Best Management Practices 137236.docx
DOCX document 21 KB Posted
- Attached to
- Mill Creek Diversion Dam Fish Ladder
- Solicitation number
- W912EF25R0003
About this file
This document outlines Best Management Practices (BMPs) for the construction of a new fish ladder on the Mill Creek flood risk reduction system in Walla Walla County, Washington, to be executed by the U.S. Army Corps of Engineers (USACE) Walla Walla District.
The project, scheduled for 2025-2026, includes construction of a new fish ladder and replacement stilling basin access ramp, with in-water work restricted to June 15-October 31 of both years. Key requirements include contractor preparation of dewatering, environmental protection, fish salvage, and water quality monitoring plans for USACE approval. Specific BMPs mandate fish salvage operations with USACE biologist oversight, smooth concrete finishing, water quality monitoring during construction, and strict fuel handling procedures within 100 feet of the creek, including secondary containment measures and spill response preparations. The new ladder must meet current fish passage criteria to improve fish passage capabilities.
View the file
Other files
Show all 28
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Mill Creek Fish Ladder Best Management Practices U.S. Army Corps of Engineers Walla Walla District Aquatics ID# 137236
September 13, 2024
This list of best management practices was prepared to comply with certain Clean Water Act requirements necessitated by the Washington Department of Ecology (Ecology). Ecology will review and approve this list prior to implementation. Ecology will also review and approve all substantive changes prior to implementation.
The U.S. Army Corps of Engineers (USACE), Walla Walla District proposes to construct a new fish ladder on the Federally owned flood risk reduction portion of Mill Creek in Walla Walla County, Washington. Work would also include construction of a new (replacement) stilling basin access ramp. Construction activities will be conducted in 2025 and 2026, spanning at least two in-water work seasons. All of the in-water work will be conducted between June 15 and October 31 of both years. After placement of the fish ladder cofferdam, work on the ladder would continue outside of the in-water work window.
Best Management Practices:
1. In-water work would be conducted during the extended in-water work window (June 15 to October 31).
2. Work areas would be dewatered. The contractor would prepare a dewatering plan for approval by USACE.
3. The contractor is required to prepare an environmental protection plan for approval by USACE.
4. The contractor is required to prepare a fish salvage plan for approval by USACE.
5. Fish salvage would be conducted prior to and during dewatering.
6. A USACE biologist would be on site for the fish salvage.
7. Concrete would be finished with smooth surfaces and no abrupt edges.
8. The contractor would be required to prepare a water quality monitoring plan for approval by USACE.
9. Water quality monitoring would be performed during in-water work activities.
10. The contractor would prepare a water quality monitoring report after completion of the work.
11. The new ladder would be designed to meet current fish passage criteria and would improve fish passage.
12. In certain instances, refueling or fuel storage near the creek may be unavoidable due to site-specific conditions or unique construction requirements (e.g., continuously operating pumps). The following precautions will be taken when refueling within 100 feet of the creek:
− Adequate amounts of absorbent materials and containment booms will be kept on hand by each construction crew to enable the rapid cleanup of any spills.
− If fuel must be stored near streams for refueling of continuously operating pumps, adequate secondary containment will be employed.
− Secondary containment structures will be lined with suitable plastic sheeting, and provide a containment volume of at least 125 percent of the storage vessel.