This is Amendment 0002 to solicitation W912EF25R0003 for the Mill Creek Diversion Dam Fish Ladder project, issued by the US Army Corps of Engineers Walla Walla District. The amendment updates the wage determination number from WA20240133 to WA20250133 dated 1/3/25 and revises three technical specification sections: Supplementary Requirements (01 11 01.0028), Governmental Safety Requirements (01 35 29.10 28), and Diversion and Care of Water (31 23 19.11 28).
Key revisions include changes to the Installation Supervisor requirements, which now require supervision of at least 2 fish ladder or fish passage systems with slide gates of similar size and complexity within the past 10 years. The amendment also modifies specifications related to Site Safety and Health Officer requirements, normal operation diversion system plans, IWW diversion system plans, downstream diversion system plans, and dewatering system plans. The changes focus on ensuring proper qualifications of key personnel and detailed documentation requirements for various water management systems during construction. All other terms and conditions of the original solicitation remain unchanged.
View the file
Other files
Show all 28
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print)
30-105-04EXCEPTION TO SF 30
APPROVED BY OIRM 11-84
STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA
FAR (48 CFR) 53.243
The purpose of this amendment is to provided an updated Wage Decision Number WA20250133 (formerly WA20240133) dated 1/3/25.
Also, included in this amendment revised techncial specification sections, 01 11 01.0028 SUPPLMENTARY REQUIREMENTS, 01 35 29.10 28
GOVERNMENTAL SAFETY REQUIRMENTS, AND 31 23 19.11 28 DIVERSION AND CARE OF WATER.
See summary of changes for further details.
All other terms and conditions remain unchanged.
1. CONTRACT ID CODE PAGE OF PAGES
1 10
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
16C. DATE SIGNED
BY 16-Jan-2025
16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR
(Signature of Contracting Officer)(Signature of person authorized to sign)
8. NAME AND ADDRESS OF CONTRACTOR (No., Street , County, State and Zip Code) X W912EF25R0003
X 9B. DATED (SEE ITEM 11)
23-Dec-2024
10B. DATED (SEE ITEM 13)
9A. AMENDMENT OF SOLICITATION NO.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.
Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:
(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN
REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE
CONTRACT ORDER NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
10A. MOD. OF CONTRACT/ORDER NO.
2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)
6. ISSUED BY
3. EFFECTIVE DATE
16-Jan-2025
CODE
USAED, WALLA WALLA - CONTRACTING DIV.
LEANNE WALLING
201 N. THIRD AVENUE
WALLA WALLA WA 99362-1876
W912EF 7. ADMINISTERED BY (If other than item 6)
4. REQUISITION/PURCHASE REQ. NO.
CODE
See Item 6
FACILITY CODECODE
EMAIL:TEL:
W912EF25R0003
SECTION SF 30 BLOCK 14 CONTINUATION PAGE
SUMMARY OF CHANGES
SECTION 00 21 00 - INSTRUCTIONS
The following have been added by full text:
Summary of changes for Amendment 0002 Mill Creek
Diversion Dam Fish Ladder Solicitation Number:
1. Updated General Decision Number from WA20240133 to WA20250133
2. Revised the following Specifications:
a. SECTION 01 11 01.00 28 “SUPPLEMENTARY REQUIREMENTS”
Revised Article 1.13 – “INSTALLATION SUPERVISOR”
b. SECTION 01 35 29.10 28 “GOVERNMENTAL SAFETY REQUIREMENTS” Revised Sub-Paragraph 1.6.1.1 – “Site Safety and Health Officer (SSHO)”
c. SECTION 31 23 19.11 28 “DIVERSION AND CARE OF WATER” Revised Paragraph 3.2.2 – “Normal Operation Diversion System Plan”
d. SECTION 31 23 19.11 28 “DIVERSION AND CARE OF WATER” Revised Paragraph 3.2.3 – “IWW Diversion System Plan”
e. SECTION 31 23 19.11 28 “DIVERSION AND CARE OF WATER”
Revised Paragraph 3.2.4 – “Downstream Diversion System Plan”
f. SECTION 31 23 19.11 28 “DIVERSION AND CARE OF WATER” Revised Paragraph 3.2.5 – “Dewatering System Plan”
See revised specifications for details.
3. Revised the following Drawings:
N/A
End Summary of Changes
SECTION 00 73 00 - SUPPLEMENTARY CONDITIONS
The following have been modified:
WAGE DETERMINATION
"General Decision Number: WA20250133 01/03/2025
Superseded General Decision Number: WA20240133
State: Washington
Construction Type: Heavy
County: Walla Walla County in Washington.
HEAVY CONSTRUCTION PROJECTS
Note: Contracts subject to the Davis-Bacon Act are generally required to pay at least the applicable minimum wage rate required under Executive Order 14026 or Executive Order 13658.
Please note that these Executive Orders apply to covered contracts entered into by the federal government that are subject to the Davis-Bacon Act itself, but do not apply to contracts subject only to the Davis-Bacon Related Acts, including those set forth at 29 CFR 5.1(a)(1).
|If the contract is entered |� Executive Order 14026 | |into on or after January 30, | generally applies to the | |2022, or the contract is | contract. | |renewed or extended (e.g., an |� The contractor must pay | |option is exercised) on or | all covered workers at | |after January 30, 2022: | least $17.75 per hour (or | | | the applicable wage rate | | | listed on this wage | | | determination, if it is | | | higher) for all hours | | | spent performing on the | | | contract in 2025. | |If the contract was awarded on|� Executive Order 13658 | |or between January 1, 2015 and| generally applies to the | |January 29, 2022, and the | contract. | |contract is not renewed or |� The contractor must pay all| |extended on or after January | covered workers at least | |30, 2022: | $13.30 per hour (or the | | | applicable wage rate listed| | | on this wage determination,| | | if it is higher) for all | | | hours performing on that | | | contract in 2025. |
The applicable Executive Order minimum wage rate will be adjusted annually. If this contract is covered by one of the Executive Orders and a classification considered necessary for performance of work on the contract does not appear on this wage determination, the contractor must still submit a conformance request.
Additional information on contractor requirements and worker protections under the Executive Orders is available at http://www.dol.gov/whd/govcontracts.
Modification Number Publication Date 0 01/03/2025
CARP0059-012 06/01/2023
Rates Fringes
CARPENTER........................$ 59.92 15.04
ELEC0077-002 02/01/2024
Rates Fringes
Line Construction:
LINE PERSON.................$ 64.17 23.58+1.5%
ELEC0077-003 02/01/2023
Rates Fringes
TREE TRIMMER: Ground Person......$ 22.60 16.37
TREE TRIMMER.....................$ 42.57 17.97
ELEC0077-005 02/01/2024
Rates Fringes
Line Construction:
EQUIPMENT OPERATOR..........$ 55.19 20.11+1.5%
ELEC0077-006 02/01/2023
Rates Fringes
Line Construction:
GROUND PERSON...............$ 37.53 17.74
ELEC0112-010 06/01/2022
Rates Fringes
ELECTRICIAN......................$ 51.75 24.18
ENGI0302-070 06/01/2023
Rates Fringes
OPERATOR:
Backhoe/Excavator/Trackhoe Under 15 metric tons........$ 52.83 25.57
ENGI0302-071 06/01/2023
Rates Fringes
OPERATOR: Bobcat/Skid
Steer/Skid Loader................$ 49.40 25.57
ENGI0302-075 06/01/2023
Rates Fringes
OPERATOR: Drill Drilling Machine............$ 56.64 25.57 Horizontal/directional drill locator...............$ 54.47 25.57 Horizontal/directional drill operator..............$ 55.09 25.57
ENGI0302-078 06/01/2023
Rates Fringes
OPERATOR: Grader/Blade..........$ 54.13 25.57
ENGI0302-080 06/01/2023
Rates Fringes
OPERATOR: Loader Overhead 6 yards but not including 8 yards...........$ 54.13 25.57 Overhead under 6 yards......$ 53.42 25.57
ENGI0302-082 06/01/2023
Rates Fringes
OPERATOR: Mechanic..............$ 54.93 25.57
ENGI0302-083 06/01/2023
Rates Fringes
OPERATOR: Oiler Drill Oilers: auger type, truck or crane mount........$ 54.47 25.57 Truck Crane Oiler/Driver:
100 tons and over...........$ 55.09 25.57
ENGI0302-084 06/01/2023
Rates Fringes
OPERATOR: Paver (Asphalt, Aggregate, and Concrete).........$ 54.13 25.57
ENGI0302-086 06/01/2023
Rates Fringes
OPERATOR: Roller Other than plant mix........$ 49.40 25.57 Plant mix or multi-lift materials...................$ 52.83 25.57
ENGI0302-087 06/01/2023
OPERATOR: Scraper Self propelled under 45 yards.......................$ 53.42 25.57
ENGI0701-046 01/01/2024
Rates Fringes
OPERATOR: Concrete Pump.........$ 49.03 16.90
IRON0014-010 01/01/2024
Rates Fringes
IRONWORKER.......................$ 38.91 32.27
LABO0238-040 06/01/2023
Rates Fringes
TRAFFIC CONTROL: Flagger.......$ 30.88 15.70
LABO0242-010 06/01/2023
Rates Fringes
LABORER: Nozzle Person...........$ 47.95 14.40
LABO0348-010 06/01/2023
Rates Fringes
LABORER: Pipelayer..............$ 34.33 15.70
PAIN0300-002 07/01/2023
Rates Fringes
PAINTER..........................$ 37.80 13.63
PLAS0072-005 06/01/2023
Rates Fringes
CEMENT MASON/CONCRETE FINISHER...$ 38.05 16.89
TEAM0313-001 06/01/2024
Rates Fringes
TRUCK DRIVER: Asphalt Mix.......$ 52.88 26.52
UAVG-WA-0019 03/01/2024
Rates Fringes
OPERATOR: Crane.................$ 54.41 25.11
SUWA2018-033 03/01/2024
GRADE CHECKER....................$ 31.40 14.10
LABORER: Asphalt, Includes Raker, Shoveler, Spreader and Distributor......................$ 36.96 8.56
LABORER: Common or General......$ 37.83 0.00
LABORER: Concrete Saw Chain.....$ 36.24 10.89
LABORER: Hod Carrier............$ 35.06 10.94
LABORER: Mason Tender - Cement/Concrete..................$ 27.51 2.96
LABORER: Fence Erector...........$ 30.21 0.00
OPERATOR: Bulldozer.............$ 28.14 15.76
OPERATOR: Forklift..............$ 45.93 19.20
TRAFFIC CONTROL:
Laborer-Cones/ Barricades/Barrels - Setter/Mover/Sweeper.............$ 30.61 10.89
TRUCK DRIVER: Dump Truck........$ 27.94 17.30
TRUCK DRIVER: Water Truck.......$ 31.62 16.84
WELDERS - Receive rate prescribed for craft performing operation to which welding is incidental.
Note: Executive Order (EO) 13706, Establishing Paid Sick Leave for Federal Contractors applies to all contracts subject to the Davis-Bacon Act for which the contract is awarded (and any solicitation was issued) on or after January 1, 2017. If this contract is covered by the EO, the contractor must provide employees with 1 hour of paid sick leave for every 30 hours they work, up to 56 hours of paid sick leave each year.
Employees must be permitted to use paid sick leave for their own illness, injury or other health-related needs, including preventive care; to assist a family member (or person who is like family to the employee) who is ill, injured, or has other health-related needs, including preventive care; or for reasons resulting from, or to assist a family member (or person who is like family to the employee) who is a victim of, domestic violence, sexual assault, or stalking. Additional information on contractor requirements and worker protections under the EO is available at https://www.dol.gov/agencies/whd/government-contracts.
Unlisted classifications needed for work not included within the scope of the classifications listed may be added after award only as provided in the labor standards contract clauses (29CFR 5.5 (a) (1) (iii)).
The body of each wage determination lists the classifications and wage rates that have been found to be prevailing for the type(s) of construction and geographic area covered by the wage determination. The classifications are listed in alphabetical order under rate identifiers indicating whether the particular rate is a union rate (current union negotiated rate), a survey rate, a weighted union average rate, a state adopted rate, or a supplemental classification rate.
Union Rate Identifiers
A four-letter identifier beginning with characters other than ""SU"", ""UAVG"", ?SA?, or ?SC? denotes that a union rate was prevailing for that classification in the survey. Example:
PLUM0198-005 07/01/2024. PLUM is an identifier of the union whose collectively bargained rate prevailed in the survey for this classification, which in this example would be Plumbers.
0198 indicates the local union number or district council number where applicable, i.e., Plumbers Local 0198. The next number, 005 in the example, is an internal number used in processing the wage determination. The date, 07/01/2024 in the example, is the effective date of the most current negotiated rate.
Union prevailing wage rates are updated to reflect all changes over time that are reported to WHD in the rates in the collective bargaining agreement (CBA) governing the classification.
Union Average Rate Identifiers
The UAVG identifier indicates that no single rate prevailed for those classifications, but that 100% of the data reported for the classifications reflected union rates. EXAMPLE:
UAVG-OH-0010 01/01/2024. UAVG indicates that the rate is a weighted union average rate. OH indicates the State of Ohio.
The next number, 0010 in the example, is an internal number used in producing the wage determination. The date, 01/01/2024 in the example, indicates the date the wage determination was updated to reflect the most current union average rate.
A UAVG rate will be updated once a year, usually in January, to reflect a weighted average of the current rates in the collective bargaining agreements on which the rate is based.
Survey Rate Identifiers
The ""SU"" identifier indicates that either a single non-union rate prevailed (as defined in 29 CFR 1.2) for this classification in the survey or that the rate was derived by computing a weighted average rate based on all the rates reported in the survey for that classification. As a weighted average rate includes all rates reported in the survey, it may include both union and non-union rates. Example: SUFL2022-007 6/27/2024. SU indicates the rate is a single non-union prevailing rate or a weighted average of survey data for that classification. FL indicates the State of Florida. 2022 is the year of the survey on which these classifications and rates are based. The next number, 007 in the example, is an internal number used in producing the wage determination. The date, 6/27/2024 in the example, indicates the survey completion date for the classifications and rates under that identifier.
?SU? wage rates typically remain in effect until a new survey is conducted. However, the Wage and Hour Division (WHD) has the discretion to update such rates under 29 CFR 1.6(c)(1).
State Adopted Rate Identifiers
The ""SA"" identifier indicates that the classifications and prevailing wage rates set by a state (or local) government were adopted under 29 C.F.R 1.3(g)-(h). Example: SAME2023-007 01/03/2024. SA reflects that the rates are state adopted. ME refers to the State of Maine. 2023 is the year during which the state completed the survey on which the listed classifications and rates are based. The next number, 007 in the example, is an internal number used in producing the wage determination.
The date, 01/03/2024 in the example, reflects the date on which the classifications and rates under the ?SA? identifier took effect under state law in the state from which the rates were adopted.
WAGE DETERMINATION APPEALS PROCESS
1) Has there been an initial decision in the matter? This can be:
a) a survey underlying a wage determination
b) an existing published wage determination
c) an initial WHD letter setting forth a position on a wage determination matter
d) an initial conformance (additional classification and rate) determination
On survey related matters, initial contact, including requests for summaries of surveys, should be directed to the WHD Branch of Wage Surveys. Requests can be submitted via email to davisbaconinfo@dol.gov or by mail to:
Branch of Wage Surveys Wage and Hour Division U.S. Department of Labor 200 Constitution Avenue, N.W.
Washington, DC 20210
Regarding any other wage determination matter such as conformance decisions, requests for initial decisions should be directed to the WHD Branch of Construction Wage Determinations.
Requests can be submitted via email to BCWD-Office@dol.gov or by mail to:
Branch of Construction Wage Determinations Wage and Hour Division U.S. Department of Labor 200 Constitution Avenue, N.W.
Washington, DC 20210
2) If an initial decision has been issued, then any interested party (those affected by the action) that disagrees with the decision can request review and reconsideration from the Wage and Hour Administrator (See 29 CFR Part 1.8 and 29 CFR Part 7).
Requests for review and reconsideration can be submitted via email to dba.reconsideration@dol.gov or by mail to:
Wage and Hour Administrator U.S. Department of Labor 200 Constitution Avenue, N.W.
Washington, DC 20210
The request should be accompanied by a full statement of the interested party's position and any information (wage payment data, project description, area practice material, etc.) that the requestor considers relevant to the issue.
3) If the decision of the Administrator is not favorable, an interested party may appeal directly to the Administrative Review Board (formerly the Wage Appeals Board). Write to:
Administrative Review Board U.S. Department of Labor 200 Constitution Avenue, N.W.
Washington, DC 20210.
END OF GENERAL DECISION"
(End of Summary of Changes)
Mill Creek Diversion Dam Fish Ladder W912EF25R0003
MCL475720DDFL
PROJECT TABLE OF CONTENTS
DIVISION 01 - GENERAL REQUIREMENTS
01 00 00.00 28 GENERAL REQUIREMENTS
01 11 01.00 28 SUPPLEMENTARY REQUIREMENTS
01 14 00.10 28 PROJECT SITE RESTRICTIONS
01 14 00.30 28 SURFACE FINISH REQUIREMENTS - BIOLOGICAL
01 14 00.90 28 INTEGRATING ANTITERRORISM (AT) AND OPERATIONS SECURITY
(OPSEC)
01 22 00.00 28 MEASUREMENT AND PAYMENT
01 32 01.00 28 PROJECT SCHEDULE
01 33 00 SUBMITTAL PROCEDURES
01 35 29.10 28 GOVERNMENTAL SAFETY REQUIREMENTS
01 42 00 SOURCES FOR REFERENCE PUBLICATIONS
01 45 01.00 28 RESIDENT MANAGEMENT SYSTEM CONTRACTOR MODE (RMS CM)
01 45 04.00 28 CONTRACTOR QUALITY CONTROL
01 51 00.00 28 TEMPORARY UTILITIES
01 54 19.10 28 MOBILE CRANE REQUIREMENTS
01 55 10.00 28 CONTRACTOR WORK, ACCESS AND STORAGE AREAS
01 57 20.00 28 ENVIRONMENTAL PROTECTION
01 71 23.01 28 CONTRACTOR SURVEYS AND REMOTE SENSING DATA COLLECTION
01 78 00.00 28 CLOSEOUT SUBMITTALS
01 78 23.00 28 OPERATION AND MAINTENANCE DATA
01 91 00.00 28 SYSTEMS TESTING AND COMMISSIONING
DIVISION 02 - EXISTING CONDITIONS
02 24 10.30 28 TRAPPED FISH CAPTURE AND RELEASE
02 24 20.00 28 WATER QUALITY MONITORING
02 32 13.00 28 SUBSURFACE DRILLING AND SAMPLING
02 41 00.00 28 DEMOLITION
DIVISION 03 - CONCRETE
03 30 00.00 28 CAST-IN-PLACE CONCRETE
03 60 00.00 28 CONCRETE CORING, DRILLING, AND CUTTING
DIVISION 05 - METALS
05 05 20.00 28 POST-INSTALLED CONCRETE ANCHORS
05 05 23.00 28 STRUCTURAL STEEL, METALWORK FABRICATION, AND WELDING
DIVISION 06 - WOOD, PLASTICS, AND COMPOSITES
06 82 14.00 28 FIBERGLASS REINFORCED PLASTIC (FRP) WALKWAYS
DIVISION 14 - CONVEYING EQUIPMENT
14 84 23.20 28 GATE HOISTING EQUIPMENT
DIVISION 25 - INTEGRATED AUTOMATION
25 05 11.00 28 CYBERSECURITY
25 31 00.01 28 ELECTRICAL CONTROL AND RELAY PANEL
DIVISION 26 - ELECTRICAL
26 05 00.00 28 GENERAL ELECTRICAL WORK
PROJECT TABLE OF CONTENTS Page 1 g4ecctgh Line Amendment-0002 - Section 01 11 01.00 28 g4ecctgh Line Amendment-0002 - Section 01 35 29.10 28
26 05 19.00 28 INSULATED WIRE AND CABLE
26 05 26.11 28 GROUNDING
26 05 33.11 28 RACEWAYS AND BOXES FOR ELECTRICAL SYSTEMS
26 05 71.11 28 LOW VOLTAGE OVERCURRENT PROTECTIVE DEVICES
26 20 00.00 28 INTERIOR DISTRIBUTION SYSTEM
26 24 16.11 28 PANELBOARDS
26 56 00.00 28 EXTERIOR LIGHTING
DIVISION 28 - ELECTRONIC SAFETY AND SECURITY
28 05 26.11 28 GROUNDING AND BONDING FOR ELECTRONIC SAFETY AND SECURITY
DIVISION 31 - EARTHWORK
31 00 00.00 28 EARTHWORK
31 11 00.00 28 CLEARING AND GRUBBING
31 23 19.11 28 DIVERSION AND CARE OF WATER
DIVISION 32 - EXTERIOR IMPROVEMENTS
32 12 16.11 28 ASPHALT PAVING
32 17 23.00 28 PAVEMENT MARKINGS
32 31 13.00 28 CHAIN LINK FENCES AND GATES
32 84 23.00 28 UNDERGROUND SPRINKLERS
32 92 23.00 28 SODDING
32 93 00.00 28 EXTERIOR PLANTS
DIVISION 33 - UTILITIES
33 51 43.00 28 INSTRUMENTATION AND PERFORMANCE MONITORING OF STRUCTURES
33 71 02.00 28 UNDERGROUND ELECTRICAL DISTRIBUTION
DIVISION 35 - WATERWAY AND MARINE CONSTRUCTION
35 20 16.00 28 SLIDE GATES AND ACTUATORS
35 20 20.00 28 ELECTRICAL EQUIPMENT FOR GATE HOIST
DIVISION 40 - PROCESS INTERCONNECTIONS
40 92 13.10 28 MOTORIZED GATE AND VALVE ACTUATORS
40 94 43.01 28 PROCESS CONTROLLERS - PROGRAMMABLE LOGIC CONTROLLERS (PLC)
-- End of Project Table of Contents --
PROJECT TABLE OF CONTENTS Page 2 g4ecctgh
Amendment-0002 - Section 31 23 19.11 28
SECTION TABLE OF CONTENTS
DIVISION 01 - GENERAL REQUIREMENTS
SECTION 01 11 01.00 28
SUPPLEMENTARY REQUIREMENTS
PART 1 GENERAL
1.1 REFERENCES
1.2 SUBMITTALS
1.3 DEFINITIONS
1.4 DOCUMENT SUBMITTALS
1.5 FIELD VERIFICATION OF SITE CONDITIONS
1.6 PRE-CONSTRUCTION ON-SITE INSPECTION
1.7 SUPPLEMENTAL DRAWINGS
1.8 REGULAR CLEANUP AND DEBRIS DISPOSAL
1.9 EQUIPMENT LIST
1.10 TESTING OF EQUIPMENT
1.11 DISPOSITION OF REMOVED MATERIALS AND EQUIPMENT
1.12 PROTECTION AND RESTORATION OF EXISTING FACILITIES
1.13 INSTALLATION SUPERVISOR
1.14 TRAINING
1.14.1 Digital Recording
1.15 PROJECT OPERATORS' TRAINING
1.16 PROJECT TECHNICAL SUPPORT
1.17 PROJECT SUPERINTENDENT
1.18 KEY PERSONNEL SUBSTITUTION
1.19 POST AWARD MEETINGS
1.19.1 Pre-Work Meeting
1.19.2 Pre-Construction Meeting
1.19.2.1 Minutes
1.19.2.2 Demobilizing And Remobilizing
1.19.3 RMS Orientation Meeting
1.20 WEEKLY PRODUCTION MEETINGS
1.20.1 Production Briefings
1.20.2 Construction Progress Photos
1.20.3 Minutes
1.21 ADDITIONAL MEETINGS
1.22 PARTNERING
1.22.1 General
1.22.2 Partnering Meetings
1.23 RED ZONE MEETING
PART 2 PRODUCTS (Not Applicable)
PART 3 EXECUTION (Not Applicable)
ATTACHMENTS:
Weekly Meeting Agenda
SECTION 01 11 01.00 28 Page 1 g4ecctgh
Amendment-0002 - Section 01 11 01.00 28 - Article 1.13
Look-Ahead
-- End of Section Table of Contents --
SECTION 01 11 01.00 28 Page 2
SECTION 01 11 01.00 28
SUPPLEMENTARY REQUIREMENTS
PART 1 GENERAL
The work covered by this section of the specifications consists of work common to more than one section of these TECHNICAL SPECIFICATIONS.
1.1 REFERENCES
The publications listed below form a part of this specification to the extent referenced. The publications are referred to in the text by the basic designation only.
U.S. ARMY CORPS OF ENGINEERS (USACE)
EM 385-1-1 Safety and Occupational Health Requirements
The Contractor is responsible for complying with the current edition and all changes posted on the web as of the effective date of this solicitation.
1.2 SUBMITTALS
Government approval is required for submittals with a "G" designation;
submittals having an "I" designation are for information only.
Designation following the "G" or "I" designation identifies the office that will review the submittal for the Government. Submit in accordance with SECTION 01 33 00 SUBMITTAL PROCEDURES:
SD-01 Preconstruction Submittals
Equipment List; I, C
Pre-Construction On-Site Inspection report; I, C
Project Superintendent; I, C
SD-07 Certificates
Installation Supervisor; G, C
Key Personnel Substitution; G, C
SD-11 Closeout Submittals
Training Manuals; G, C
1.3 DEFINITIONS
a. Qualified Person.
As defined in EM 385-1-1; "DEFINITIONS", unless otherwise specified.
SECTION 01 11 01.00 28 Page 3
1.4 DOCUMENT SUBMITTALS
In addition to other specified submittal requirements, a copy of all documents submitted as part of work on this contract, must be e-mailed to the Contracting Officer and submitted in Resident Management System Contractor Mode (RMS CM). Include project contract number, title, and e-mail topic in all e-mail subject lines.
1.5 FIELD VERIFICATION OF SITE CONDITIONS
Field verify all elevations, dimensions, and coordinates of existing features indicated on the contract drawings that affect new construction.
Any variations must be updated as per SECTION 01 78 00.00 28, CLOSEOUT SUBMITTALS, paragraphs WORKING AS-BUILT DRAWINGS.
1.6 PRE-CONSTRUCTION ON-SITE INSPECTION
Prepare a Pre-Construction On-Site Inspection report of existing conditions, prior to start of on-site work, with the Contracting Officer.
Document existing site conditions prior to Construction by digital photographs, and/or videos along with descriptive narrative report to the Contracting Officer within five (5) days after completion.
1.7 SUPPLEMENTAL DRAWINGS
a) A “Supplemental Drawings” packet is provided as part of this contract for information only and is not part of Contract work. These drawings are not available in CAD. These drawings depict the best estimate of existing components and equipment. The Government does not guarantee the accuracy of Supplemental Drawings.
b) Contractor shall verify accuracy of these drawings prior to use. Any errors or deficiencies arising from use of these drawings shall be the responsibility of the Contractor and corrected at no additional cost to the Government.
1.8 REGULAR CLEANUP AND DEBRIS DISPOSAL
With the exception of materials specifically indicated or specified to be salvaged for reuse in construction, or turned over to the Government, all wastes and demolished materials becomes the property of the Contractor and must be removed from the job site daily in accordance with Federal, State, and local regulations. The Contractor shall furnish waste containers. All small waste containers provided by the contractor must be emptied daily, large bin containers must be emptied when full or once a week.
1.9 EQUIPMENT LIST
Furnish a complete list of all equipment to be used on the Project 30 days prior to commencement of on-site work. Submit a revised list in the event of change of equipment. Lists shall include rented equipment as well as lease-purchase or sale-leaseback equipment. The initial list and the revised lists shall indicate dates equipment is assigned to or removed from the Project and adequate identification or description of each item of equipment including manufacturer's name (abbreviated), model number, manufacturer's serial number, year of manufacture, and Contractor's assigned serial or record number.
SECTION 01 11 01.00 28 Page 4
1.10 TESTING OF EQUIPMENT
Before any machinery or mechanized equipment is put to use on the job, it must be inspected and tested by a qualified person and determined to be in safe operating condition. Cranes or derricks must be tested by the Contractor or a qualified testing agency in accordance with EM 385-1-1.
Equipment must be large enough to safely handle proposed picks or tasks without exceeding the crane rating established by these tests.
1.11 DISPOSITION OF REMOVED MATERIALS AND EQUIPMENT
Unless otherwise specified in other sections of the specifications, all existing equipment removed and not reinstalled becomes the property of the Contractor, removed from the Project site, and disposed of in a legal manner. Materials that cannot be removed daily may be temporarily stored on-site at an approved area. Salvaged materials shall not be sold on the project site.
1.12 PROTECTION AND RESTORATION OF EXISTING FACILITIES
Reference FAR 52.236-9 Protection of Existing Vegetation, Structures, Equipment, Utilities, and Improvements (Apr 1984).
1.13 INSTALLATION SUPERVISOR
A representative of the Contractor who is technically qualified to supervise the installation, preparation, and testing of radialslide gates and fish ladder or fish passage systems. The Installation Supervisor, or approved substitute, must be available at all times and is experienced in the installation of the radialslide gates and fish ladder or fish passage systems. Approved substitute must have the same qualifications as the Installation Supervisor. The representative must report immediately in writing to the Contracting Officer any work not in accordance with the manufacturer's recommendation or any special conditions which may result in an unsatisfactory job. The representative must have supervised the construction of at least a2 fish ladder or fish passage systems with slide gates of at least 2 similar projectsof similar size and complexity to this contract, or larger, within the past 10 years. Installation supervisor's, and potential substitute's resumes must be submitted to the Contracting Officer.
1.14 TRAINING
Provide the services of authorized start-up engineers (Manufacturer's Representatives) as necessary to provide training in programming, operation and maintenance of radial gate controls. Provide two, eight-hour class sessions; one class for operations and maintenance personnel and one for system support engineers. Each class session shall include approximately 6 employees. The Government will provide for the training location. Submit training manuals and documentation for approval 30 days prior to scheduled classes and furnish sufficient training materials at the training classes for all students plus a minimum of three (3) copies for project files. Where audio/visual materials are used in training classes, three (3) copies of such materials must be furnished to the Project for use in future training. It is the Contractor's responsibility to coordinate the training sessions with the Contracting Officer's Representative to ensure minimum conflicts with ongoing Project work.
SECTION 01 11 01.00 28 Page 5 g4ecctgh
Amendment-0002 - Section 01 11 01.00 28 - Article 1.13 - INSTALLATION SUPERVISOR
1.14.1 Digital Recording
Film the first training session of each equipment with independent function. Filmed sessions must cover all new equipment installed.
Filming is not required for equipment with redundant functions; i.e. only one SU board is necessary. Two (2) copies of the filmed sessions shall be provided to the Government on DVD. DVD's shall have professional labels on both the DVD case and on the DVD. Labels shall include the equipment covered on that training disc. Recordings shall use at a minimum MPEG-2 format with a resolution of no less than 720 X 480 pixels at 29.92 frames per second. Different recording formats may be proposed by the Contractor but require approval before the Government will accept them.
1.15 PROJECT OPERATORS' TRAINING
Provide the services of one or more authorized individuals for Project Operators' training. Contractor personnel must be experienced in the operational requirements of all newly installed equipment, and control features. Provide a recommended maintenance job plan with step by step training to complete the job plan for each type of equipment. Contractor personnel must be present at the project and available for assistance for three (3) ten hour work shifts immediately following Government acceptance of newly installed features. Required work shifts must be coordinated with the Contracting Officer.
1.16 PROJECT TECHNICAL SUPPORT
a. Provide 20 hours of project technical support after Government acceptance of the completed project. One or more Contractor personnel experienced in the operational requirements of all newly installed equipment, and control features must be available for Technical Support during normal Government Work Schedule hours. See paragraph "Government's Work Schedule" in SECTION 01 14 00.10 28.
b. Support includes site visits by Contractor personnel. Contractor personnel must be available at the project within 48 hours, or the next normal Government Work Schedule day following notification by the Government - whichever is later. Technical support must be available for 60 days following Government acceptance of the newly installed Diversion Dam Fish Ladder, or until final Operation and Maintenance Manuals and Parts Catalogs have been approved and received by the Government - whichever is later. See SECTIONS 01 78 00.00 28 CLOSEOUT.
c. Technical Support shall include all contractor Supervision, Safety and QC personnel required to maintain proper control of work in accordance with contract requirements.
1.17 PROJECT SUPERINTENDENT
The Contractor's Project Superintendent must be on the worksite during performance of work on this contract. The Project Superintendent is required on the worksite, at all times work is being performed, until work on this contract is completed and accepted. Assign a competent superintendent as per FAR Clause 52.236-6 "Superintendence by the Contractor". Submit Superintendent name and contact information prior to start of on-site construction.
SECTION 01 11 01.00 28 Page 6
1.18 KEY PERSONNEL SUBSTITUTION
If the Contractor plans on replacing any Key personnel (Project Superintendent, Installation Supervisor, CQC System Manager, or CQC staff Members) they must have the approval of the Contracting Officer.
Personnel shall possess the qualifications that meet or exceed those stated in this contract for the position of the individual they are replacing. Submit qualifications of new personnel at least 15 calendar days in advance of date of replacement.
1.19 POST AWARD MEETINGS
1.19.1 Pre-Work Meeting
Within thirty (30) calendar days after receipt of Notice to Proceed, attend a Pre-Work Meeting. Senior Level members of the Contractor's staff involved with this contract shall participate in this meeting to discuss the overall contract requirements. The Government will lead this meeting and take the meeting minutes.
1.19.2 Pre-Construction Meeting
Coordinate with the Contracting Officer and establish the date of the Pre-Construction Meeting. The meeting will be held at the Project site at least one (1) week prior to mobilizing to the job site. The Contractor shall lead the Pre-Construction Meeting discussing the Contractor's plan on executing the work at the project site, schedule, required clearances and timeframe for them, and plan for implementing safety and quality control. The Government will have key members from the Project staff to discuss environmental and clearance issues. Key members of the contractor staff shall attend this meeting including the Quality Control (QC) System Manager, Site Safety and Health Officer (SSHO) and any other members determined by the Government to be required.
1.19.2.1 Minutes
Contractor is responsible for taking the meeting minutes and shall send them electronically within 48 hours of the meeting to the Government's Project Engineer, Quality Assurance Representative, and Resident Engineer. Include project name and meeting topic in e-mail subject line.
1.19.2.2 Demobilizing And Remobilizing
Anytime the Contractor demobilizes from the site and remobilizes at a later date, another Pre-Construction Meeting must be held following the requirements listed above.
1.19.3 RMS Orientation Meeting
a. Upon the Contractor's request, an RMS (Resident Management System) Orientation Meeting will be held within fifteen (15) calendar days after receipt of Notice to Proceed. See SECTION 01 45 01.00 28 RESIDENT MANAGEMENT SYSTEM CONTRACTOR MODE (RMS CM) for additional information. The Orientation Meeting will be held at NWW District Headquarters, and may occur in conjunction with, but not at the same time as, the Pre-Work Meeting. The Orientation Meeting can also occur via video conference. Coordinate meeting date and time with the Contracting Officer a minimum of 7 calendar days prior to the meeting.
SECTION 01 11 01.00 28 Page 7
b. At a minimum, the Contractor's RMS-CM Administrator and QC system manager must attend the RMS Orientation meeting. A Government Representative will lead the orientation. Anticipate the following at the meeting:
1. Allow for a maximum 4 hour duration.
2. Cover the following topics, at a minimum, in RMS Contractor Mode (CM):
i. Contractor use of RMS (CM) system.
ii. Contractor Data.
iii. Quality Control Reports.
iv. Submittals.
v. RFIs.
vi. Payment.
3. Receive a follow-up handout/guide for reference on the above items.
c. Contractor employees shall bring a computer with Wi-Fi capability (to gain access to the Internet), with RMS pre-loaded.
d. The RMS Orientation Meeting is required for Contractors with no prior RMS experience. The RMS Orientation Meeting, is optional, but may be requested, for all other Contractors.
e. The purpose of the RMS Orientation Meeting is to facilitate Contractor's use of RMS (CM). It does not relieve the Contractor of the requirement to use RMS (CM) in accordance with the Contract. See
SECTION 01 45 01.00 28 RESIDENT MANAGEMENT SYSTEM CONTRACTOR MODE
(RMS CM), paragraph RMS SOFTWARE for information related to required download and installation deadlines.
1.20 WEEKLY PRODUCTION MEETINGS
1.20.1 Production Briefings
During all onsite construction work, hold a weekly production meeting to brief the Government on the status of the project.
a. Use the attached "Weekly Meeting Agenda" and discuss all elements of this agenda.
b. Provide a three (3) week 'look ahead'. The "Look-Ahead" must be generated in P6 and then copied into Excel for more detail (see look-ahead examples at the end of this section).
1. Describe all planned construction activities, on-site and off-site over the next three (3) weeks.
2. ENSURE these activities align to the overall Construction Schedule submitted under SECTION 01 32 01.00 28 PROJECT SCHEDULE.
SECTION 01 11 01.00 28 Page 8
3. RECORD any changes to the Project Schedule AND INCLUDE IN the next scheduled update.
c. Key members of the Contractor's staff including the Quality Control System Manager and the SITE SAFETY AND HEALTH OFFICER shall attend.
d. The Quality Control System Manager shall discuss all QC aspects outlined in SECTION 01 45 04.00 28 CONTRACTOR QUALITY CONTROL.
e. The Government reserves the right to require any person from the Contractor's staff such as the Project Manager, Engineer, Scheduler or Key Subcontractor Personnel to attend the meeting.
1.20.2 Construction Progress Photos
a. During on site construction activities record construction progress using weekly progress photographs. Submit digital photographs weekly for use at the WEEKLY PRODUCTION MEETING. Photographs provided are for unrestricted use by the Government.
1. Submit photos at the end of each work week.
2. Furnish digital photographs, Utilize JPEG file format for all photograph and image files.
3. Provide full-color photos with photo resolution of not less than 4 megapixels and not more than 12 megapixels. Photos shall show the sequence and progress of work.
4. Take a minimum of 20 digital photographs each week throughout the entire project.
b. Ensure that the photographs are digitally dated. A log must be furnished for each photograph that records the following information:
1. Photograph number (the specific format should be tied to the filename of the digital photograph).
2. Date the photograph was taken.
3. A brief description of the location, what the photograph depicts, and the orientation of the view.
1.20.3 Minutes
The Contractor is responsible for taking the meeting minutes and shall send them electronically within 24 hours of the meeting to the Government's Project Engineer, Quality Assurance Representative, and Resident Engineer. Include project name and meeting topic in e-mail subject line.
1.21 ADDITIONAL MEETINGS
Record the minutes of all meetings, including all conference calls, that occur between the Contractor and Government. Send minutes electronically within 24 hours of the meeting to the Contracting Officer for concurrence.
E-mail subject line shall include project name and meeting topic.
SECTION 01 11 01.00 28 Page 9
1.22 PARTNERING
1.22.1 General
The Government intends to encourage the foundation of a cohesive partnership with the Contractor and its subcontractors by informally partnering this contract. This partnership will be structured to draw on the strengths of each organization to identify and achieve reciprocal goals. The objectives are effective and efficient contract performance with the intent to achieve a safe completion of the work - within budget, on schedule, and in accordance with plans and specifications. This partnership would be bilateral in makeup and participation will be totally voluntary. If Partnering is pursued, meetings would be held as identified in the following paragraph.
1.22.2 Partnering Meetings
Within 30 calendar days of receipt of Notice to Proceed, the initial partnering meeting will be scheduled if the meeting is requested by the Contractor. The Contractor's key personnel will attend a face-to-face partnering meeting (typically one day in duration) together with key Government personnel, to discuss project goals and communication.
Follow-up meetings will be held periodically, as required, throughout the duration of the contract, as agreed to by the Contractor and the Government. The Government will facilitate the meeting.
1.23 RED ZONE MEETING
Within one (1) month of completing the project or when the project is 80 percent completed, the Contractor shall set up and lead a Red Zone meeting. The Contractor shall contact the Contracting Officer to Schedule this meeting. The Government’s representative will include the Contracting Officer, key personnel from the Project, Project Engineer, Quality Assurance Representative, and Resident Engineer. The key people from the Contractor must be, at a minimum, the Project Superintendent, Quality Control System Manager, Scheduler, key subcontractors personnel, and Project Manager.
The purpose of this meeting is to develop an overall schedule for all activities required by both the Government and Contractor and to complete the project through commissioning and final acceptance. The Government will come prepared with all their activities, key dates, and durations for all work required by the Government to complete the project. The Contractor shall provide the same information for all of their activities. The Contractor’s scheduler shall input all of this information into the Contractor’s project schedule during the meeting.
This schedule must be updated weekly, or as needed, based on the information from the weekly production meetings for both the Government and Contractor activities.
PART 2 PRODUCTS (Not Applicable)
PART 3 EXECUTION (Not Applicable)
-- End of Section --
SECTION 01 11 01.00 28 Page 10
SECTION TABLE OF CONTENTS
DIVISION 01 - GENERAL REQUIREMENTS
SECTION 01 35 29.10 28
GOVERNMENTAL SAFETY REQUIREMENTS
PART 1 GENERAL
1.1 REFERENCES
1.2 SUBMITTALS
1.3 DEFINITIONS
1.3.1 Competent Person (CP)
1.3.2 High Hazard Work Group Activities
1.3.3 High Visibility Accident
1.3.4 Load Handling Equipment (LHE)
1.3.5 Medical Treatment
1.3.6 Near Miss
1.3.7 Operating Envelope
1.3.8 Qualified Person (QP)
1.3.9 Recordable Injuries or Illnesses
1.3.10 USACE Property and Equipment
1.3.11 Load Handling Equipment (LHE) Accident or Load Handling
Equipment Mishap
1.4 MONTHLY EXPOSURE REPORTS
1.5 REGULATORY REQUIREMENTS
1.6 SITE QUALIFICATIONS, DUTIES, AND MEETINGS
1.6.1 Personnel Qualifications
1.6.1.1 Site Safety and Health Officer (SSHO)
1.6.1.2 Competent Person Qualifications
1.6.1.3 Qualified Trainer Requirements
1.6.2 Meetings
1.6.2.1 Preconstruction Meeting
1.6.2.2 Safety Meetings
1.7 ACCIDENT PREVENTION PLAN (APP)
1.7.1 Plans
1.7.1.1 Confined Space Entry Plan
1.7.1.2 Standard Lift Plan (SLP)
1.7.1.3 Critical Lift Plan- Crane or Load Handling Equipment
1.7.1.4 Fall Protection and Prevention (FP&P) Plan
1.7.1.5 Rescue and Evacuation Plan
1.7.1.6 Hazardous Energy Control Program (HECP)
1.7.1.7 Excavation Plan
1.7.1.8 Site Demolition Plan
1.8 ACTIVITY HAZARD ANALYSIS (AHA)
1.8.1 AHA Signature Log
1.9 LOCKOUT/TAGOUT (LOTO)-SAFE CLEARANCE OR HAZARDOUS ENERGY CONTROL
PROGRAM (HECP) PROCEDURES
1.9.1 Safe Clearance Training
1.10 DISPLAY OF SAFETY INFORMATION
1.10.1 Safety Bulletin Board
1.10.2 Safety and Occupational Health (SOH) Deficiency Tracking
System
SECTION 01 35 29.10 28 Page 1 g4ecctgh
Amendment-0002 - Section 01 35 29.10 28 - Sub-Paragraph 1.6.1.1
1.11 SITE SAFETY REFERENCE MATERIALS
1.12 EMERGENCY MEDICAL TREATMENT
1.13 NOTIFICATIONS and REPORTS
1.13.1 Mishap Notification
1.13.2 Accident Reports
1.13.3 LHE Inspection Reports
1.13.4 Certificate of Compliance and Pre-lift Plan/Checklist for LHE and Rigging
1.14 HOT WORK
1.15 RADIATION SAFETY REQUIREMENTS
1.16 CONFINED SPACE ENTRY REQUIREMENTS
1.16.1 Entry Procedures
1.16.2 Forced Air Ventilation
1.16.3 Sewer Wet Wells
1.16.4 Rescue Procedures and Coordination with Local Emergency
Responders
1.17 SEVERE STORM PLAN
PART 2 PRODUCTS (Not Applicable)
PART 3 EXECUTION
3.1 CONSTRUCTION AND OTHER WORK
3.1.1 Worksite Communication
3.1.2 Hazardous Material Exclusions
3.1.3 Unforeseen Hazardous Material
3.2 PRE-OUTAGE COORDINATION MEETING
3.3 CONTROL OF HAZARDOUS ENERGY (LOCKOUT/TAGOUT)
3.4 FALL PROTECTION PROGRAM
3.4.1 Training
3.4.2 Fall Protection Equipment and Systems
3.4.2.1 Additional Personal Fall Protection
3.4.2.2 Personal Fall Protection Harnesses
3.4.3 Flexible Horizontal Lifelines (HLL)
3.4.4 Guardrails and Safety Nets
3.4.5 Rescue and Evacuation Plan and Procedures
3.5 WORK PLATFORMS
3.5.1 Scaffolding
3.5.2 Elevated Aerial Work Platforms (AWP's)
3.6 EQUIPMENT
3.6.1 Material Handling Equipment (MHE)
3.6.2 Load Handling Equipment (LHE)
3.6.3 Machinery and Mechanized Equipment
3.6.4 Explosives
3.7 EXCAVATIONS
3.7.1 Utility Locations
3.7.2 Utility Location Verification
3.7.3 Utilities Within and Under Concrete, Bituminous Asphalt, and
Other Impervious Surfaces
3.8 ELECTRICAL
3.8.1 Conduct of Electrical Work
3.8.2 Qualifications
3.8.3 Grounding
3.8.4 Testing
-- End of Section Table of Contents --
SECTION 01 35 29.10 28 Page 2
SECTION 01 35 29.10 28
GOVERNMENTAL SAFETY REQUIREMENTS
PART 1 GENERAL
1.1 REFERENCES
The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.
AMERICAN SOCIETY OF SAFETY PROFESSIONALS (ASSP)
ASSP A10.34 (2021) Protection of the Public on or Adjacent to Construction Sites
ASSP A10.44 (2020) Control of Energy Sources (Lockout/Tagout) for Construction and Demolition Operations
ASSP Z244.1 (2016) The Control of Hazardous Energy Lockout, Tagout and Alternative Methods
ASSP Z359.0 (2018) Definitions and Nomenclature Used for Fall Protection and Fall Arrest
ASSP Z359.1 (2020) The Fall Protection Code
ASSP Z359.2 (2017) Minimum Requirements for a Comprehensive Managed Fall Protection Program
ASSP Z359.3 (2019) Safety Requirements for Lanyards and Positioning Lanyards
ASSP Z359.4 (2013) Safety Requirements for Assisted-Rescue and Self-Rescue Systems, Subsystems and Components
ASSP Z359.6 (2016) Specifications and Design Requirements for Active Fall Protection Systems
ASSP Z359.7 (2019) Qualification and Verification Testing of Fall Protection Products
ASSP Z359.11 (2021) Safety Requirements for Full Body Harnesses
ASSP Z359.12 (2019) Connecting Components for Personal Fall Arrest Systems
ASSP Z359.13 (2013) Personal Energy Absorbers and Energy Absorbing Lanyards
SECTION 01 35 29.10 28 Page 3
ASSP Z359.14 (2021) Safety Requirements for Self-Retracting Devices for Personal Fall Arrest and Rescue Systems
ASSP Z359.15 (2014) Safety Requirements for Single Anchor Lifelines and Fall Arresters for Personal Fall Arrest Systems
AMERICAN SOCIETY OF MECHANICAL ENGINEERS (ASME)
ASME B30.20 (2018) Below-the-Hook Lifting Devices
ASME B30.22 (2023) Articulating Boom Cranes
ASME B30.26 (2015; R 2020) Rigging Hardware
ASME B30.3 (2020) Tower Cranes
ASME B30.5 (2021) Mobile and Locomotive Cranes
ASME B30.8 (2020) Floating Cranes and Floating Derricks
ASME B30.9 (2018) Slings
ASTM INTERNATIONAL (ASTM)
ASTM F855 (2019) Standard Specifications for Temporary Protective Grounds to Be Used on De-energized Electric Power Lines and Equipment
INSTITUTE OF ELECTRICAL AND ELECTRONICS ENGINEERS (IEEE)
IEEE 1048 (2016) Guide for Protective Grounding of Power Lines
IEEE C2 (2023) National Electrical Safety Code
NATIONAL FIRE PROTECTION ASSOCIATION (NFPA)
NFPA 10 (2022; ERTA 1 2021) Standard for Portable Fire Extinguishers
NFPA 241 (2022) Standard for Safeguarding Construction, Alteration, and Demolition Operations
NFPA 51B (2024) Standard for Fire Prevention During Welding, Cutting, and Other Hot Work
NFPA 70 (2023) National Electrical Code
NFPA 70E (2024) Standard for Electrical Safety in the Workplace
U.S. ARMY CORPS OF ENGINEERS (USACE)
EM 385-1-1 Safety and Occupational Health Requirements
SECTION 01 35 29.10 28 Page 4
The Contractor is responsible for complying with the current edition and all changes posted on the web as of the effective date of this solicitation.
U.S. NATIONAL ARCHIVES AND RECORDS ADMINISTRATION (NARA)
10 CFR 20 Standards for Protection Against Radiation
29 CFR 1910 Occupational Safety and Health Standards
29 CFR 1910.29 (Nov 2016) Fall Protection System and Falling Object Protection - Criteria and Practices
29 CFR 1910.146 Permit-required Confined Spaces
29 CFR 1910.147 Control of Hazardous Energy (Lock Out/Tag Out)
29 CFR 1910.333 Selection and Use of Work Practices
29 CFR 1915 Confined and Enclosed Spaces and Other Dangerous Atmospheres in Shipyard Employment
29 CFR 1915.89 Control of Hazardous Energy (Lockout/Tags-Plus)
29 CFR 1926 Safety and Health Regulations for Construction
29 CFR 1926.1400 Cranes and Derricks in Construction
29 CFR 1926.16 Rules of Construction
29 CFR 1926.450 Scaffolds
29 CFR 1926.500 Fall Protection
CPL 2.100 (1995) Application of the Permit-Required Confined Spaces (PRCS) Standards, 29 CFR 1910.146
1.2 SUBMITTALS
Government approval is required for submittals with a "G" designation;
submittals having an "I" designation are for information only. A designation following the "G" or "I" designation identifies the office that will review the submittal for the Government. Submit the following in accordance with SECTION 01 33 00 SUBMITTAL PROCEDURES:
SD-01 Preconstruction Submittals
Accident Prevention Plan (APP); G, C
Activity Hazard Analysis (AHA); G, C
Safe Clearance; I, C
SECTION 01 35 29.10 28 Page 5
Authorized Individuals; I, C
Standard Lift Plan; G, C
Critical Lift Plan; G, C
Competent Person Qualifications; G, C
Confined Space Entry Plan; G, C
Site Safety And Health Officer (SSHO) Designation Letter; G, C
SD-06 Test Reports
Notifications and Reports; I, C
Accident Reports; I, C
LHE…
This is the start of the file's text. The full file is on GovTribe.