3.8 Calendars
3.3.9 Open Ended Logic
3.3.10 Default Progress Data Disallowed
3.3.11 Out-of-Sequence Progress
3.3.12 Added and Deleted Activities
SECTION 01 32 01.00 10 Page 1
3.3.13 Original Durations
3.3.14 Leads, Lags, and Start to Finish Relationships
3.3.15 Retained Logic
3.3.16 Percent Complete
3.3.17 Remaining Duration
3.3.18 Cost Loading of Closeout Activities
3.3.18.1 As-Built Drawings
3.3.18.2 O & M Manuals
3.3.19 Early Completion Schedule and the Right to Finish Early
3.4 PROJECT SCHEDULE SUBMISSIONS
3.4.1 Preliminary Project Schedule Submission
3.4.2 Initial Project Schedule Submission
3.4.3 Periodic Schedule Updates
3.5 SUBMISSION REQUIREMENTS
3.5.1 Data CD/DVDs
3.5.2 Narrative Report
3.5.3 Schedule Reports
3.5.3.1 Activity Report
3.5.3.2 Logic Report
3.5.3.3 Total Float Report
3.5.3.4 Earnings Report by CLIN
3.5.3.5 Schedule Log
3.5.4 Network Diagram
3.5.4.1 Continuous Flow
3.5.4.2 Project Milestone Dates
3.5.4.3 Critical Path
3.5.4.4 Banding
3.5.4.5 Cash Flow / Schedule Variance Control (SVC) Diagram
3.6 PERIODIC SCHEDULE UPDATE
3.6.1 Periodic Schedule Update Meetings
3.6.2 Update Submission Following Progress Meeting
3.7 WEEKLY PROGRESS MEETINGS
3.8 REQUESTS FOR TIME EXTENSIONS
3.8.1 Justification of Delay
3.8.2 Time Impact Analysis (Prospective Analysis)
3.8.3 Forensic Schedule Analysis (Retrospective Analysis)
3.8.4 Fragmentary Network (Fragnet)
3.8.5 Time Extension
3.8.6 Impact to Early Completion Schedule
3.9 FAILURE TO ACHIEVE PROGRESS
3.9.1 Artificially Improving Progress
3.9.2 Failure to Perform
3.9.3 Recovery Schedule
3.10 OWNERSHIP OF FLOAT
3.11 TRANSFER OF SCHEDULE DATA INTO RMS/QCS
3.12 PRIMAVERA P6 MANDATORY REQUIREMENTS
SECTION 01 32 01.00 10 Page 2
SECTION 01 32 01.00 1
PROJECT SCHEDULE
02/15
PART 1 GENERAL
1.1 REFERENCES
The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.
AACE INTERNATIONAL (AACE)
AACE 29R-03 (2011) Forensic Schedule Analysis
AACE 52R-06 (2006) Time Impact Analysis - As Applied in Construction
U.S. ARMY CORPS OF ENGINEERS (USACE)
ER 1-1-11 (1995) Administration -- Progress, Schedules, and Network Analysis Systems
1.2 SUBMITTALS
Government approval is required for submittals with a "G" designation;
submittals not having a "G" designation are for When used, a designation following the "G" designation identifies the office that will review the submittal for the Government. Submittals with an "S" are for inclusion in the Sustainability eNotebook, in conformance to Section 01 33 29 SUSTAINABILITY REPORTING. Submit the following in accordance with Section 01 33 00 SUBMITTAL PROCEDURES:
SD-01 Preconstruction Submittals
Project Scheduler Qualifications ; G, RO
Preliminary Project Schedule ; G, RO
Initial Project Schedule ; G, RO
Periodic Schedule Update ; G, RO
1.3 PROJECT SCHEDULER QUALIFICATIONS
Designate an authorized representative to be responsible for the preparation of the schedule and all required updating and production of reports. The authorized representative must have a minimum of 2-years experience scheduling construction projects similar in size and nature to this project with scheduling software that meets the requirements of this specification. Representative must have a comprehensive knowledge of CPM scheduling principles and application.
SECTION 01 32 01.00 10 Page 3
PART 2 PRODUCTS
2.1 SOFTWARE
The scheduling software utilized to produce and update the schedules required herein must be capable of meeting all requirements of this specification.
2.1.1 Government Default Software
The Government intends to use Primavera P6.
2.1.2 Contractor Software
Scheduling software used by the contractor must be commercially available from the software vendor for purchase with vendor software support agreements available. The software routine used to create the required sdef file must be created and supported by the software manufacturer.
2.1.2.1 Primavera
If Primavera P6 is selected for use, provide the "xer" export file in a version of P6 importable by the Government system.
2.1.2.2 Other Than Primavera
If the contractor chooses software other than Primavera P6, that is compliant with this specification, provide for the Government's use two licenses, two computers, and training for two Government employees in the use of the software. These computers will be stand-alone and not connected to Government network. Computers and licenses will be returned at project completion.
PART 3 EXECUTION
3.1 GENERAL REQUIREMENTS
Prepare for approval a Project Schedule, as specified herein, pursuant to FAR Clause 52.236-15 Schedules for Construction Contracts. Show in the schedule the proposed sequence to perform the work and dates contemplated for starting and completing all schedule activities. The scheduling of the entire project is required. The scheduling of construction is the responsibility of the Contractor. Contractor management personnel must actively participate in its development. Subcontractors and suppliers working on the project must also contribute in developing and maintaining an accurate Project Schedule. Provide a schedule that is a forward planning as well as a project monitoring tool. Use the Critical Path Method (CPM) of network calculation to generate all Project Schedules.
Prepare each Project Schedule using the Precedence Diagram Method (PDM).
3.2 BASIS FOR PAYMENT AND COST LOADING
The schedule is the basis for determining contract earnings during each update period and therefore the amount of each progress payment. The aggregate value of all activities coded to a contract CLIN must equal the value of the CLIN.
SECTION 01 32 01.00 10 Page 4
3.2.1 Activity Cost Loading
Activity cost loading must be reasonable and without front-end loading.
Provide additional documentation to demonstrate reasonableness if requested by the Contracting Officer.
3.2.2 Withholdings / Payment Rejection
Failure to meet the requirements of this specification may result in the disapproval of the preliminary, initial or periodic schedule updates and subsequent rejection of payment requests until compliance is met.
In the event that the Contracting Officer directs schedule revisions and those revisions have not been included in subsequent Project Schedule revisions or updates, the Contracting Officer may withhold 10 percent of pay request amount from each payment period until such revisions to the project schedule have been made.
3.3 PROJECT SCHEDULE DETAILED REQUIREMENTS
3.3.1 Level of Detail Required
Develop the Project Schedule to the appropriate level of detail to address major milestones and to allow for satisfactory project planning and execution. Failure to develop the Project Schedule to an appropriate level of detail will result in its disapproval. The Contracting Officer will consider, but is not limited to, the following characteristics and requirements to determine appropriate level of detail:
3.3.2 Activity Durations
Reasonable activity durations are those that allow the progress of ongoing activities to be accurately determined between update periods.
Less than 2 percent of all non-procurement activities may have Original Durations (OD) greater than 20 work days or 30 calendar days.
3.3.3 Procurement Activities
Include activities associated with the critical submittals and their approvals, procurement, fabrication, and delivery of long lead materials, equipment, fabricated assemblies, and supplies. Long lead procurement activities are those with an anticipated procurement sequence of over 90 calendar days.
3.3.4 Mandatory Tasks
Include the following activities/tasks in the initial project schedule and all updates.
a. Submission, review and acceptance of SD-01 Preconstruction Submittals (individual activity for each).
b. Submission, review and acceptance of features require design completion
c. Submission of mechanical/electrical/information systems layout drawings.
d. Long procurement activities
SECTION 01 32 01.00 10 Page 5
e. Submission and approval of O & M manuals.
f. Submission and approval of as-built drawings.
g. Submission and approval of DD1354 data and installed equipment lists.
h. Submission and approval of testing and air balance (TAB).
i. Submission of TAB specialist design review report.
j. Submission and approval of fire protection specialist.
k. Submission and approval of Building Commissioning Plan, test data, and reports: Develop the schedule logic associated with testing and commissioning of mechanical systems to a level of detail consistent with the contract commissioning requirements. All tasks associated with all building testing and commissioning will be completed prior to submission of building commissioning report and subsequent contract completion.
l. Air and water balancing.
m. Building commissioning - Functional Performance Testing.
n. Controls testing plan submission.
o. Controls testing.
p. Performance Verification testing.
q. Other systems testing, if required.
r. Contractor's pre-final inspection.
s. Correction of punch list from Contractor's pre-final inspection.
t. Government's pre-final inspection.
u. Correction of punch list from Government's pre-final inspection.
v. Final inspection.
3.3.5 Government Activities
Show Government and other agency activities that could impact progress.
These activities include, but are not limited to: approvals, environmental permit approvals by State regulators, inspections, utility tie-in, Government Furnished Equipment (GFE) and Notice to Proceed (NTP) for phasing requirements.
3.3.6 Standard Activity Coding Dictionary
Use the activity coding structure defined in the Standard Data Exchange Format (SDEF) in ER 1-1-11 . This exact structure is mandatory. Develop and assign all Activity Codes to activities as detailed herein. A template SDEF compatible schedule backup file is available on the QCS web site: http://rms.usace.army.mil .
The SDEF format is as follows:
SECTION 01 32 01.00 10 Page 6
Field Activity Code Length Description
1 WRKP 3 Workers per day
2 RESP 4 Responsible party
3 AREA 4 Area of work
4 MODF 6 Modification Number
5 BIDI 6 Bid Item (CLIN)
6 PHAS 2 Phase of work
7 CATW 1 Category of work
8 FOW 20 Feature of work*
*Some systems require that FEATURE OF WORK values be placed in several activity code fields. The notation shown is for Primavera P6. Refer to the specific software guidelines with respect to the FEATURE OF WORK field requirements.
3.3.6.1 Workers Per Day (WRKP)
Assign Workers per Day for all field construction or direct work activities, if directed by the Contracting Officer. Workers per day is based on the average number of workers expected each day to perform a task for the duration of that activity.
3.3.6.2 Responsible Party Coding (RESP)
Assign responsibility code for all activities to the Prime Contractor, Subcontractor(s) or Government agency(ies) responsible for performing the activity.
a. Activities coded with a Government Responsibility code include, but are not limited to: Government approvals, Government design reviews, environmental permit approvals by State regulators, Government Furnished Property/Equipment (GFP) and Notice to Proceed (NTP) for phasing requirements.
b. Activities cannot have more than one Responsibility Code. Examples of acceptable activity code values are: DOR (for the designer of record);
ELEC (for the electrical subcontractor); MECH (for the mechanical subcontractor); and GOVT (for USACE).
3.3.6.3 Area of Work Coding (AREA)
Assign Work Area code to activities based upon the work area in which the activity occurs. Define work areas based on resource constraints or space constraints that would preclude a resource, such as a particular trade or craft work crew from working in more than one work area at a time due to restraints on resources or space. Examples of Work Area Coding include different areas within a floor of a building, different floors within a building, and different buildings within a complex of buildings.
SECTION 01 32 01.00 10 Page 7
Activities cannot have more than one Work Area Code.
Not all activities are required to be Work Area coded. A lack of Work Area coding indicates the activity is not resource or space constrained.
3.3.6.4 Modification Number (MODF)
Assign a Modification Number Code to any activity or sequence of activities added to the schedule as a result of a Contract Modification, when approved by Contracting Officer. Key all Code values to the Government's modification numbering system. An activity can have only one Modification Number Code.
3.3.6.5 Bid Item Coding (BIDI)
Assign a Bid Item Code to all activities using the Contract Line Item Schedule (CLIN) to which the activity belongs, even when an activity is not cost loaded. An activity can have only one BIDI Code.
3.3.6.6 Phase of Work Coding (PHAS)
Assign Phase of Work Code to all activities. Examples of phase of work are procurement phase and construction phase. Each activity can have only one Phase of Work code.
a. Code proposed fast track design and construction phases proposed to allow filtering and organizing the schedule by fast track design and construction packages.
b. If the contract specifies phasing with separately defined performance periods, identify a Phase Code to allow filtering and organizing the schedule accordingly.
3.3.6.7 Category of Work Coding (CATW)
Assign a Category of Work Code to all activities. Category of Work Codes include, but are not limited to construction submittal, procurement, fabrication, weather sensitive installation, non-weather sensitive installation, start-up, and testing activities. Each activity can have no more than one Category of Work Code.
3.3.6.8 Feature of Work Coding (FOW)
Assign a Feature of Work Code to appropriate activities based on the Definable Feature of Work to which the activity belongs based on the approved QC plan.
Definable Feature of Work is defined in Section 01 45 00.00 10 QUALITY CONTROL. An activity can have only one Feature of Work Code.
3.3.7 Contract Milestones and Constraints
Milestone activities are to be used for significant project events including, but not limited to, project phasing, project start and end activities, or interim completion dates. The use of artificial float constraints such as "zero free float" or "zero total float" are prohibited.
Mandatory constraints that ignore or effect network logic are prohibited.
SECTION 01 32 01.00 10 Page 8
No constrained dates are allowed in the schedule other than those specified herein. Submit additional constraints to the Contracting Officer for approval on a case by case basis.
3.3.7.1 Project Start Date Milestone and Constraint
The first activity in the project schedule must be a start milestone titled "NTP Acknowledged," which must have a "Start On" constraint date equal to the date that the NTP is acknowledged.
3.3.7.2 End Project Finish Milestone and Constraint
The last activity in the schedule must be a finish milestone titled "End Project."
Constrain the project schedule to the Contract Completion Date in such a way that if the schedule calculates an early finish, then the float calculation for "End Project" milestone reflects positive float on the longest path. If the project schedule calculates a late finish, then the "End Project" milestone float calculation reflects negative float on the longest path. The Government is under no obligation to accelerate Government activities to support a Contractor's early completion.
3.3.7.3 Interim Completion Dates and Constraints
Constrain contractually specified interim completion dates to show negative float when the calculated late finish date of the last activity in that phase is later than the specified interim completion date.
3.3.7.3.1 Start Phase
Use a start milestone as the first activity for a project phase. Call the start milestone "Start Phase X" where "X" refers to the phase of work.
3.3.7.3.2 End Phase
Use a finish milestone as the last activity for a project phase. Call the finish milestone "End Phase X" where "X" refers to the phase of work.
3.3.8 Calendars
Schedule activities on a Calendar to which the activity logically belongs. Develop calendars to accommodate any contract defined work period such as a 7-day calendar for Government Acceptance activities, concrete cure times, etc. Develop the default Calendar to match the physical work plan with non-work periods identified including weekends and holidays. Develop sSeasonal Calendar(s) and assign to seasonally affected activities as applicable.
If an activity is weather sensitive it should be assigned to a calendar showing non-work days on a monthly basis, with the non-work days selected at random across the weeks of the calendar, using the anticipated adverse weather delay work days provided in the Special Contract Clauses.